Fundamental Challenges and Management Opportunities in Post Disaster Reconstruction Project

Meervat R. Altaie, Marwa Makki Dishar, Ibrahim F. Muhsin
{"title":"Fundamental Challenges and Management Opportunities in Post Disaster Reconstruction Project","authors":"Meervat R. Altaie, Marwa Makki Dishar, Ibrahim F. Muhsin","doi":"10.28991/cej-2023-09-09-05","DOIUrl":null,"url":null,"abstract":"The study examines the root causes of delays that the project manager is unable to resolve or how the decision-maker can identify the best opportunities to get over these obstacles by considering the project constraints defined as the project triangle (cost, time, and quality) in post-disaster reconstruction projects to review the real challenges to overcome these obstacles. The methodology relied on the exploratory description and qualitative data examined. 43 valid questionnaires were distributed to qualified experienced engineers. A list of 49 factors causes was collected from previous international and local studies. A Relative Important Index (RII) is adapted to determine the level of importance of each sub-criterion in the four main criteria (scope, time, cost, and quality) to represent the causing changes in projects. The concluded 13 important factors represent the challenges faced by managers. This process requires active participation in the management role to overcome potential delays that face a great challenge and cause huge waves of displacement that affect the Iraqi economy and lead to social and environmental modifications. Reconstruction projects create jobs, improve the quality of life, and encourage people to return to their homes and rebuild their cities. So, unlocking local potential is the key to sustainable rebuilding in Iraq. Doi: 10.28991/CEJ-2023-09-09-05 Full Text: PDF","PeriodicalId":10233,"journal":{"name":"Civil Engineering Journal","volume":"2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Civil Engineering Journal","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.28991/cej-2023-09-09-05","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The study examines the root causes of delays that the project manager is unable to resolve or how the decision-maker can identify the best opportunities to get over these obstacles by considering the project constraints defined as the project triangle (cost, time, and quality) in post-disaster reconstruction projects to review the real challenges to overcome these obstacles. The methodology relied on the exploratory description and qualitative data examined. 43 valid questionnaires were distributed to qualified experienced engineers. A list of 49 factors causes was collected from previous international and local studies. A Relative Important Index (RII) is adapted to determine the level of importance of each sub-criterion in the four main criteria (scope, time, cost, and quality) to represent the causing changes in projects. The concluded 13 important factors represent the challenges faced by managers. This process requires active participation in the management role to overcome potential delays that face a great challenge and cause huge waves of displacement that affect the Iraqi economy and lead to social and environmental modifications. Reconstruction projects create jobs, improve the quality of life, and encourage people to return to their homes and rebuild their cities. So, unlocking local potential is the key to sustainable rebuilding in Iraq. Doi: 10.28991/CEJ-2023-09-09-05 Full Text: PDF
灾后重建面临的基本挑战与管理机遇
该研究考察了项目经理无法解决的延迟的根本原因,或者决策者如何通过考虑灾后重建项目中定义为项目三角的项目约束(成本、时间和质量)来确定克服这些障碍的最佳机会,以审查克服这些障碍的真正挑战。该方法依赖于探索性描述和检验的定性数据。向合格的经验工程师发放有效问卷43份。从以前的国际和本地研究中收集了49个因素的清单。相对重要指数(RII)用于确定四个主要标准(范围、时间、成本和质量)中每个子标准的重要程度,以表示导致项目变化的原因。总结的13个重要因素代表了管理者面临的挑战。这一进程需要积极参与管理作用,以克服可能出现的延误,这些延误将面临巨大挑战,并造成影响伊拉克经济并导致社会和环境变化的巨大流离失所浪潮。重建项目创造就业机会,提高生活质量,并鼓励人们返回家园,重建城市。因此,释放当地潜力是伊拉克可持续重建的关键。Doi: 10.28991/CEJ-2023-09-09-05全文:PDF
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信