TIME SCHEDULING AND COST OF THE INDONESIAN NAVY SHIP DEVELOPMENT PROJECT USING NETWORK DIAGRAM AND EARNED VALUE METHOD (EVM) (CASE STUDY OF FAST MISSILE BOAT DEVELOPMENT)

JOURNAL ASRO Pub Date : 2018-11-29 DOI:10.37875/asro.v9i2.80
Arica Dwi Susanto, S. Suparno, O. S. Suharyo, A. Ahmadi
{"title":"TIME SCHEDULING AND COST OF THE INDONESIAN NAVY SHIP DEVELOPMENT PROJECT USING NETWORK DIAGRAM AND EARNED VALUE METHOD (EVM) (CASE STUDY OF FAST MISSILE BOAT DEVELOPMENT)","authors":"Arica Dwi Susanto, S. Suparno, O. S. Suharyo, A. Ahmadi","doi":"10.37875/asro.v9i2.80","DOIUrl":null,"url":null,"abstract":"Missile Boat is one of Indonesian Navy Warship (KCR-60) which has a length of 60 meters and made domestically by Indonesian people at the PT. X in Surabaya. Time delay and cost overruns are the problems in the Missile Boat construction project (KCR-60). The purpose of this research was to schedule the time and cost of the project so that it can be completed on time and there is no swelling of costs for the implementation of the construction of the Missile Boats (KCR-60). The scheduling method used in this study was Precedence Diagram Method (PDM) on Network Diagram and Earned Value Method (EVM). Precedence Diagram Method (PDM) was used for scheduling the project time and showing the critical trajectory of project activities along with the acceleration time (Crashing Project) while Earned Value Method (EVM)  was used to determine the costs and time performance and the factors that cause delays or progress of the project. The results showed that the project schedule had 13 activities that had a zero slack or critical activities which were in activities 1, 2, 3, 4, 5, 6, 16, 18, 21, 23, 26, 27, 28. There acceleration of time (Crashing Project) by adding hours of work or overtime for 1 hour every day to 21 activities (1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19) will accelerate and reduce the duration of project completion, which was originally 414 days from the completion of the actual work of implementation to 363 days, thus the difference of effectiveness was 51 days (more effective). Meanwhile, for cost efficiency, based on the analysis of the real cost of project implementation, the amount of Rp. 20.407,094,998, - became Rp. 18,410,738,982, thus it became more efficient by Rp. 2,470,548,998, -","PeriodicalId":356564,"journal":{"name":"JOURNAL ASRO","volume":"154 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-11-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"JOURNAL ASRO","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.37875/asro.v9i2.80","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

Missile Boat is one of Indonesian Navy Warship (KCR-60) which has a length of 60 meters and made domestically by Indonesian people at the PT. X in Surabaya. Time delay and cost overruns are the problems in the Missile Boat construction project (KCR-60). The purpose of this research was to schedule the time and cost of the project so that it can be completed on time and there is no swelling of costs for the implementation of the construction of the Missile Boats (KCR-60). The scheduling method used in this study was Precedence Diagram Method (PDM) on Network Diagram and Earned Value Method (EVM). Precedence Diagram Method (PDM) was used for scheduling the project time and showing the critical trajectory of project activities along with the acceleration time (Crashing Project) while Earned Value Method (EVM)  was used to determine the costs and time performance and the factors that cause delays or progress of the project. The results showed that the project schedule had 13 activities that had a zero slack or critical activities which were in activities 1, 2, 3, 4, 5, 6, 16, 18, 21, 23, 26, 27, 28. There acceleration of time (Crashing Project) by adding hours of work or overtime for 1 hour every day to 21 activities (1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19) will accelerate and reduce the duration of project completion, which was originally 414 days from the completion of the actual work of implementation to 363 days, thus the difference of effectiveness was 51 days (more effective). Meanwhile, for cost efficiency, based on the analysis of the real cost of project implementation, the amount of Rp. 20.407,094,998, - became Rp. 18,410,738,982, thus it became more efficient by Rp. 2,470,548,998, -
基于网络图和挣值法(evm)的印尼海军舰艇开发项目的时间安排和成本(以快速导弹艇开发为例)
导弹艇是印度尼西亚海军军舰(KCR-60)的一艘,长度为60米,由印度尼西亚人在泗水的PT. X国内制造。KCR-60导弹艇建造项目存在工期延误和成本超支等问题。这项研究的目的是安排项目的时间和成本,以便它可以按时完成,并且没有实施建造导弹艇(KCR-60)的成本膨胀。本研究采用的调度方法为网络图优先图法(PDM)和挣值法(EVM)。优先图法(PDM)用于规划项目时间,并显示项目活动的关键轨迹以及加速时间(崩溃项目),而挣值法(EVM)用于确定成本和时间绩效以及导致项目延迟或进度的因素。结果表明,项目进度有13个活动为零松弛或关键活动,分别为活动1、2、3、4、5、6、16、18、21、23、26、27、28。在21个活动(1、2、3、4、5、6、7、8、9、10、11、12、13、14、15、16、17、18、19)中增加工作时数或每天加班1小时的时间加速(crash Project),将加速并缩短项目完成时间,从完成实际实施工作的414天缩短到363天,因此效果差51天(更有效)。同时,在成本效率方面,根据对项目实施实际成本的分析,将Rp. 20.407,094,998, -的金额变为Rp. 18,410,738,982,从而提高了Rp. 2,470,548,998, -的效率
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信