APPLICATION OF ADVANCED JET GROUTING SOLUTIONS FOR THE CONSTRUCTION OF HYDROELECTRIC POWER PLANTS

Davorin Lesnik, A. Zöhrer, M. Mešić
{"title":"APPLICATION OF ADVANCED JET GROUTING SOLUTIONS FOR THE CONSTRUCTION OF HYDROELECTRIC POWER PLANTS","authors":"Davorin Lesnik, A. Zöhrer, M. Mešić","doi":"10.35123/geo-expo_2022_2","DOIUrl":null,"url":null,"abstract":"The construction of hydroelectric power plants typically requires the execution of deep construction pits close to or even inside of rivers. The paper describes geotechnical challenges and solutions of such projects on the basis of the expansion of the water power plant in Kirchbichl, Austria. This power plant is in operation since the late 1940s and was upgraded with an additional power house as well as a new floodwater relief channel. Therefore two approx. 100m long construction pits were built bordering the existing power plant. Differences in water levels of up to 20m in combination with high permeable soil layers required the execution of water tight and stiff retaining walls and high as well as deep seated sealing slabs. Especially the areas next to the existing structure were critical for the success, as the more than 70 years old building is very sensible to deformations. Moreover, the execution of piles and jet grouting columns had to pass through the former excavation, which was backfilled using very heterogenic material. Thus, various geotechnical products were applied, including jet grouting, bored piles, micro piles and strand anchors. The paper points out the key challenges of such projects, ranging from design stage, execution on site till quality control and documentation. It also addresses the risks faced during the various project phases and describes proper approaches how to mitigate them.","PeriodicalId":203089,"journal":{"name":"ZBORNIK RADOVA GEO-EXPO 2022","volume":"8 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-10-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ZBORNIK RADOVA GEO-EXPO 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.35123/geo-expo_2022_2","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The construction of hydroelectric power plants typically requires the execution of deep construction pits close to or even inside of rivers. The paper describes geotechnical challenges and solutions of such projects on the basis of the expansion of the water power plant in Kirchbichl, Austria. This power plant is in operation since the late 1940s and was upgraded with an additional power house as well as a new floodwater relief channel. Therefore two approx. 100m long construction pits were built bordering the existing power plant. Differences in water levels of up to 20m in combination with high permeable soil layers required the execution of water tight and stiff retaining walls and high as well as deep seated sealing slabs. Especially the areas next to the existing structure were critical for the success, as the more than 70 years old building is very sensible to deformations. Moreover, the execution of piles and jet grouting columns had to pass through the former excavation, which was backfilled using very heterogenic material. Thus, various geotechnical products were applied, including jet grouting, bored piles, micro piles and strand anchors. The paper points out the key challenges of such projects, ranging from design stage, execution on site till quality control and documentation. It also addresses the risks faced during the various project phases and describes proper approaches how to mitigate them.
先进喷射注浆解决方案在水电站建设中的应用
水力发电厂的建设通常需要在靠近河流甚至在河流内部进行深基坑施工。本文以奥地利Kirchbichl水电厂扩建工程为例,介绍了此类工程的岩土工程挑战和解决方案。该发电厂自20世纪40年代末开始运行,并进行了升级,增加了一个发电厂和一个新的泄洪通道。所以两个近似。在现有电厂附近修建了100米长的施工坑。水位差达20米,加上高渗透性土层,需要实施防水和刚性挡土墙,以及高嵌和深嵌的止水板。特别是现有结构附近的区域对成功至关重要,因为这座70多年的建筑对变形非常敏感。此外,桩和喷射注浆柱的施工必须穿过原开挖,而原开挖采用非均质材料进行回填。因此,采用了各种岩土工程产品,包括喷射注浆、钻孔灌注桩、微桩和锚杆。本文指出了此类工程从设计阶段、现场施工到质量控制和文件编制的主要挑战。它还讨论了在各个项目阶段面临的风险,并描述了如何减轻风险的适当方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信