Cost Reduction of Truss Type Roof Truss Installation

Weerayut Wongdee, Weerakarj Dokchan
{"title":"Cost Reduction of Truss Type Roof Truss Installation","authors":"Weerayut Wongdee, Weerakarj Dokchan","doi":"10.14416/j.ted.2023.02.006","DOIUrl":null,"url":null,"abstract":"The objectives of this research were to: 1) to reduced costs incur in the installation of reducing of trusses installing, 2) to improved work processes to be more efficient y applying Lean's approach In practice, MUDA theory and 7 WASTE were overproduction, waiting, unnecessary movement (transporting), unprofitable work (inappropriate processing), excessive inventory (unnecessary inventory), unnecessary motions, and defect in order to work efficiently. Then compared the information before and after revision. The results of this study indicated that: 1) after studying, analyzing and improving the working process, the cost of installing the roof truss per area was reduced (Unit per square meters). Project I had installation cost for truss type roof trusses 194.43 baht per square meters. Project II had installation cost for truss type roof trusses 89.91 baht per square meters. It showed that cost was reduced for 104.52 baht per square meters, accounting for 53.76 percentage. Or calculated as reduced cost from Project I to 74,780 baht, accounting for 30.3 percentage. 2) Completed time for installation was reduced for 795 minutes or 1.66 days, accounting for 25.4 percentage. Consequently, work was completed successfully within 4.86 days as planned (5 days) without overtime work. This way could reduce cost when comparing the ratio of the area of project II. The area was greater than 643.91 square meters, accounting for 33.66 percentage. In addition, the weight of the steel frame was greater than 13 tons, accounting for 34.21 percentage. Even though it was using to lift the building floor 72 times, it could be reduced waste. It could be actually reduced the time of installing of trusses it so true. It has resulted in a lot of efficiency and productivity within the organization. Whether it was about a faster time, quality inspection of workpieces before installation, collecting details of the workpieces, editing workpieces conveniently, quickly and it will have also reduced the risk of working at heights.","PeriodicalId":120890,"journal":{"name":"Journal Of Technical Education Development","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-03-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal Of Technical Education Development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.14416/j.ted.2023.02.006","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The objectives of this research were to: 1) to reduced costs incur in the installation of reducing of trusses installing, 2) to improved work processes to be more efficient y applying Lean's approach In practice, MUDA theory and 7 WASTE were overproduction, waiting, unnecessary movement (transporting), unprofitable work (inappropriate processing), excessive inventory (unnecessary inventory), unnecessary motions, and defect in order to work efficiently. Then compared the information before and after revision. The results of this study indicated that: 1) after studying, analyzing and improving the working process, the cost of installing the roof truss per area was reduced (Unit per square meters). Project I had installation cost for truss type roof trusses 194.43 baht per square meters. Project II had installation cost for truss type roof trusses 89.91 baht per square meters. It showed that cost was reduced for 104.52 baht per square meters, accounting for 53.76 percentage. Or calculated as reduced cost from Project I to 74,780 baht, accounting for 30.3 percentage. 2) Completed time for installation was reduced for 795 minutes or 1.66 days, accounting for 25.4 percentage. Consequently, work was completed successfully within 4.86 days as planned (5 days) without overtime work. This way could reduce cost when comparing the ratio of the area of project II. The area was greater than 643.91 square meters, accounting for 33.66 percentage. In addition, the weight of the steel frame was greater than 13 tons, accounting for 34.21 percentage. Even though it was using to lift the building floor 72 times, it could be reduced waste. It could be actually reduced the time of installing of trusses it so true. It has resulted in a lot of efficiency and productivity within the organization. Whether it was about a faster time, quality inspection of workpieces before installation, collecting details of the workpieces, editing workpieces conveniently, quickly and it will have also reduced the risk of working at heights.
降低桁架式屋架安装成本
本研究的目的是:1)降低安装或减少桁架安装的成本,2)通过应用精益方法改善工作流程以提高效率。在实践中,MUDA理论和7浪费是生产过剩、等待、不必要的移动(运输)、无利可图的工作(不适当的加工)、过多的库存(不必要的库存)、不必要的运动和缺陷,以提高工作效率。然后比较修改前后的信息。研究结果表明:1)通过对工作流程的研究、分析和改进,降低了单位面积屋架安装成本(单位/平方米)。项目一桁架式屋架安装费用为每平方米194.43泰铢。二期工程桁架式屋架安装费用为89.91泰铢/平方米。结果显示,每平方米成本降低了104.52泰铢,占53.76%。或按项目一降低成本74,780泰铢计算,占30.3%。2)安装完成时间缩短795分钟,缩短1.66天,占25.4%。因此,工作在4.86天内(5天)顺利完成,没有加班。这种方式可以在比较二期工程的面积比例时降低成本。面积大于643.91平方米,占33.66%。另外,钢架自重大于13吨,占比34.21%。虽然它要用72次才能把楼抬起来,但它可以减少浪费。它实际上可以减少安装桁架的时间,这是真的。它在组织内带来了很多效率和生产力。无论是关于更快的时间,在安装前对工件进行质量检查,收集工件的细节,方便,快速地编辑工件,它也降低了高空作业的风险。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信