Milestone Planning: A Participatory and Visual Approach

Eduardo Miranda
{"title":"Milestone Planning: A Participatory and Visual Approach","authors":"Eduardo Miranda","doi":"10.19255/JMPM02003","DOIUrl":null,"url":null,"abstract":"This paper introduces a participatory and visual approach to milestone planning called the Visual Milestone Planning (VMP) Method. VMP promotes involvement and commitment, through the reification of the planning artifacts and their direct manipulation by team members who collectively create the plan. Once a project scope is defined via a work breakdown structure and relevant milestones identified, a novel construct called the milestone planning matrix is used to systematically and visually capture dependencies among milestones and map WBS elements to the milestones they help realize. The milestones due dates are later determined by accommodating sticky notes representing the work to be done on a resource and time scaled milestone scheduling canvas. The method is applicable to traditional as well as to agile projects.","PeriodicalId":320094,"journal":{"name":"The Journal of Modern Project Management","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"The Journal of Modern Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.19255/JMPM02003","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

Abstract

This paper introduces a participatory and visual approach to milestone planning called the Visual Milestone Planning (VMP) Method. VMP promotes involvement and commitment, through the reification of the planning artifacts and their direct manipulation by team members who collectively create the plan. Once a project scope is defined via a work breakdown structure and relevant milestones identified, a novel construct called the milestone planning matrix is used to systematically and visually capture dependencies among milestones and map WBS elements to the milestones they help realize. The milestones due dates are later determined by accommodating sticky notes representing the work to be done on a resource and time scaled milestone scheduling canvas. The method is applicable to traditional as well as to agile projects.
里程碑规划:参与式和可视化方法
本文介绍了一种参与式和可视化的里程碑规划方法,称为可视化里程碑规划(VMP)方法。VMP通过计划工件的具体化和团队成员共同创建计划的直接操作来促进参与和承诺。一旦通过工作分解结构定义了项目范围,并确定了相关的里程碑,就可以使用一个称为里程碑计划矩阵的新结构来系统地、可视化地捕获里程碑之间的依赖关系,并将WBS元素映射到它们帮助实现的里程碑。里程碑的截止日期稍后通过在资源和时间尺度的里程碑调度画布上容纳代表要完成的工作的便利贴来确定。该方法既适用于传统项目,也适用于敏捷项目。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信