Project monitoring by dynamic statistical control charts

G. Galante, C. M. L. Fata, G. Passannanti
{"title":"Project monitoring by dynamic statistical control charts","authors":"G. Galante, C. M. L. Fata, G. Passannanti","doi":"10.19255/JMPM02106","DOIUrl":null,"url":null,"abstract":"Project monitoring activities are fundamental to assure a timely identification of unacceptable deviations from the baseline, so that corrective actions may be taken to bring the project back in line with its objectives. In regard to this, the most used approach is the Earned Value Management (EVM) technique whose traditional metrics do not allow to discriminate between acceptable and unacceptable performance variations. With this recognition, a statistical approach based on the use of dynamic Shewhart’s and CUmulative SUM (CUSUM) control charts is proposed in the present paper to deal with the project monitoring problem. Its efficaciousness is demonstrated by its application to a set of real projects.","PeriodicalId":320094,"journal":{"name":"The Journal of Modern Project Management","volume":"30 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-12-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"The Journal of Modern Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.19255/JMPM02106","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Project monitoring activities are fundamental to assure a timely identification of unacceptable deviations from the baseline, so that corrective actions may be taken to bring the project back in line with its objectives. In regard to this, the most used approach is the Earned Value Management (EVM) technique whose traditional metrics do not allow to discriminate between acceptable and unacceptable performance variations. With this recognition, a statistical approach based on the use of dynamic Shewhart’s and CUmulative SUM (CUSUM) control charts is proposed in the present paper to deal with the project monitoring problem. Its efficaciousness is demonstrated by its application to a set of real projects.
项目监控采用动态统计控制图
项目监测活动是确保及时识别不可接受的基线偏差的基础,以便采取纠正行动,使项目回到与其目标一致的水平。关于这一点,最常用的方法是挣值管理(EVM)技术,其传统度量不允许区分可接受和不可接受的性能变化。基于这一认识,本文提出了一种基于动态Shewhart和累积SUM (CUSUM)控制图的统计方法来处理项目监控问题。通过对一组实际工程的应用,证明了该方法的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信