Analytical Calculation of Electric and Magnetic Fields Near a Proposed 132kV Line with Constrained Right of Way - Kenyan Case Study

Julius Ndirangu, Peter Kimemia, J. Nderu, Raphael Ndolo, G. Irungu
{"title":"Analytical Calculation of Electric and Magnetic Fields Near a Proposed 132kV Line with Constrained Right of Way - Kenyan Case Study","authors":"Julius Ndirangu, Peter Kimemia, J. Nderu, Raphael Ndolo, G. Irungu","doi":"10.1109/ICHVET.2019.8724201","DOIUrl":null,"url":null,"abstract":"A 6.5km 132kV overhead line is proposed to link a Bulk supply substation with a proposed 132/33kV,2×45MVA substation in a coastal island city in Kenya. The proposed line is to be constructed in steel monopoles and will have 33kV overhead lines below the 132kV single circuit line. The recommended right of way (wayleave) for 132kV single circuit line is 30m as per Kenya Power and Lighting Company (KPLC) standards. However, since this particular line passes through highly constructed area in a city, the available right of way was constrained to 10m i.e, 5m on each side measured from the center of the line. From site survey, 3 specific points of interest were also identified where already constructed storey buildings were found just beyond the edge of the right of way. The objective of this paper is to do analytical calculations of the electric and magnetic fields anticipated to be experienced at 1m above the ground at the edge of the 10m right of way of the proposed 132kV line, as well as at the top of the storey buildings at the specific points of interest identified during site visit. The calculations were done using the parameters of the already proposed steel monopoles whose heights had been determined based on terrain and clearance requirements only. Since the electric field values obtained were found to be beyond the recommended limits by International Commission on Non Ionizing Radiation Protection (ICNIRP) 2010 guidelines, recommendations on mitigation measures to ensure compliance are proposed and recalculations were carried out to demonstrate adequacy of the recommendations to ensure compliance.","PeriodicalId":165193,"journal":{"name":"2019 International Conference on High Voltage Engineering and Technology (ICHVET)","volume":"55 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-02-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2019 International Conference on High Voltage Engineering and Technology (ICHVET)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICHVET.2019.8724201","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

A 6.5km 132kV overhead line is proposed to link a Bulk supply substation with a proposed 132/33kV,2×45MVA substation in a coastal island city in Kenya. The proposed line is to be constructed in steel monopoles and will have 33kV overhead lines below the 132kV single circuit line. The recommended right of way (wayleave) for 132kV single circuit line is 30m as per Kenya Power and Lighting Company (KPLC) standards. However, since this particular line passes through highly constructed area in a city, the available right of way was constrained to 10m i.e, 5m on each side measured from the center of the line. From site survey, 3 specific points of interest were also identified where already constructed storey buildings were found just beyond the edge of the right of way. The objective of this paper is to do analytical calculations of the electric and magnetic fields anticipated to be experienced at 1m above the ground at the edge of the 10m right of way of the proposed 132kV line, as well as at the top of the storey buildings at the specific points of interest identified during site visit. The calculations were done using the parameters of the already proposed steel monopoles whose heights had been determined based on terrain and clearance requirements only. Since the electric field values obtained were found to be beyond the recommended limits by International Commission on Non Ionizing Radiation Protection (ICNIRP) 2010 guidelines, recommendations on mitigation measures to ensure compliance are proposed and recalculations were carried out to demonstrate adequacy of the recommendations to ensure compliance.
具有受限通行权的拟议132kV线路附近电场和磁场的解析计算——肯尼亚案例研究
拟建一条长6.5公里的132千伏架空线路,将肯尼亚沿海岛屿城市的大容量供电变电站与拟建的132/33千伏2×45MVA变电站连接起来。拟议的线路将采用钢单极管结构,并将在132kV单回路线路下方安装33kV架空线路。根据肯尼亚电力和照明公司(KPLC)的标准,建议132kV单回路线路的通行权(wayleave)为30m。然而,由于这条特殊的线路经过城市中高度建设的区域,可用的路权被限制为10米,即从线路中心开始每边5米。从现场调查中,还确定了3个特定的兴趣点,在这些地方发现了已经建成的多层建筑,就在路权边缘之外。本文的目的是对拟议的132kV线路10米路权边缘距离地面1米处预计会经历的电场和磁场进行分析计算,以及在现场访问期间确定的特定兴趣点的多层建筑顶部。计算是使用已经提出的钢单极子的参数进行的,其高度仅根据地形和间隙要求确定。由于发现获得的电场值超出了国际非电离辐射防护委员会(ICNIRP) 2010年准则所建议的限值,因此提出了关于确保遵守的缓解措施的建议,并进行了重新计算,以证明确保遵守的建议的充分性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信