Investigation and replacement of bus partial differential zones in a ring bus application at centerpoint energy

D. Sevcik, H.J. Do Carmo
{"title":"Investigation and replacement of bus partial differential zones in a ring bus application at centerpoint energy","authors":"D. Sevcik, H.J. Do Carmo","doi":"10.1109/CPRE.2005.1430441","DOIUrl":null,"url":null,"abstract":"This paper is based on the actual occurrence of the loss of service to all load at a CenterPoint Energy substation that serves three metropolitan underground 12.47 kV distribution networks. Subsequent investigation determined that the loss of service was caused by the maloperation of multiple, 69 kV bus electromechanical instantaneous overcurrent partial differential relay zones of protection for a fault in the 69 kV ring bus. Modeling and simulation substantiated that the maloperation occurred due to current transformer saturation in the presence of high DC offset current during a second unsuccessful automatic reclose attempt after all protection had operated properly for the initial fault and for the first unsuccessful automatic reclose attempt This event occurred in June of 2004 and a temporary fix was implemented shortly there after. Transient testing of the selected replacement protection system was conducted. The permanent solution is scheduled to be complete in early 2005.","PeriodicalId":395312,"journal":{"name":"58th Annual Conference for Protective Relay Engineers, 2005.","volume":"40 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2005-04-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"58th Annual Conference for Protective Relay Engineers, 2005.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CPRE.2005.1430441","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

This paper is based on the actual occurrence of the loss of service to all load at a CenterPoint Energy substation that serves three metropolitan underground 12.47 kV distribution networks. Subsequent investigation determined that the loss of service was caused by the maloperation of multiple, 69 kV bus electromechanical instantaneous overcurrent partial differential relay zones of protection for a fault in the 69 kV ring bus. Modeling and simulation substantiated that the maloperation occurred due to current transformer saturation in the presence of high DC offset current during a second unsuccessful automatic reclose attempt after all protection had operated properly for the initial fault and for the first unsuccessful automatic reclose attempt This event occurred in June of 2004 and a temporary fix was implemented shortly there after. Transient testing of the selected replacement protection system was conducted. The permanent solution is scheduled to be complete in early 2005.
在中心点能量的环形母线应用中母线偏微分区的调查和替换
本文是基于一个中心点能源变电站的实际情况,该变电站为三个大都市地下12.47千伏配电网络服务。随后的调查确定,服务损失是由多个误操作造成的,69千伏母线机电瞬时过流部分差动继电器区域保护69千伏环形母线的故障。建模和仿真证实,在所有保护措施对初始故障和第一次自动合闸尝试失败后,在第二次自动合闸尝试失败时,由于存在高直流偏置电流的电流互感器饱和而发生误操作。该事件发生在2004年6月,此后不久实施了临时修复。对选定的替代保护系统进行了暂态试验。永久解决方案定于2005年初完成。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信