Rock Load Transfer Mechanisms and Interactions at Cavern Junctions

A. Seto, A. Kwong, Joel Y F Wong
{"title":"Rock Load Transfer Mechanisms and Interactions at Cavern Junctions","authors":"A. Seto, A. Kwong, Joel Y F Wong","doi":"10.21467/proceedings.133.39","DOIUrl":null,"url":null,"abstract":"Rock at depth is subjected to stresses resulting from the weight of the overlying strata. When an underground opening is excavated, the stress field in this rock mass is locally disrupted and induces a new set of stresses surrounding the new opening. At tunnel and cavern associated junctions, the re-distributed stresses will alter the stress fields of adjacent openings. For example, loadings from a taller cavern will be transferred through the rock arch and concentrated as additional vertical stress above the crown of the shorter cavern. The load transferring mechanisms in this paper refer to the construction of the cavern complex, which involves developing new sewage treatment works in caverns to be constructed at Nui Po Shan, A Kung Kok, Sha Tin, to replace the existing Sha Tin Sewage Treatment Works (STSTW). Upon functioning of the new STSTW, the existing site will be released for other uses beneficial to the development of Hong Kong.The works at the new STSTW occupies about 14 hectares in the area comprising of Main Access Tunnel (MAT), Secondary Access Tunnel (SAT), fifteen Process Caverns, the Main Driveway (MD), Secondary Driveway (SD), four Branch Driveways, Ventilation Shaft, Ventilation Adit, two Effluent Pipelines, and lining and portal structure of MAT and SAT. These structures are excavated mainly by the drill-and-blast method in hard rock, with rock covering more than half of the excavation span/height above the crown. They are designed as drained and are primarily supported by the rock arch, reinforced by systematic permanent rock bolts with permanent sprayed concrete. In addition, drained cast-in-situ reinforced concrete lining is proposed for poor ground conditions.For the proposed cavern complex, most of the Branch Driveways are taller than Process Caverns and MD/SD except for the middle cavern for sludge treatment (STC) purposes. STC's design span and height are 30 m and 35 m, respectively. Therefore, additional stresses are expected to transfer from Branch Driveways and STC to other Process Caverns and MD/SD. Numerical modeling using finite element methods has been established, where two-dimensional design models and three-dimensional verification models in accordance with the varying excavation profiles, overburden depth, and rock mass quality have been carried out. By observing the stress redistribution from the taller STC to other Process Caverns, the two-dimensional and three-dimensional models aim to study the stress concentration zones and the extent of the influence zone at tunnel and cavern associated junctions. The maximum deformation is located along with the crown of STC and intruding corners at the associated junctions, in which the Process Caverns with the largest excavation span and height are proposed.This paper provided a detailed description of the geology, cavern complex geometrical arrangements, rock mass properties for the modeling, methodology of modeling, and mechanism of load redistribution observed at the junctions.","PeriodicalId":379153,"journal":{"name":"Proceedings of The HKIE Geotechnical Division 42nd Annual Seminar: A New Era of Metropolis and Infrastructure Developments in Hong Kong, Challenges and Opportunities to Geotechnical Engineering","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of The HKIE Geotechnical Division 42nd Annual Seminar: A New Era of Metropolis and Infrastructure Developments in Hong Kong, Challenges and Opportunities to Geotechnical Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21467/proceedings.133.39","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Rock at depth is subjected to stresses resulting from the weight of the overlying strata. When an underground opening is excavated, the stress field in this rock mass is locally disrupted and induces a new set of stresses surrounding the new opening. At tunnel and cavern associated junctions, the re-distributed stresses will alter the stress fields of adjacent openings. For example, loadings from a taller cavern will be transferred through the rock arch and concentrated as additional vertical stress above the crown of the shorter cavern. The load transferring mechanisms in this paper refer to the construction of the cavern complex, which involves developing new sewage treatment works in caverns to be constructed at Nui Po Shan, A Kung Kok, Sha Tin, to replace the existing Sha Tin Sewage Treatment Works (STSTW). Upon functioning of the new STSTW, the existing site will be released for other uses beneficial to the development of Hong Kong.The works at the new STSTW occupies about 14 hectares in the area comprising of Main Access Tunnel (MAT), Secondary Access Tunnel (SAT), fifteen Process Caverns, the Main Driveway (MD), Secondary Driveway (SD), four Branch Driveways, Ventilation Shaft, Ventilation Adit, two Effluent Pipelines, and lining and portal structure of MAT and SAT. These structures are excavated mainly by the drill-and-blast method in hard rock, with rock covering more than half of the excavation span/height above the crown. They are designed as drained and are primarily supported by the rock arch, reinforced by systematic permanent rock bolts with permanent sprayed concrete. In addition, drained cast-in-situ reinforced concrete lining is proposed for poor ground conditions.For the proposed cavern complex, most of the Branch Driveways are taller than Process Caverns and MD/SD except for the middle cavern for sludge treatment (STC) purposes. STC's design span and height are 30 m and 35 m, respectively. Therefore, additional stresses are expected to transfer from Branch Driveways and STC to other Process Caverns and MD/SD. Numerical modeling using finite element methods has been established, where two-dimensional design models and three-dimensional verification models in accordance with the varying excavation profiles, overburden depth, and rock mass quality have been carried out. By observing the stress redistribution from the taller STC to other Process Caverns, the two-dimensional and three-dimensional models aim to study the stress concentration zones and the extent of the influence zone at tunnel and cavern associated junctions. The maximum deformation is located along with the crown of STC and intruding corners at the associated junctions, in which the Process Caverns with the largest excavation span and height are proposed.This paper provided a detailed description of the geology, cavern complex geometrical arrangements, rock mass properties for the modeling, methodology of modeling, and mechanism of load redistribution observed at the junctions.
岩洞连接处岩石荷载传递机制及相互作用
深处的岩石承受着由上覆岩层的重量所产生的应力。当地下开孔开挖时,该岩体的应力场局部被破坏,并在新开孔周围诱发一组新的应力。在隧道与洞室的连接处,应力的重新分布将改变相邻洞口的应力场。例如,来自较高洞穴的载荷将通过岩石拱传递,并集中为较短洞穴顶部上方的附加垂直应力。本文件所述的负荷转移机制是指建造洞穴综合设施,即在沙田阿公角瑞埔山的洞穴内发展新的污水处理厂,以取代现有的沙田污水处理厂。新污水处理厂运作后,现有的土地将会作其他对香港发展有益的用途。新污水处理厂的工程占地约14公顷,包括主出入口隧道、次出入口隧道、15个工艺洞、主车道、次车道、4个支路、通风竖井、通风坑道、两条污水管道,以及主车道和副车道的衬砌和入口结构。这些结构主要采用钻爆法在硬岩石中挖掘。岩石覆盖了超过一半的开挖跨度/顶部高度。它们被设计为排水,主要由岩拱支撑,由系统的永久岩石螺栓和永久喷射混凝土加固。此外,针对地基条件较差的情况,建议采用排水现浇钢筋混凝土衬砌。就拟议的溶洞建筑群而言,除用作污泥处理用途的中间溶洞外,大部分支路的高度均高于过程溶洞和MD/SD。STC的设计跨度为30m,设计高度为35m。因此,额外的压力预计会从分支车道和STC转移到其他工艺洞穴和MD/SD。建立了基于有限元方法的数值模拟,根据不同开挖剖面、覆盖层深度和岩体质量建立了二维设计模型和三维验证模型。通过观察较高的过程洞室向其他过程洞室的应力分布情况,建立二维和三维模型,研究隧道与洞室相关连接处的应力集中区及其影响范围。变形最大的位置位于STC的顶部和相邻连接处的侵入角处,在此位置提出了开挖跨度和高度最大的过程洞室。本文详细介绍了洞室的地质情况、洞室复杂的几何布置、建模的岩体性质、建模方法以及在连接处观察到的荷载重分布机制。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信