{"title":"Well Decommissioning Campaign in Block SK305, Sarawak, Malaysia 7 Production Wells and 9 Suspended Subsea Mud Line Suspension Exploration Wells","authors":"M. H. Yusof, M. I. M. Ros, Mohammad Annas Omar","doi":"10.2118/194054-MS","DOIUrl":null,"url":null,"abstract":"\n This paper will discuss the Case study of well decommissioning campaign in block SK 305, Sarawak, Malaysia which had completed in October 2017. All the seven (7) production wells from 2 platforms and nine (9) suspended subsea (with mudline suspension system, MLS) exploration wells have been successfully abandoned, safely and with very optimum cost.\n Many challenges were encountered during planning and execution of the well decommissioning campaign (i.e. well integrity - leaking well, high annulus pressure, facilities integrity and complexity, shallow gas, pipelines and old rig footprint issues, handling tubulars with marine growth, grout cement - dual cemented casing, buried well, etc), and the main challenges as a company is to execute the operation safely with optimum cost, whilst ensuring safe barrier being installed for long term well isolation.\n This paper will present: Well Decommissioning Planning, Preparation and Execution at Block SK 305 (Production and suspended Exploration Wells)Major Challenges and Lesson LearntOptimization, Technologies, and Best PracticesCAPROCK P&A Method Application\n This paper sharing session will help other operators to understand better on how well decommissioning can be planned and executed, as well as improvement that can be performed in the future.","PeriodicalId":437819,"journal":{"name":"Day 1 Mon, December 03, 2018","volume":"8 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-11-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, December 03, 2018","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/194054-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
Abstract
This paper will discuss the Case study of well decommissioning campaign in block SK 305, Sarawak, Malaysia which had completed in October 2017. All the seven (7) production wells from 2 platforms and nine (9) suspended subsea (with mudline suspension system, MLS) exploration wells have been successfully abandoned, safely and with very optimum cost.
Many challenges were encountered during planning and execution of the well decommissioning campaign (i.e. well integrity - leaking well, high annulus pressure, facilities integrity and complexity, shallow gas, pipelines and old rig footprint issues, handling tubulars with marine growth, grout cement - dual cemented casing, buried well, etc), and the main challenges as a company is to execute the operation safely with optimum cost, whilst ensuring safe barrier being installed for long term well isolation.
This paper will present: Well Decommissioning Planning, Preparation and Execution at Block SK 305 (Production and suspended Exploration Wells)Major Challenges and Lesson LearntOptimization, Technologies, and Best PracticesCAPROCK P&A Method Application
This paper sharing session will help other operators to understand better on how well decommissioning can be planned and executed, as well as improvement that can be performed in the future.
本文将讨论2017年10月完成的马来西亚Sarawak SK 305区块油井停产活动的案例研究。来自2个平台的所有7口生产井和9口悬挂式海底探井(采用泥线悬挂系统,MLS)都已成功废弃,安全且成本非常低。在计划和执行弃井作业过程中遇到了许多挑战(例如,井完整性—泄漏井、高环空压力、设施完整性和复杂性、浅层天然气、管道和旧钻机占地问题、处理海洋生长的管柱、注浆水泥—双胶结套管、埋井等),作为公司的主要挑战是如何以最佳成本安全执行作业。同时确保安全屏障的安装,以实现长期的井隔离。本文将介绍:SK 305区块(生产井和暂停探井)的油井退役计划、准备和执行主要挑战和经验教训优化、技术和最佳实践caprock P&A方法的应用本文分享会帮助其他作业者更好地了解如何计划和执行油井退役,以及未来可以进行的改进。