Implementation of an unconventional voltage slide scheme

I.L. van der Merwe, J. Cloete, N. Fischer
{"title":"Implementation of an unconventional voltage slide scheme","authors":"I.L. van der Merwe, J. Cloete, N. Fischer","doi":"10.1109/CPRE.2005.1430425","DOIUrl":null,"url":null,"abstract":"Eskom experienced a voltage collapse condition in part of its subtransmission network. The network consists of a number of subtransmission substations that are interconnected and fed from three transmission substations. The voltage collapse condition occurred after a protection operation cleared a fault on one of the 132 kV lines feeding the network from one of the transmission substations. Network studies have shown that the source is relatively weak and that a voltage collapse will occur again if any one of a number of lines from the source transmission substations is tripped out due to a fault. From a solution point of view, constructing additional lines feeding into the network from the transmission substations would solve the problem. However, the load in the area is of such a nature that it is not possible to economically justify the construction of new lines. The paper finally focuses on one specific solution that was selected as being the most appropriate and cost effective. In summary, this solution is an undervoltage load-shedding scheme. The system studies showed that a conventional definite-time undervoltage load-shedding scheme would not provide much benefit. A unique undervoltage algorithm was developed so that load could be shed at selected substations based on the voltage depression at that substation, while still supplying a large part of the network. This unique algorithm was required because voltage at specific substations greatly differs depending on the various contingencies of incoming feeders tripping. The algorithm uses inverse time to shed load based on the severity of the voltage collapse at a specific substation. A modern numerical relay enabled the user to freely program unique algorithms, and could also be used to perform tripping. The paper discusses this solution and its implementation.","PeriodicalId":395312,"journal":{"name":"58th Annual Conference for Protective Relay Engineers, 2005.","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2005-04-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"58th Annual Conference for Protective Relay Engineers, 2005.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CPRE.2005.1430425","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

Eskom experienced a voltage collapse condition in part of its subtransmission network. The network consists of a number of subtransmission substations that are interconnected and fed from three transmission substations. The voltage collapse condition occurred after a protection operation cleared a fault on one of the 132 kV lines feeding the network from one of the transmission substations. Network studies have shown that the source is relatively weak and that a voltage collapse will occur again if any one of a number of lines from the source transmission substations is tripped out due to a fault. From a solution point of view, constructing additional lines feeding into the network from the transmission substations would solve the problem. However, the load in the area is of such a nature that it is not possible to economically justify the construction of new lines. The paper finally focuses on one specific solution that was selected as being the most appropriate and cost effective. In summary, this solution is an undervoltage load-shedding scheme. The system studies showed that a conventional definite-time undervoltage load-shedding scheme would not provide much benefit. A unique undervoltage algorithm was developed so that load could be shed at selected substations based on the voltage depression at that substation, while still supplying a large part of the network. This unique algorithm was required because voltage at specific substations greatly differs depending on the various contingencies of incoming feeders tripping. The algorithm uses inverse time to shed load based on the severity of the voltage collapse at a specific substation. A modern numerical relay enabled the user to freely program unique algorithms, and could also be used to perform tripping. The paper discusses this solution and its implementation.
实现一种非常规的电压滑动方案
Eskom在其部分子输电网络中经历了电压崩溃情况。该网络由若干子传输变电站组成,这些子传输变电站相互连接,并从三个传输变电站馈电。电压崩溃情况发生在保护操作清除了其中一条从一个输电变电站馈电的132千伏线路的故障后。电网研究表明,电源相对较弱,如果来自源传输变电站的许多线路中的任何一条因故障跳闸,将再次发生电压崩溃。从解决方案的角度来看,从输电变电站建造额外的线路进入电网将解决这个问题。然而,该地区的负荷是这样的性质,不可能在经济上证明建设新线路是合理的。本文最后着重于一个被选择为最合适和最具成本效益的具体解决方案。总之,该方案是一种欠压减载方案。系统研究表明,传统的定时间欠压减载方案效果不佳。开发了一种独特的欠压算法,以便根据该变电站的电压下降情况在选定的变电站上卸载负载,同时仍然为网络的大部分供电。这种独特的算法是必需的,因为特定变电站的电压根据输入馈线跳闸的各种意外情况而有很大差异。该算法基于特定变电站电压崩溃的严重程度,使用逆时间来卸载负载。现代数字继电器使用户能够自由编程独特的算法,也可以用来执行跳闸。本文讨论了该解决方案及其实现。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信