Analysis of Extension of Time Impact on Project’s Performance: A Case Study of Projects in Hupsekot Rural Municipality

B. Aryal, Bhawani Dhakal
{"title":"Analysis of Extension of Time Impact on Project’s Performance: A Case Study of Projects in Hupsekot Rural Municipality","authors":"B. Aryal, Bhawani Dhakal","doi":"10.36346/sarjet.2022.v04i05.002","DOIUrl":null,"url":null,"abstract":"This study was carried out on the basis of literature review and the questionnaire survey on selected construction projects with 5-point Likert scale and earned value analysis to know the opinion of different parties involved. The questionnaire contained statements on practices adopted of extension of time in construction field, consequences of extension of time in the project’s cost and time and impacts of extension of time in the project’s performance through literature review. The different timing of the extension of time claim were identified for the practices of extension of time adopted in the Hupsekot Rural Municipality and the study focused the consequences of extension of time in the projects’ cost and time and the real factors for the projects time and cost overrun were also studied from Earned Value Analysis. Also, the impacts of extension of time in the project’s performance were tested through Hypothesis test method. Total of four statements from practices adopted in construction, seventeen statements from the consequences of extension of time and four statements from the impacts of extension of time in projects performance were established and administrated on twelve projects for collecting the information in Hupsekot Rural Municipality. The identified results were analyzed with Relative Importance Index (RII) and Ranking.","PeriodicalId":185348,"journal":{"name":"South Asian Research Journal of Engineering and Technology","volume":"21 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"South Asian Research Journal of Engineering and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36346/sarjet.2022.v04i05.002","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This study was carried out on the basis of literature review and the questionnaire survey on selected construction projects with 5-point Likert scale and earned value analysis to know the opinion of different parties involved. The questionnaire contained statements on practices adopted of extension of time in construction field, consequences of extension of time in the project’s cost and time and impacts of extension of time in the project’s performance through literature review. The different timing of the extension of time claim were identified for the practices of extension of time adopted in the Hupsekot Rural Municipality and the study focused the consequences of extension of time in the projects’ cost and time and the real factors for the projects time and cost overrun were also studied from Earned Value Analysis. Also, the impacts of extension of time in the project’s performance were tested through Hypothesis test method. Total of four statements from practices adopted in construction, seventeen statements from the consequences of extension of time and four statements from the impacts of extension of time in projects performance were established and administrated on twelve projects for collecting the information in Hupsekot Rural Municipality. The identified results were analyzed with Relative Importance Index (RII) and Ranking.
延期对项目绩效的影响分析——以于普措市农村项目为例
本研究是在文献综述的基础上,对选定的建设项目采用李克特五点量表进行问卷调查,并进行挣值分析,以了解各方的意见。问卷通过文献综述的方式,阐述了在施工领域采用的延期做法、延期对项目成本和时间的影响以及延期对项目绩效的影响。在Hupsekot农村自治市采用的延长时间的做法确定了延长时间索赔的不同时间,研究重点是项目成本和时间延长的后果,以及项目时间和成本超支的实际因素也从挣值分析中进行了研究。同时,通过假设检验方法检验了时间延长对项目绩效的影响。在husekot农村市收集信息的12个项目中,共建立和管理了4项关于施工中采用的做法的陈述,17项关于延长时间的后果的陈述和4项关于延长时间对项目绩效影响的陈述。采用相对重要性指数(Relative Importance Index, RII)和排序对鉴定结果进行分析。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信