Optimasi Pelaksanaan Proyek Jalan Dengan Earned Value dan Fast Track

Desi Yasri, A. Yuliardi, Randhi Saily
{"title":"Optimasi Pelaksanaan Proyek Jalan Dengan Earned Value dan Fast Track","authors":"Desi Yasri, A. Yuliardi, Randhi Saily","doi":"10.35583/js.v10i1.226","DOIUrl":null,"url":null,"abstract":"Sei Akar – Bagan Jaya Mayor Rehabilitation Project is located on the Sei Akar – Bagan Jaya road, Indragiri Hilir Regency, Riau Province. Corresponding on the project progress report status up to week 18 or 119 calendar working days, the project has been behind schedules 0.871 % and can lead to project failure. Collaboration of Earned Value Analysis, in time and cost monitoring project performance and Fast-Tracking, in accelerating, overlapping or compressing projects, schedule can be optimized project schedule and prevented from contractual penalties. Earned value analysis forcast additional time for 13 days and cost of Rp. 83.390.308,59 for direct cost, Rp.68.793.391,35 for indirect cost, and Rp.181.614.553,16 for penalties. Implementation of Fast Track in anticipating delays for 13 days, the possibility enclose to Tack Coat activity (42 days) and Asphalt Concrete-Binder Course Work activity (35 days). Both activities have met the rules in the application of fast tracking and have the longest duration. Therefor, has the greatest potential reduction in time.","PeriodicalId":104283,"journal":{"name":"Sainstek (e-Journal)","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-06-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Sainstek (e-Journal)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.35583/js.v10i1.226","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Sei Akar – Bagan Jaya Mayor Rehabilitation Project is located on the Sei Akar – Bagan Jaya road, Indragiri Hilir Regency, Riau Province. Corresponding on the project progress report status up to week 18 or 119 calendar working days, the project has been behind schedules 0.871 % and can lead to project failure. Collaboration of Earned Value Analysis, in time and cost monitoring project performance and Fast-Tracking, in accelerating, overlapping or compressing projects, schedule can be optimized project schedule and prevented from contractual penalties. Earned value analysis forcast additional time for 13 days and cost of Rp. 83.390.308,59 for direct cost, Rp.68.793.391,35 for indirect cost, and Rp.181.614.553,16 for penalties. Implementation of Fast Track in anticipating delays for 13 days, the possibility enclose to Tack Coat activity (42 days) and Asphalt Concrete-Binder Course Work activity (35 days). Both activities have met the rules in the application of fast tracking and have the longest duration. Therefor, has the greatest potential reduction in time.
优化执行街道项目,有价值和快速跟踪
塞阿卡尔-蒲甘查亚市长康复项目位于廖内省因德拉吉里希里尔县塞阿卡尔-蒲甘查亚公路上。对应到第18周或119个日历工作日的项目进度报告状态,项目已落后于计划0.871%,并可能导致项目失败。协作挣值分析,在时间和成本监控项目绩效和快速跟踪,在加速,重叠或压缩项目,进度可以优化项目进度,防止合同处罚。挣值分析预测额外时间为13天,直接成本为83.390.308卢比,间接成本为68.793.391卢比,35卢比,处罚成本为181.614.553卢比,16卢比。快速通道的实施,预计延迟13天,可能包括粘性涂层作业(42天)和沥青混凝土粘结剂作业(35天)。这两项活动均符合快速跟踪应用规则,且持续时间最长。因此,在时间上具有最大的降低潜力。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信