Simulations of ride-through possibilities for a line operated synchronous machine

F. Carlsson, J. Engstrom
{"title":"Simulations of ride-through possibilities for a line operated synchronous machine","authors":"F. Carlsson, J. Engstrom","doi":"10.1109/ICPST.2000.897155","DOIUrl":null,"url":null,"abstract":"Voltage sags and interruptions are a big power quality problem for the industry. Protection equipment automatically breaks the circuit when the power quality is degraded too much. In many cases short voltage sags or interruptions that last for only a hundred milliseconds lead to stoppage for hours in the production. This is mainly due to long start-up times of the industrial process. Simulations have been done on a blast furnace blower in the steel plant SSAB Oxelosund in Sweden. A line operated synchronous machine powers this. The results show that it is possible to reconnect to the mains if the voltage interruption is no longer than 150 ms long. If the remaining voltage is higher than 55% there is no need to break at all. These results show that changing the settings in the protection equipment may reduce the number of unwanted shutdowns.","PeriodicalId":330989,"journal":{"name":"PowerCon 2000. 2000 International Conference on Power System Technology. Proceedings (Cat. No.00EX409)","volume":"7 6","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2000-12-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"PowerCon 2000. 2000 International Conference on Power System Technology. Proceedings (Cat. No.00EX409)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICPST.2000.897155","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

Abstract

Voltage sags and interruptions are a big power quality problem for the industry. Protection equipment automatically breaks the circuit when the power quality is degraded too much. In many cases short voltage sags or interruptions that last for only a hundred milliseconds lead to stoppage for hours in the production. This is mainly due to long start-up times of the industrial process. Simulations have been done on a blast furnace blower in the steel plant SSAB Oxelosund in Sweden. A line operated synchronous machine powers this. The results show that it is possible to reconnect to the mains if the voltage interruption is no longer than 150 ms long. If the remaining voltage is higher than 55% there is no need to break at all. These results show that changing the settings in the protection equipment may reduce the number of unwanted shutdowns.
线路操作同步机穿越可能性的模拟
电压骤降和电压中断是电力行业面临的一大电能质量问题。当电能质量下降过多时,保护设备会自动断开电路。在许多情况下,短暂的电压下降或仅持续100毫秒的中断会导致生产停止数小时。这主要是由于工业过程的启动时间较长。对瑞典SSAB Oxelosund钢铁厂的高炉鼓风机进行了模拟。由线路操作的同步电机驱动。结果表明,如果电压中断时间不超过150毫秒,则可以重新连接到市电。如果剩余电压高于55%,则完全不需要断开。这些结果表明,改变保护设备的设置可以减少不必要的停机次数。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信