A. Casavola, G. Franzé, Francesco Saverio Tedesco, E. Garone
{"title":"Distributed coordination-by-constraint strategies in networked multi-area power systems","authors":"A. Casavola, G. Franzé, Francesco Saverio Tedesco, E. Garone","doi":"10.1109/ISIE.2011.5984417","DOIUrl":null,"url":null,"abstract":"A distributed constrained supervisory strategy for Load/Frequency control problems in networked multi-area power systems is presented. The aim is at finding a coordination strategy able to reconfigure, whenever necessary in response to unexpected load changes and/or faults, the nominal set-point on frequency and generated power to the generators of each area so that viable evolutions arise for the overall power system during transients and a new post-fault sustainable equilibrium is reached. In order to demonstrate the effectiveness of the strategy an example on a four-area power system is presented.","PeriodicalId":162453,"journal":{"name":"2011 IEEE International Symposium on Industrial Electronics","volume":"47 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2011-06-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2011 IEEE International Symposium on Industrial Electronics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ISIE.2011.5984417","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7
Abstract
A distributed constrained supervisory strategy for Load/Frequency control problems in networked multi-area power systems is presented. The aim is at finding a coordination strategy able to reconfigure, whenever necessary in response to unexpected load changes and/or faults, the nominal set-point on frequency and generated power to the generators of each area so that viable evolutions arise for the overall power system during transients and a new post-fault sustainable equilibrium is reached. In order to demonstrate the effectiveness of the strategy an example on a four-area power system is presented.