基于IEC 61850的微电网电源管理系统实施和测试的高级框架

K. Gray, J. Kumm, J. Mraz
{"title":"基于IEC 61850的微电网电源管理系统实施和测试的高级框架","authors":"K. Gray, J. Kumm, J. Mraz","doi":"10.1109/TDC.2016.7520026","DOIUrl":null,"url":null,"abstract":"A North American oil refinery recently improved on-site power system reliability by extensively modifying the inplant electric system. Simultaneously, the refinery upgraded protective relaying to support IEC 61850 GOOSE messaging. New load caused a generation deficit when islanded from the local utility. The project team implemented a power management system to preserve critical loads when the refinery microgrid is islanded from the utility. The power management controllers use IEC 61850 GOOSE messaging. The project team performed thorough hardware-in-the-loop testing using a Real Time Digital Simulator (RTDS) along with traditional protection test-set testing to validate system operation for designed transitions and anticipated equipment failure modes. In studying these projects, we have developed a framework, which this paper shares, for successfully implementing other, similar microgrid power management system projects.","PeriodicalId":6497,"journal":{"name":"2016 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)","volume":"161 ","pages":"1-4"},"PeriodicalIF":0.0000,"publicationDate":"2016-05-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"A high-level framework for implementation and test of IEC 61850-based microgrid power management systems\",\"authors\":\"K. Gray, J. Kumm, J. Mraz\",\"doi\":\"10.1109/TDC.2016.7520026\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"A North American oil refinery recently improved on-site power system reliability by extensively modifying the inplant electric system. Simultaneously, the refinery upgraded protective relaying to support IEC 61850 GOOSE messaging. New load caused a generation deficit when islanded from the local utility. The project team implemented a power management system to preserve critical loads when the refinery microgrid is islanded from the utility. The power management controllers use IEC 61850 GOOSE messaging. The project team performed thorough hardware-in-the-loop testing using a Real Time Digital Simulator (RTDS) along with traditional protection test-set testing to validate system operation for designed transitions and anticipated equipment failure modes. In studying these projects, we have developed a framework, which this paper shares, for successfully implementing other, similar microgrid power management system projects.\",\"PeriodicalId\":6497,\"journal\":{\"name\":\"2016 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)\",\"volume\":\"161 \",\"pages\":\"1-4\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2016-05-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2016 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/TDC.2016.7520026\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2016 IEEE/PES Transmission and Distribution Conference and Exposition (T&D)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TDC.2016.7520026","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

最近,一家北美炼油厂通过对工厂内电力系统进行大规模改造,提高了现场电力系统的可靠性。同时,炼油厂升级了保护继电器以支持IEC 61850 GOOSE消息传递。当新负荷与当地公用事业隔绝时,会造成发电赤字。项目团队实施了一个电源管理系统,以在炼油厂微电网与公用事业隔离时保持关键负载。电源管理控制器使用IEC 61850 GOOSE消息传递。项目团队使用实时数字模拟器(RTDS)和传统的保护测试集进行了全面的硬件在环测试,以验证系统在设计转换和预期设备故障模式下的运行情况。在研究这些项目的过程中,我们开发了一个框架,本文将其共享,以成功实施其他类似的微电网电源管理系统项目。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A high-level framework for implementation and test of IEC 61850-based microgrid power management systems
A North American oil refinery recently improved on-site power system reliability by extensively modifying the inplant electric system. Simultaneously, the refinery upgraded protective relaying to support IEC 61850 GOOSE messaging. New load caused a generation deficit when islanded from the local utility. The project team implemented a power management system to preserve critical loads when the refinery microgrid is islanded from the utility. The power management controllers use IEC 61850 GOOSE messaging. The project team performed thorough hardware-in-the-loop testing using a Real Time Digital Simulator (RTDS) along with traditional protection test-set testing to validate system operation for designed transitions and anticipated equipment failure modes. In studying these projects, we have developed a framework, which this paper shares, for successfully implementing other, similar microgrid power management system projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信