案例研究:包含阀件互换性的冶金选择和节流设计,以满足Raageshwari深层气田的整个生产周期

C. Bhardwaj, V. Ranjan, S. Jetley, S. Tiwari, A. Ghosh, Swapnil Sharma, A. Bohra, Abhishek Kumar, Abhudai Beohar, Sidharth Sharma
{"title":"案例研究:包含阀件互换性的冶金选择和节流设计,以满足Raageshwari深层气田的整个生产周期","authors":"C. Bhardwaj, V. Ranjan, S. Jetley, S. Tiwari, A. Ghosh, Swapnil Sharma, A. Bohra, Abhishek Kumar, Abhudai Beohar, Sidharth Sharma","doi":"10.2118/194562-MS","DOIUrl":null,"url":null,"abstract":"\n The Raageshwari Deep Gas (RDG) field, situated within Barmer Basin in the State of Rajasthan, India, was discovered in 2003. The field is a tight gas condensate reservoir, with excellent gas quality of approximately 80% methane, low CO2 and no H2S. Since the permeability (0.01 - 1 md) is low in this reservoir, hydraulic fracturing is required to get substantial recovery from the wells. The field has been under production since 2010. The development of this field has been carried out in three phases and more than 150 fracturing treatments have been pumped in this reservoir till date to achieve sustained economical production. This paper deals with the lessons learnt and changes implemented in choke design through various development phases of the field.\n In the initial phase of field development, chokes with a low Flow Coefficient (Cv) were installed to meet the requirement of controlling the wells at low flow rates and high differential pressure. Later as the surface handling capacity increased, the chokes had to be de-bottlenecked, requiring additional Capex for new chokes. To avoid a similar scenario in the future, a comprehensive approach has been followed to envisage Cv requirement, considering well wise production profiles and surface handling capacities throughout the life of field. Since a single trim can't operate over the complete life-cycle of a well, trim interchangeability has been included in the choke design such that low and high Cv trims are interchangeable.\n Pre-mature failures of trims were observed in initial phase and a root cause analysis was done to ascertain the reason. Based on the analysis, trim metallurgy has been changed from Tungsten Carbide to ASTM A276 Specific Stainless Steel Grade 440C. Trims with newly selected mettalurgy have been installed in the existing chokes.\n The introduction of trim interchangeability has saved MMUSD 0.3 in the future Opex as the requirement of procuring altogether new chokes for late life period of wells is avoided. Initially failures in the trim bodies were observed as early as two months of commissioning but with the change in metallurgy zero failures have been observed with operational life of chokes being higher than four years. This has avoided significant downtime on wells and expenditure on regular trim changeovers.\n Although Tungsten Carbide is one of the most common materials used for constructing trims world over, there could be specific cases where-in other metallurgy may add better value. The workflow followed in this paper will help select a suitable metallurgy and can impart a significant value to the industry.","PeriodicalId":11150,"journal":{"name":"Day 2 Wed, April 10, 2019","volume":"244 5","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-04-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Case Study: Metallurgy Selection and Choke Design Incorporating Trim Interchangeability to Cater to the Entire Production Lifecycle of Raageshwari Deep Gas Field\",\"authors\":\"C. Bhardwaj, V. Ranjan, S. Jetley, S. Tiwari, A. Ghosh, Swapnil Sharma, A. Bohra, Abhishek Kumar, Abhudai Beohar, Sidharth Sharma\",\"doi\":\"10.2118/194562-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The Raageshwari Deep Gas (RDG) field, situated within Barmer Basin in the State of Rajasthan, India, was discovered in 2003. The field is a tight gas condensate reservoir, with excellent gas quality of approximately 80% methane, low CO2 and no H2S. Since the permeability (0.01 - 1 md) is low in this reservoir, hydraulic fracturing is required to get substantial recovery from the wells. The field has been under production since 2010. The development of this field has been carried out in three phases and more than 150 fracturing treatments have been pumped in this reservoir till date to achieve sustained economical production. This paper deals with the lessons learnt and changes implemented in choke design through various development phases of the field.\\n In the initial phase of field development, chokes with a low Flow Coefficient (Cv) were installed to meet the requirement of controlling the wells at low flow rates and high differential pressure. Later as the surface handling capacity increased, the chokes had to be de-bottlenecked, requiring additional Capex for new chokes. To avoid a similar scenario in the future, a comprehensive approach has been followed to envisage Cv requirement, considering well wise production profiles and surface handling capacities throughout the life of field. Since a single trim can't operate over the complete life-cycle of a well, trim interchangeability has been included in the choke design such that low and high Cv trims are interchangeable.\\n Pre-mature failures of trims were observed in initial phase and a root cause analysis was done to ascertain the reason. Based on the analysis, trim metallurgy has been changed from Tungsten Carbide to ASTM A276 Specific Stainless Steel Grade 440C. Trims with newly selected mettalurgy have been installed in the existing chokes.\\n The introduction of trim interchangeability has saved MMUSD 0.3 in the future Opex as the requirement of procuring altogether new chokes for late life period of wells is avoided. Initially failures in the trim bodies were observed as early as two months of commissioning but with the change in metallurgy zero failures have been observed with operational life of chokes being higher than four years. This has avoided significant downtime on wells and expenditure on regular trim changeovers.\\n Although Tungsten Carbide is one of the most common materials used for constructing trims world over, there could be specific cases where-in other metallurgy may add better value. The workflow followed in this paper will help select a suitable metallurgy and can impart a significant value to the industry.\",\"PeriodicalId\":11150,\"journal\":{\"name\":\"Day 2 Wed, April 10, 2019\",\"volume\":\"244 5\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Wed, April 10, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/194562-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, April 10, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/194562-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

Raageshwari深层天然气(RDG)气田位于印度拉贾斯坦邦的Barmer盆地,于2003年被发现。该油田为致密凝析气藏,天然气质量优良,甲烷含量约为80%,二氧化碳含量低,不含H2S。由于该油藏渗透率(0.01 - 1 md)较低,因此需要进行水力压裂以获得可观的采收率。该油田自2010年以来一直处于生产状态。该油田的开发分三个阶段进行,迄今已在该储层进行了150多次压裂作业,以实现持续的经济生产。本文介绍了在油田的各个开发阶段,在节流道设计中吸取的经验教训和实施的变化。在油田开发的初始阶段,安装了具有低流量系数(Cv)的节流阀,以满足在低流量和高压差下控制井的要求。后来,随着地面处理能力的增加,必须消除扼流圈的瓶颈,这就需要额外的资本支出来购买新的扼流圈。为了避免未来发生类似的情况,我们采用了一种综合的方法来设想Cv要求,同时考虑到油田整个生命周期内的生产概况和地面处理能力。由于单个阀芯无法在井的整个生命周期内工作,因此节流器设计中包含了阀芯的互换性,使得低Cv和高Cv阀芯可以互换。在初始阶段观察到阀芯过早失效,并进行了根本原因分析,以确定其原因。在分析的基础上,装饰冶金从碳化钨改为ASTM A276专用不锈钢等级440C。与新选择的冶金装饰已安装在现有的扼流圈。由于避免了在井的生命周期后期购买全新的节流阀,因此节流件互换性的引入在未来的运营成本中节省了0.3 MMUSD。最初在调试两个月时就观察到阀芯体的故障,但随着冶金技术的变化,在使用寿命超过四年的情况下,已观察到零故障。这避免了大量的井停工期和定期更换修整器的费用。虽然碳化钨是世界上最常用的装饰材料之一,但在某些特殊情况下,其他冶金材料可能会有更好的价值。本文所遵循的工作流程将有助于选择合适的冶金方法,并可为工业提供重要价值。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Case Study: Metallurgy Selection and Choke Design Incorporating Trim Interchangeability to Cater to the Entire Production Lifecycle of Raageshwari Deep Gas Field
The Raageshwari Deep Gas (RDG) field, situated within Barmer Basin in the State of Rajasthan, India, was discovered in 2003. The field is a tight gas condensate reservoir, with excellent gas quality of approximately 80% methane, low CO2 and no H2S. Since the permeability (0.01 - 1 md) is low in this reservoir, hydraulic fracturing is required to get substantial recovery from the wells. The field has been under production since 2010. The development of this field has been carried out in three phases and more than 150 fracturing treatments have been pumped in this reservoir till date to achieve sustained economical production. This paper deals with the lessons learnt and changes implemented in choke design through various development phases of the field. In the initial phase of field development, chokes with a low Flow Coefficient (Cv) were installed to meet the requirement of controlling the wells at low flow rates and high differential pressure. Later as the surface handling capacity increased, the chokes had to be de-bottlenecked, requiring additional Capex for new chokes. To avoid a similar scenario in the future, a comprehensive approach has been followed to envisage Cv requirement, considering well wise production profiles and surface handling capacities throughout the life of field. Since a single trim can't operate over the complete life-cycle of a well, trim interchangeability has been included in the choke design such that low and high Cv trims are interchangeable. Pre-mature failures of trims were observed in initial phase and a root cause analysis was done to ascertain the reason. Based on the analysis, trim metallurgy has been changed from Tungsten Carbide to ASTM A276 Specific Stainless Steel Grade 440C. Trims with newly selected mettalurgy have been installed in the existing chokes. The introduction of trim interchangeability has saved MMUSD 0.3 in the future Opex as the requirement of procuring altogether new chokes for late life period of wells is avoided. Initially failures in the trim bodies were observed as early as two months of commissioning but with the change in metallurgy zero failures have been observed with operational life of chokes being higher than four years. This has avoided significant downtime on wells and expenditure on regular trim changeovers. Although Tungsten Carbide is one of the most common materials used for constructing trims world over, there could be specific cases where-in other metallurgy may add better value. The workflow followed in this paper will help select a suitable metallurgy and can impart a significant value to the industry.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信