线性调度在水渠施工中的应用及关键路径法的比较

IF 0.8 Q4 CONSTRUCTION & BUILDING TECHNOLOGY
P. Ramani, P. Selvaraj, S. T, Anshul Gupta
{"title":"线性调度在水渠施工中的应用及关键路径法的比较","authors":"P. Ramani, P. Selvaraj, S. T, Anshul Gupta","doi":"10.21315/jcdc2022.27.1.11","DOIUrl":null,"url":null,"abstract":"Critical path method (CPM) still remains the most commonly used scheduling technique, despite many studies confirming its shortcomings for scheduling repetitive construction projects. This research evaluated the case study of an alignment-based precast water canal erection project, which was originally planned with CPM and analysed the suitability of using linear scheduling method (LSM) for the same project. The case study project was scheduled using both CPM and LSM tools and the results were compared in terms of estimated total duration and resource cost. The results showed that LSM produced a saving of 10 days in total duration and 20.07% in estimated resource cost over CPM. LSM also proved to be the better tool in terms of other schedule attributes like resource assignment, levelling, visualisation, etc., for alignment-based projects. LSM can be highly efficient for scheduling different types of repetitive construction and offers benefits like better workflow and continuous resource usage.","PeriodicalId":51876,"journal":{"name":"Journal of Construction in Developing Countries","volume":"31 2 1","pages":""},"PeriodicalIF":0.8000,"publicationDate":"2022-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Application of Linear Scheduling in Water Canal Construction with a Comparison of Critical Path Method\",\"authors\":\"P. Ramani, P. Selvaraj, S. T, Anshul Gupta\",\"doi\":\"10.21315/jcdc2022.27.1.11\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Critical path method (CPM) still remains the most commonly used scheduling technique, despite many studies confirming its shortcomings for scheduling repetitive construction projects. This research evaluated the case study of an alignment-based precast water canal erection project, which was originally planned with CPM and analysed the suitability of using linear scheduling method (LSM) for the same project. The case study project was scheduled using both CPM and LSM tools and the results were compared in terms of estimated total duration and resource cost. The results showed that LSM produced a saving of 10 days in total duration and 20.07% in estimated resource cost over CPM. LSM also proved to be the better tool in terms of other schedule attributes like resource assignment, levelling, visualisation, etc., for alignment-based projects. LSM can be highly efficient for scheduling different types of repetitive construction and offers benefits like better workflow and continuous resource usage.\",\"PeriodicalId\":51876,\"journal\":{\"name\":\"Journal of Construction in Developing Countries\",\"volume\":\"31 2 1\",\"pages\":\"\"},\"PeriodicalIF\":0.8000,\"publicationDate\":\"2022-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Construction in Developing Countries\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21315/jcdc2022.27.1.11\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"CONSTRUCTION & BUILDING TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Construction in Developing Countries","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21315/jcdc2022.27.1.11","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 2

摘要

关键路径法(CPM)仍然是最常用的调度技术,尽管许多研究证实了它在重复建设项目调度中的不足。本研究评估了一个基于对齐的预制水渠安装项目的案例研究,该项目最初是用CPM计划的,并分析了在同一项目中使用线性调度方法(LSM)的适用性。案例研究项目使用CPM和LSM工具进行计划,并根据估计的总持续时间和资源成本对结果进行比较。结果表明,与CPM相比,LSM的总工期节省了10天,估计资源成本节省了20.07%。LSM在其他进度属性方面也被证明是更好的工具,比如资源分配、平衡、可视化等,这些都是基于一致性的项目。LSM可以高效地调度不同类型的重复构建,并提供诸如更好的工作流和持续的资源使用等好处。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Application of Linear Scheduling in Water Canal Construction with a Comparison of Critical Path Method
Critical path method (CPM) still remains the most commonly used scheduling technique, despite many studies confirming its shortcomings for scheduling repetitive construction projects. This research evaluated the case study of an alignment-based precast water canal erection project, which was originally planned with CPM and analysed the suitability of using linear scheduling method (LSM) for the same project. The case study project was scheduled using both CPM and LSM tools and the results were compared in terms of estimated total duration and resource cost. The results showed that LSM produced a saving of 10 days in total duration and 20.07% in estimated resource cost over CPM. LSM also proved to be the better tool in terms of other schedule attributes like resource assignment, levelling, visualisation, etc., for alignment-based projects. LSM can be highly efficient for scheduling different types of repetitive construction and offers benefits like better workflow and continuous resource usage.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Journal of Construction in Developing Countries
Journal of Construction in Developing Countries CONSTRUCTION & BUILDING TECHNOLOGY-
CiteScore
1.50
自引率
0.00%
发文量
25
审稿时长
20 weeks
期刊介绍: The Journal of Construction in Developing Countries seeks to provide a central vehicle for the exchange and dissemination of knowledge on issues relevant to the built environment of developing countries. The journal provides a wide range of original research an application papers on current developments and advances in the built environment as well as the economic, social, cultural and technological contexts of developing countries. It also publishes detailed case studies, as well as short communications and discussions. Topics covered include, but are not restricted to planning, urban economics, rural and regional development, housing, management and resource issues, sustiainability, knowledge and technology transfer, construction procurement, facilities management, information an communication technologies, strategies and policy issues, design issues, conservation and environmental issues.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信