FPSO和FPS系泊系统寿命延长评估和挑战问题

Huoping Wang, Qinghe Zhang, Yiyong Liu, Mao Jiayou, Weiquan Zhu, Hui Shen
{"title":"FPSO和FPS系泊系统寿命延长评估和挑战问题","authors":"Huoping Wang, Qinghe Zhang, Yiyong Liu, Mao Jiayou, Weiquan Zhu, Hui Shen","doi":"10.4043/29338-MS","DOIUrl":null,"url":null,"abstract":"\n Mooring system life extension for offshore floating production installation has become a hot topic for offshore industry as more and more floating units approach the end of their design lives. Some mooring system life extension projects have already been completed successfully, there are still some issues upon which the mooring industry has not reached consensus, such as field inspection capability/accuracy, uninspected items assessment, component degradation assessment, and acceptance criteria for numerical evaluation. This paper demonstrates two mooring system life extension processes located at Liuhua (LH) 11-1 oil field, following ABS rules as well as industry best practices. It also presents the challenging issues met during this long period of operation, initiated in 2016 and to be completed by end of 2019.\n Nanhai Shengli (NHSL) FPSO and Nanhai Tiaozhan (NHTZ) FPS are located in Liuhua 11-1 oil field. Both of the mooring systems were installed in 1995 with an originally designed life of 10 years, and already upgraded/replaced partially to extend their lives for continual safety operation. Thus, this is the second life extension for them, and some special challenges are presented. The upgrade of the mooring system is proposed based on inspection, testing, and analysis results for the existing mooring components. This paper focuses on some of the work that has been performed. These experiences may be helpful for the life extension of other similar mooring systems.","PeriodicalId":11149,"journal":{"name":"Day 1 Mon, May 06, 2019","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2019-04-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Liuhua 11-1 FPSO & FPS Mooring System Life Extension Evaluation and Challenging Issues\",\"authors\":\"Huoping Wang, Qinghe Zhang, Yiyong Liu, Mao Jiayou, Weiquan Zhu, Hui Shen\",\"doi\":\"10.4043/29338-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Mooring system life extension for offshore floating production installation has become a hot topic for offshore industry as more and more floating units approach the end of their design lives. Some mooring system life extension projects have already been completed successfully, there are still some issues upon which the mooring industry has not reached consensus, such as field inspection capability/accuracy, uninspected items assessment, component degradation assessment, and acceptance criteria for numerical evaluation. This paper demonstrates two mooring system life extension processes located at Liuhua (LH) 11-1 oil field, following ABS rules as well as industry best practices. It also presents the challenging issues met during this long period of operation, initiated in 2016 and to be completed by end of 2019.\\n Nanhai Shengli (NHSL) FPSO and Nanhai Tiaozhan (NHTZ) FPS are located in Liuhua 11-1 oil field. Both of the mooring systems were installed in 1995 with an originally designed life of 10 years, and already upgraded/replaced partially to extend their lives for continual safety operation. Thus, this is the second life extension for them, and some special challenges are presented. The upgrade of the mooring system is proposed based on inspection, testing, and analysis results for the existing mooring components. This paper focuses on some of the work that has been performed. These experiences may be helpful for the life extension of other similar mooring systems.\",\"PeriodicalId\":11149,\"journal\":{\"name\":\"Day 1 Mon, May 06, 2019\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-26\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Mon, May 06, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/29338-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, May 06, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29338-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

随着越来越多的浮式装置接近设计寿命,延长海上浮式生产装置的系泊系统寿命已成为海上工业的热点问题。一些系泊系统延寿项目已经成功完成,但仍存在一些系泊行业尚未达成共识的问题,如现场检验能力/精度、未检验项目评估、部件退化评估、数值评估验收标准等。本文演示了位于柳花(LH) 11-1油田的两个系泊系统延长寿命的过程,遵循了ABS规则和行业最佳实践。它还介绍了在2016年开始并将于2019年底完成的长期运营期间遇到的挑战性问题。南海胜利(NHSL) FPSO和南海挑战(NHTZ) FPSO位于流花11-1油田。这两个系泊系统都是在1995年安装的,最初设计的使用寿命为10年,现在已经进行了部分升级/更换,以延长其使用寿命,确保持续安全运行。因此,这是它们的第二次寿命延长,并提出了一些特殊的挑战。根据对现有系泊部件的检查、测试和分析结果,提出了对系泊系统进行升级改造的方案。本文的重点是一些已经完成的工作。这些经验可能对其他类似系泊系统的寿命延长有所帮助。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Liuhua 11-1 FPSO & FPS Mooring System Life Extension Evaluation and Challenging Issues
Mooring system life extension for offshore floating production installation has become a hot topic for offshore industry as more and more floating units approach the end of their design lives. Some mooring system life extension projects have already been completed successfully, there are still some issues upon which the mooring industry has not reached consensus, such as field inspection capability/accuracy, uninspected items assessment, component degradation assessment, and acceptance criteria for numerical evaluation. This paper demonstrates two mooring system life extension processes located at Liuhua (LH) 11-1 oil field, following ABS rules as well as industry best practices. It also presents the challenging issues met during this long period of operation, initiated in 2016 and to be completed by end of 2019. Nanhai Shengli (NHSL) FPSO and Nanhai Tiaozhan (NHTZ) FPS are located in Liuhua 11-1 oil field. Both of the mooring systems were installed in 1995 with an originally designed life of 10 years, and already upgraded/replaced partially to extend their lives for continual safety operation. Thus, this is the second life extension for them, and some special challenges are presented. The upgrade of the mooring system is proposed based on inspection, testing, and analysis results for the existing mooring components. This paper focuses on some of the work that has been performed. These experiences may be helpful for the life extension of other similar mooring systems.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信