造船长期规划与中期调度的整合

IF 6.1 3区 管理学 Q1 ENGINEERING, INDUSTRIAL
Suheon Ju, J. Woo
{"title":"造船长期规划与中期调度的整合","authors":"Suheon Ju, J. Woo","doi":"10.1080/09537287.2021.1940344","DOIUrl":null,"url":null,"abstract":"Abstract A shipyard’s production plan has a hierarchical structure comprising a long-term plan and a mid-term or short-term plan. The mid-term schedule is established based on the major schedules of the long-term plan. However, in the long-term planning stage, the mid-term schedule is not considered owing to timing discrepancies and the lack of data. Therefore, even if a major schedule is changed to achieve production goals – such as workload balancing in the mid-term scheduling process – this is not reflected in the long-term plan. To solve these discrepancy challenges in conventional production planning, the problems of an existing shipbuilding production planning process were derived, and an algorithm to optimize the berth schedule by reflecting the mid-term schedule when establishing a long-term plan was developed. The developed methodology and algorithm were installed in an existing planning system and applied to an actual shipyard production planning process. Results showed improvements in long-term and mid-term scheduling.","PeriodicalId":20627,"journal":{"name":"Production Planning & Control","volume":"9 1","pages":"524 - 542"},"PeriodicalIF":6.1000,"publicationDate":"2021-07-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Integration of long-term planning and mid-term scheduling of shipbuilding\",\"authors\":\"Suheon Ju, J. Woo\",\"doi\":\"10.1080/09537287.2021.1940344\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract A shipyard’s production plan has a hierarchical structure comprising a long-term plan and a mid-term or short-term plan. The mid-term schedule is established based on the major schedules of the long-term plan. However, in the long-term planning stage, the mid-term schedule is not considered owing to timing discrepancies and the lack of data. Therefore, even if a major schedule is changed to achieve production goals – such as workload balancing in the mid-term scheduling process – this is not reflected in the long-term plan. To solve these discrepancy challenges in conventional production planning, the problems of an existing shipbuilding production planning process were derived, and an algorithm to optimize the berth schedule by reflecting the mid-term schedule when establishing a long-term plan was developed. The developed methodology and algorithm were installed in an existing planning system and applied to an actual shipyard production planning process. Results showed improvements in long-term and mid-term scheduling.\",\"PeriodicalId\":20627,\"journal\":{\"name\":\"Production Planning & Control\",\"volume\":\"9 1\",\"pages\":\"524 - 542\"},\"PeriodicalIF\":6.1000,\"publicationDate\":\"2021-07-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Production Planning & Control\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.1080/09537287.2021.1940344\",\"RegionNum\":3,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Production Planning & Control","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1080/09537287.2021.1940344","RegionNum":3,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 3

摘要

摘要船厂生产计划是由长期计划和中期或短期计划组成的分层结构。中期计划是在长期计划主要计划的基础上制定的。但是,在长期规划阶段,由于时间差异和缺乏数据,没有考虑中期时间表。因此,即使为了实现生产目标而改变了一个主要的计划——比如在中期调度过程中平衡工作负载——这也不会反映在长期计划中。针对传统生产计划中存在的这些差异挑战,推导了现有船舶生产计划流程中存在的问题,提出了一种在制定长期计划时反映中期计划的泊位计划优化算法。所开发的方法和算法安装在现有的计划系统中,并应用于实际的造船厂生产计划过程。结果显示长期和中期计划均有改善。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Integration of long-term planning and mid-term scheduling of shipbuilding
Abstract A shipyard’s production plan has a hierarchical structure comprising a long-term plan and a mid-term or short-term plan. The mid-term schedule is established based on the major schedules of the long-term plan. However, in the long-term planning stage, the mid-term schedule is not considered owing to timing discrepancies and the lack of data. Therefore, even if a major schedule is changed to achieve production goals – such as workload balancing in the mid-term scheduling process – this is not reflected in the long-term plan. To solve these discrepancy challenges in conventional production planning, the problems of an existing shipbuilding production planning process were derived, and an algorithm to optimize the berth schedule by reflecting the mid-term schedule when establishing a long-term plan was developed. The developed methodology and algorithm were installed in an existing planning system and applied to an actual shipyard production planning process. Results showed improvements in long-term and mid-term scheduling.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Production Planning & Control
Production Planning & Control 管理科学-工程:工业
CiteScore
19.30
自引率
9.60%
发文量
72
审稿时长
6-12 weeks
期刊介绍: Production Planning & Control is an international journal that focuses on research papers concerning operations management across industries. It emphasizes research originating from industrial needs that can provide guidance to managers and future researchers. Papers accepted by "Production Planning & Control" should address emerging industrial needs, clearly outlining the nature of the industrial problem. Any suitable research methods may be employed, and each paper should justify the method used. Case studies illustrating international significance are encouraged. Authors are encouraged to relate their work to existing knowledge in the field, particularly regarding its implications for management practice and future research agendas.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信