无钻机干预确保文莱海上天然气井喷的IBO监测

A. Leong, Y. Azizan, Yee Tzen Yong, Yan Song, Rudzaifi Adizamri Abd Rani, Mohd Majdi Jasni
{"title":"无钻机干预确保文莱海上天然气井喷的IBO监测","authors":"A. Leong, Y. Azizan, Yee Tzen Yong, Yan Song, Rudzaifi Adizamri Abd Rani, Mohd Majdi Jasni","doi":"10.2118/192000-MS","DOIUrl":null,"url":null,"abstract":"Mature fields often include wells or platforms that require a plug and abandonment (P&A) job and decommissioning. Two high-pressure gas wells were identified in a field offshore Brunei that required a coiled tubing unit (CTU) intervention to secure them. The job was further complicated by high reservoir pressure in a tight formation, a small platform area, and no existing surface facility.\n Because the flowline and pipeline equipment on the platform are not in service, a method was needed to take large volumes of returns. To overcome this challenge, an integrated operation was designed and planned that uses a complete catenary CTU and a pumping and flowback package with a mobile storage support vessel. The returns system will enable liquid (brine and spacer) and gas returns with pressures of up to 5,000 psi. The mobile storage support vessel enables the returns to be stored before disposal at an onshore facility.\n Before killing the wells and pumping cement across the perforation, multiple tubing plugs must be removed. High tubing pressure indicated some communication to the reservoir; consequently, the plug removal strategy with coiled tubing (CT) must include risk mitigation to ensure that the plugs can be removed safely.\n After all plugs were removed, the wells were successfully killed by using a 17 kPa/m (14.45 ppg) calcium chloride/calcium bromide (CaCl2/CaBr2) blend brine. The next operation was to spot cement across the perforation to a depth that is below where the tubing will be cut during the P&A process. The spacers and cement design must be tailored to avoid compatibility issues with the CaCl2/CaBr2 and the presence of carbon dioxide (CO2). The cement placement with CT is critical to prevent flash reaction with the kill fluid and to minimize the volume of contaminated cement. The cement was placed successfully and tested in accordance with the Brunei Shell Petroleum requirement.\n The wells were safely secured and ready for the planned P&A process. These operations marked the first successful operation on high-pressure, tight gas wells with no surface facilities on the platform within a sensitive environment. The use of a mobile storage support vessel enabled the wells to be killed successfully. This approach demonstrates that a similar method and similar planning can be used to safely and economically perform future interventions.","PeriodicalId":11182,"journal":{"name":"Day 3 Thu, October 25, 2018","volume":"2 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2018-10-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Rigless Intervention to Secure Internal Blowout IBO Monitoring Gas Wells Offshore of Brunei\",\"authors\":\"A. Leong, Y. Azizan, Yee Tzen Yong, Yan Song, Rudzaifi Adizamri Abd Rani, Mohd Majdi Jasni\",\"doi\":\"10.2118/192000-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Mature fields often include wells or platforms that require a plug and abandonment (P&A) job and decommissioning. Two high-pressure gas wells were identified in a field offshore Brunei that required a coiled tubing unit (CTU) intervention to secure them. The job was further complicated by high reservoir pressure in a tight formation, a small platform area, and no existing surface facility.\\n Because the flowline and pipeline equipment on the platform are not in service, a method was needed to take large volumes of returns. To overcome this challenge, an integrated operation was designed and planned that uses a complete catenary CTU and a pumping and flowback package with a mobile storage support vessel. The returns system will enable liquid (brine and spacer) and gas returns with pressures of up to 5,000 psi. The mobile storage support vessel enables the returns to be stored before disposal at an onshore facility.\\n Before killing the wells and pumping cement across the perforation, multiple tubing plugs must be removed. High tubing pressure indicated some communication to the reservoir; consequently, the plug removal strategy with coiled tubing (CT) must include risk mitigation to ensure that the plugs can be removed safely.\\n After all plugs were removed, the wells were successfully killed by using a 17 kPa/m (14.45 ppg) calcium chloride/calcium bromide (CaCl2/CaBr2) blend brine. The next operation was to spot cement across the perforation to a depth that is below where the tubing will be cut during the P&A process. The spacers and cement design must be tailored to avoid compatibility issues with the CaCl2/CaBr2 and the presence of carbon dioxide (CO2). The cement placement with CT is critical to prevent flash reaction with the kill fluid and to minimize the volume of contaminated cement. The cement was placed successfully and tested in accordance with the Brunei Shell Petroleum requirement.\\n The wells were safely secured and ready for the planned P&A process. These operations marked the first successful operation on high-pressure, tight gas wells with no surface facilities on the platform within a sensitive environment. The use of a mobile storage support vessel enabled the wells to be killed successfully. This approach demonstrates that a similar method and similar planning can be used to safely and economically perform future interventions.\",\"PeriodicalId\":11182,\"journal\":{\"name\":\"Day 3 Thu, October 25, 2018\",\"volume\":\"2 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-10-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Thu, October 25, 2018\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/192000-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Thu, October 25, 2018","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/192000-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

成熟油田通常包括需要封堵弃井(P&A)和退役的井或平台。在文莱近海油田发现了两口高压气井,需要连续油管(CTU)干预来保护它们。由于致密地层中储层压力高,平台面积小,并且没有现有的地面设施,使得作业更加复杂。由于平台上的管线和管道设备没有投入使用,因此需要一种方法来获取大量的回采。为了克服这一挑战,设计和规划了一个综合作业,使用了一个完整的接触网CTU和一个带移动存储支持容器的泵送和反排包。回流系统将使液体(盐水和隔离液)和气体能够在高达5000 psi的压力下回流。移动存储支持船可以在岸上设施处理之前将回收物存储起来。在压井和泵入水泥穿过射孔之前,必须拆除多个油管塞。油管压力高表明与储层有一定的连通;因此,使用连续油管(CT)的桥塞移除策略必须包括降低风险,以确保可以安全移除桥塞。所有桥塞拆除后,使用17 kPa/m (14.45 ppg)氯化钙/溴化钙(CaCl2/CaBr2)混合盐水成功压井。接下来的作业是在射孔处定位水泥,直至在封堵弃井过程中切断油管的深度以下。隔离剂和水泥的设计必须量身定制,以避免CaCl2/CaBr2的兼容性问题以及二氧化碳(CO2)的存在。连续油管固井对于防止与压井液发生闪蒸反应以及将受污染的水泥体积降至最低至关重要。根据文莱壳牌石油公司的要求,水泥被成功放置并进行了测试。这些井已被安全加固,并准备进行计划的P&A过程。这些作业标志着高压致密气井在敏感环境下的首次成功作业,平台上没有地面设施。使用移动存储支持船,成功完成了压井作业。这种方法表明,类似的方法和类似的规划可以用于安全、经济地执行未来的干预措施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Rigless Intervention to Secure Internal Blowout IBO Monitoring Gas Wells Offshore of Brunei
Mature fields often include wells or platforms that require a plug and abandonment (P&A) job and decommissioning. Two high-pressure gas wells were identified in a field offshore Brunei that required a coiled tubing unit (CTU) intervention to secure them. The job was further complicated by high reservoir pressure in a tight formation, a small platform area, and no existing surface facility. Because the flowline and pipeline equipment on the platform are not in service, a method was needed to take large volumes of returns. To overcome this challenge, an integrated operation was designed and planned that uses a complete catenary CTU and a pumping and flowback package with a mobile storage support vessel. The returns system will enable liquid (brine and spacer) and gas returns with pressures of up to 5,000 psi. The mobile storage support vessel enables the returns to be stored before disposal at an onshore facility. Before killing the wells and pumping cement across the perforation, multiple tubing plugs must be removed. High tubing pressure indicated some communication to the reservoir; consequently, the plug removal strategy with coiled tubing (CT) must include risk mitigation to ensure that the plugs can be removed safely. After all plugs were removed, the wells were successfully killed by using a 17 kPa/m (14.45 ppg) calcium chloride/calcium bromide (CaCl2/CaBr2) blend brine. The next operation was to spot cement across the perforation to a depth that is below where the tubing will be cut during the P&A process. The spacers and cement design must be tailored to avoid compatibility issues with the CaCl2/CaBr2 and the presence of carbon dioxide (CO2). The cement placement with CT is critical to prevent flash reaction with the kill fluid and to minimize the volume of contaminated cement. The cement was placed successfully and tested in accordance with the Brunei Shell Petroleum requirement. The wells were safely secured and ready for the planned P&A process. These operations marked the first successful operation on high-pressure, tight gas wells with no surface facilities on the platform within a sensitive environment. The use of a mobile storage support vessel enabled the wells to be killed successfully. This approach demonstrates that a similar method and similar planning can be used to safely and economically perform future interventions.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信