使用Scrum方法进行软件开发中的成熟度级别分析:Xyz初创公司案例研究

Naomi Panjaitan, B. Hardian
{"title":"使用Scrum方法进行软件开发中的成熟度级别分析:Xyz初创公司案例研究","authors":"Naomi Panjaitan, B. Hardian","doi":"10.59888/ajosh.v1i10.67","DOIUrl":null,"url":null,"abstract":"Startup XYZ is a pioneer in the EWA (Earned Wage Access) application in Indonesia which has been around since 2020. The main vision of Startup XYZ is to build financial health for low and middle income workers in Asia. In achieving its vision and facing current competitors, Startup XYZ continues to innovate to meet market needs. XYZ startup uses the Scrum methodology in the application development process. It was found that there were several problems that occurred, namely the development process was not optimal, causing the release plan to be delayed. This problem is considered to affect the quality and performance of Startup XYZ. This study aims to measure the scrum maturity level of Startup XYZ so that recommendations can be made to improve the maturity level. Data were obtained from several sources such as interviews, observations, and questionnaires that adapted the Scrum Maturity Assessment. The results obtained are calculated using the KPA Rating based on the Agile Maturity Model. Recapitulating the calculation of the maturity level of the scrum methodology, it is known that XYZ startup is still at level 2 with the Largely Achieved category. After obtaining the level of maturity for each level, recommendations are made based on the results of observations, Scrum Guide 2020, Scrum Essentials and SBOK v3. It was found that there were 24 recommendations to improve the maturity level of Startup XYZ","PeriodicalId":92175,"journal":{"name":"Asian journal of research in social sciences and humanities","volume":"32 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-07-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Maturity Level Analysis in Software Development Using Scrum Methodology: Xyz Startup Case Study\",\"authors\":\"Naomi Panjaitan, B. Hardian\",\"doi\":\"10.59888/ajosh.v1i10.67\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Startup XYZ is a pioneer in the EWA (Earned Wage Access) application in Indonesia which has been around since 2020. The main vision of Startup XYZ is to build financial health for low and middle income workers in Asia. In achieving its vision and facing current competitors, Startup XYZ continues to innovate to meet market needs. XYZ startup uses the Scrum methodology in the application development process. It was found that there were several problems that occurred, namely the development process was not optimal, causing the release plan to be delayed. This problem is considered to affect the quality and performance of Startup XYZ. This study aims to measure the scrum maturity level of Startup XYZ so that recommendations can be made to improve the maturity level. Data were obtained from several sources such as interviews, observations, and questionnaires that adapted the Scrum Maturity Assessment. The results obtained are calculated using the KPA Rating based on the Agile Maturity Model. Recapitulating the calculation of the maturity level of the scrum methodology, it is known that XYZ startup is still at level 2 with the Largely Achieved category. After obtaining the level of maturity for each level, recommendations are made based on the results of observations, Scrum Guide 2020, Scrum Essentials and SBOK v3. It was found that there were 24 recommendations to improve the maturity level of Startup XYZ\",\"PeriodicalId\":92175,\"journal\":{\"name\":\"Asian journal of research in social sciences and humanities\",\"volume\":\"32 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-25\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Asian journal of research in social sciences and humanities\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.59888/ajosh.v1i10.67\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Asian journal of research in social sciences and humanities","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.59888/ajosh.v1i10.67","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

Startup XYZ是印尼EWA (Earned Wage Access)应用程序的先驱,该应用程序自2020年以来一直存在。Startup XYZ的主要愿景是为亚洲的中低收入工人建立财务健康。为了实现其愿景并面对当前的竞争对手,Startup XYZ不断创新以满足市场需求。XYZ初创公司在应用程序开发过程中使用Scrum方法。发现出现了几个问题,即开发过程不优化,导致发布计划延迟。这个问题被认为会影响Startup XYZ的质量和性能。这项研究的目的是衡量Startup XYZ的scrum成熟度水平,以便可以提出建议来提高成熟度水平。数据是从几个来源获得的,比如采访、观察和问卷调查,这些都适应了Scrum成熟度评估。使用基于敏捷成熟度模型的KPA评级来计算得到的结果。概括一下scrum方法成熟度级别的计算,我们知道XYZ初创公司仍然处于“大部分已完成”类别的第2级。在获得每个级别的成熟度级别后,根据观察结果、Scrum Guide 2020、Scrum Essentials和SBOK v3提出建议。结果发现,有24条建议可以提高Startup XYZ的成熟度
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Maturity Level Analysis in Software Development Using Scrum Methodology: Xyz Startup Case Study
Startup XYZ is a pioneer in the EWA (Earned Wage Access) application in Indonesia which has been around since 2020. The main vision of Startup XYZ is to build financial health for low and middle income workers in Asia. In achieving its vision and facing current competitors, Startup XYZ continues to innovate to meet market needs. XYZ startup uses the Scrum methodology in the application development process. It was found that there were several problems that occurred, namely the development process was not optimal, causing the release plan to be delayed. This problem is considered to affect the quality and performance of Startup XYZ. This study aims to measure the scrum maturity level of Startup XYZ so that recommendations can be made to improve the maturity level. Data were obtained from several sources such as interviews, observations, and questionnaires that adapted the Scrum Maturity Assessment. The results obtained are calculated using the KPA Rating based on the Agile Maturity Model. Recapitulating the calculation of the maturity level of the scrum methodology, it is known that XYZ startup is still at level 2 with the Largely Achieved category. After obtaining the level of maturity for each level, recommendations are made based on the results of observations, Scrum Guide 2020, Scrum Essentials and SBOK v3. It was found that there were 24 recommendations to improve the maturity level of Startup XYZ
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信