组织约束和资金约束下的购物中心建设优化

I. Meneiliuk, O. Nikiforov
{"title":"组织约束和资金约束下的购物中心建设优化","authors":"I. Meneiliuk, O. Nikiforov","doi":"10.26906/znp.2019.52.1699","DOIUrl":null,"url":null,"abstract":"The article presents the results of optimizing the construction duration of the object and the average monthly financing intensityof the shopping center construction under organizational and financial constraints, namely: the work processes alignment– 68-76%; the maximum monthly financing intensity – 40 million UAN; number of work brigades – 1-2; the maximum constructionduration – 360 days. There were developed the method for optimizing and the results of numerical modeling of organizationaland financial decisions were obtained. The most efficient models of construction were identified by graphicalway under limited conditions of their implementation.","PeriodicalId":32910,"journal":{"name":"Zbirnik naukovikh prats'' Seriia Galuzeve mashinobuduvannia budivnitstvo","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2019-07-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Optimization of shopping center construction under organizational and financial constraints\",\"authors\":\"I. Meneiliuk, O. Nikiforov\",\"doi\":\"10.26906/znp.2019.52.1699\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The article presents the results of optimizing the construction duration of the object and the average monthly financing intensityof the shopping center construction under organizational and financial constraints, namely: the work processes alignment– 68-76%; the maximum monthly financing intensity – 40 million UAN; number of work brigades – 1-2; the maximum constructionduration – 360 days. There were developed the method for optimizing and the results of numerical modeling of organizationaland financial decisions were obtained. The most efficient models of construction were identified by graphicalway under limited conditions of their implementation.\",\"PeriodicalId\":32910,\"journal\":{\"name\":\"Zbirnik naukovikh prats'' Seriia Galuzeve mashinobuduvannia budivnitstvo\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-07-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Zbirnik naukovikh prats'' Seriia Galuzeve mashinobuduvannia budivnitstvo\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.26906/znp.2019.52.1699\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Zbirnik naukovikh prats'' Seriia Galuzeve mashinobuduvannia budivnitstvo","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.26906/znp.2019.52.1699","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文给出了组织约束和财务约束下购物中心建设目标工期和月平均融资强度的优化结果,即:工作流程一致性- 68-76%;每月最大融资强度- 4000万人民币;工旅数量- 1-2个;最长施工时间- 360天。提出了优化方法,并对组织决策和财务决策进行了数值模拟。在有限的实施条件下,以图形方式确定了最有效的构建模型。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Optimization of shopping center construction under organizational and financial constraints
The article presents the results of optimizing the construction duration of the object and the average monthly financing intensityof the shopping center construction under organizational and financial constraints, namely: the work processes alignment– 68-76%; the maximum monthly financing intensity – 40 million UAN; number of work brigades – 1-2; the maximum constructionduration – 360 days. There were developed the method for optimizing and the results of numerical modeling of organizationaland financial decisions were obtained. The most efficient models of construction were identified by graphicalway under limited conditions of their implementation.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
审稿时长
24 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信