{"title":"新地铁下穿既有地铁站的实时安全监测","authors":"Lihong Chen, Fei Chen, Li Wu","doi":"10.1109/ICETCE.2011.5775329","DOIUrl":null,"url":null,"abstract":"As more and more metros were built in modern city, the new constructing metro lines will be inevitably crossing the existing one. During the construction process of the new metro line, excavation may lead to the displacement of the existing tunnels and the tracks, sequentially affect the travel of trains, so monitoring on the new constructing lines is very important. The traditional manual monitoring techniques can be not available due to the busy traffic. Therefore, automatic remote real-time monitoring system should be applied to supervise the deformation of structures and tracks of existing metro 24-hours/7 days. During the construction of new metro station under-pass a existing station in Beijing, DAMS—IV intelligent distributed safety monitoring system was adopted, 84 hydro-static levelings and other instruments were installed to monitor the exiting station structures and the tracks; The observed data do help to adjust the construction plan and grouting strength to make sure that the deformation of the existing station and tracks was under control.","PeriodicalId":6340,"journal":{"name":"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)","volume":"44 1","pages":"6767-6770"},"PeriodicalIF":0.0000,"publicationDate":"2011-04-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Real-time safety monitoring on existing metro station underpassed by new metro\",\"authors\":\"Lihong Chen, Fei Chen, Li Wu\",\"doi\":\"10.1109/ICETCE.2011.5775329\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"As more and more metros were built in modern city, the new constructing metro lines will be inevitably crossing the existing one. During the construction process of the new metro line, excavation may lead to the displacement of the existing tunnels and the tracks, sequentially affect the travel of trains, so monitoring on the new constructing lines is very important. The traditional manual monitoring techniques can be not available due to the busy traffic. Therefore, automatic remote real-time monitoring system should be applied to supervise the deformation of structures and tracks of existing metro 24-hours/7 days. During the construction of new metro station under-pass a existing station in Beijing, DAMS—IV intelligent distributed safety monitoring system was adopted, 84 hydro-static levelings and other instruments were installed to monitor the exiting station structures and the tracks; The observed data do help to adjust the construction plan and grouting strength to make sure that the deformation of the existing station and tracks was under control.\",\"PeriodicalId\":6340,\"journal\":{\"name\":\"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)\",\"volume\":\"44 1\",\"pages\":\"6767-6770\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-04-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICETCE.2011.5775329\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICETCE.2011.5775329","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

随着现代城市中越来越多的地铁建成,新建的地铁线路不可避免地要与现有的地铁线路交叉。在新建地铁线路的施工过程中,开挖会引起既有隧道和轨道的位移,进而影响列车的运行,因此对新建地铁线路的监测非常重要。由于交通繁忙,传统的人工监控技术无法发挥作用。因此,应采用自动远程实时监测系统对既有地铁结构和轨道的变形进行24小时/7天的监测。在北京某既有车站地下通道新建地铁车站施工过程中,采用DAMS-IV智能分布式安全监控系统,安装了84台静压水准仪等仪器,对现有车站结构和轨道进行监控;观测数据有助于调整施工方案和注浆强度,以确保现有车站和轨道的变形得到控制。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Real-time safety monitoring on existing metro station underpassed by new metro
As more and more metros were built in modern city, the new constructing metro lines will be inevitably crossing the existing one. During the construction process of the new metro line, excavation may lead to the displacement of the existing tunnels and the tracks, sequentially affect the travel of trains, so monitoring on the new constructing lines is very important. The traditional manual monitoring techniques can be not available due to the busy traffic. Therefore, automatic remote real-time monitoring system should be applied to supervise the deformation of structures and tracks of existing metro 24-hours/7 days. During the construction of new metro station under-pass a existing station in Beijing, DAMS—IV intelligent distributed safety monitoring system was adopted, 84 hydro-static levelings and other instruments were installed to monitor the exiting station structures and the tracks; The observed data do help to adjust the construction plan and grouting strength to make sure that the deformation of the existing station and tracks was under control.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信