{"title":"合同条款的效用与价值:以室内承包商为例","authors":"N. Suriyanon, Pitch Sutheerawatthana, M. Kaewmoracharoen, Veera Klansai","doi":"10.5130/ajceb.v23i1/2.8532","DOIUrl":null,"url":null,"abstract":"This study applied the conjoint analysis technique to appraise the utility of interior contractors' contract terms and project price conditions, the sample group comprising 112 interior contractors working in 12 shopping centers of a public company in Thailand. The results showed that the advance payment term, the period of an interim payment term, the period to make a payment term, and the project price conditions had average utility ratios (ratio of its utility to the total utility) of 28.53%, 20.24%, 20.41%, and 25.87%, respectively. These results confirmed that each of these three contract terms are as important to interior contractors as the project price condition (no price reduction by 5% of the proposed price). This study also valued the three contract terms by comparing their utility with the utility of the project price condition. The values of the terms to the interior contractor were as follows: the value of the advance payment term varied between 0.00–11.67% of the proposed price; the value of the period of the interim payment term varied between 1.25–8.33% of the proposed price; and the value of the period to make a payment term varied between 2.00–11.67% of the proposed price. The value of all three contract terms varied between 12.00–20.00% of the proposed price. The insights into the utility and value of these three contract terms from this study could aid project owners or tenants of shopping centers in project price negotiations.","PeriodicalId":51729,"journal":{"name":"Construction Economics and Building","volume":null,"pages":null},"PeriodicalIF":1.8000,"publicationDate":"2023-07-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The utility and value of contract terms: a case study on interior contractors\",\"authors\":\"N. Suriyanon, Pitch Sutheerawatthana, M. Kaewmoracharoen, Veera Klansai\",\"doi\":\"10.5130/ajceb.v23i1/2.8532\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study applied the conjoint analysis technique to appraise the utility of interior contractors' contract terms and project price conditions, the sample group comprising 112 interior contractors working in 12 shopping centers of a public company in Thailand. The results showed that the advance payment term, the period of an interim payment term, the period to make a payment term, and the project price conditions had average utility ratios (ratio of its utility to the total utility) of 28.53%, 20.24%, 20.41%, and 25.87%, respectively. These results confirmed that each of these three contract terms are as important to interior contractors as the project price condition (no price reduction by 5% of the proposed price). This study also valued the three contract terms by comparing their utility with the utility of the project price condition. The values of the terms to the interior contractor were as follows: the value of the advance payment term varied between 0.00–11.67% of the proposed price; the value of the period of the interim payment term varied between 1.25–8.33% of the proposed price; and the value of the period to make a payment term varied between 2.00–11.67% of the proposed price. The value of all three contract terms varied between 12.00–20.00% of the proposed price. The insights into the utility and value of these three contract terms from this study could aid project owners or tenants of shopping centers in project price negotiations.\",\"PeriodicalId\":51729,\"journal\":{\"name\":\"Construction Economics and Building\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.8000,\"publicationDate\":\"2023-07-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Construction Economics and Building\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5130/ajceb.v23i1/2.8532\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction Economics and Building","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5130/ajceb.v23i1/2.8532","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 0

摘要

本研究应用联合分析技术来评估室内承包商的合同条款和项目价格条件的效用,样本组包括112名室内承包商在泰国一家上市公司的12个购物中心工作。结果表明,预付款期限、中期付款期限、付款期限和项目价格条件的平均效用比(其效用与总效用之比)分别为28.53%、20.24%、20.41%和25.87%。这些结果证实,这三个合同条款中的每一个都与项目价格条件(不降价5%的建议价格)对室内承包商同样重要。本研究亦通过比较三种合约条款的效用与项目价格条件的效用来评估合约条款的价值。这些条款对室内承包商的价值如下:预付款条款的价值在建议价格的0.00-11.67%之间变化;中期付款期限期间的价值为建议价格的1.25-8.33%;而支付期限的价值在建议价格的2.00-11.67%之间变化。所有三个合同条款的价值在建议价格的12.00-20.00%之间变化。本研究对这三种合约条款的效用与价值的洞见,可协助项目业主或购物中心租户进行项目价格谈判。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
The utility and value of contract terms: a case study on interior contractors
This study applied the conjoint analysis technique to appraise the utility of interior contractors' contract terms and project price conditions, the sample group comprising 112 interior contractors working in 12 shopping centers of a public company in Thailand. The results showed that the advance payment term, the period of an interim payment term, the period to make a payment term, and the project price conditions had average utility ratios (ratio of its utility to the total utility) of 28.53%, 20.24%, 20.41%, and 25.87%, respectively. These results confirmed that each of these three contract terms are as important to interior contractors as the project price condition (no price reduction by 5% of the proposed price). This study also valued the three contract terms by comparing their utility with the utility of the project price condition. The values of the terms to the interior contractor were as follows: the value of the advance payment term varied between 0.00–11.67% of the proposed price; the value of the period of the interim payment term varied between 1.25–8.33% of the proposed price; and the value of the period to make a payment term varied between 2.00–11.67% of the proposed price. The value of all three contract terms varied between 12.00–20.00% of the proposed price. The insights into the utility and value of these three contract terms from this study could aid project owners or tenants of shopping centers in project price negotiations.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
3.80
自引率
6.20%
发文量
0
审稿时长
20 weeks
期刊介绍: Construction Economics and Building (formerly known as the Australasian Journal of Construction Economics and Building [AJCEB]) is a peer reviewed, open access publication for original research into all aspects of the economics and management of building and construction, quantity surveying and property management as well as construction and property education. It is free for authors, readers and libraries.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信