由于井导管套管失效,海上井口平台结构设计的新建议:基于实际发现的研究结果

Abdul Gaffur Varikkodan, A. Sarkar, Mohammed Eissa Mohammed
{"title":"由于井导管套管失效,海上井口平台结构设计的新建议:基于实际发现的研究结果","authors":"Abdul Gaffur Varikkodan, A. Sarkar, Mohammed Eissa Mohammed","doi":"10.2118/207632-ms","DOIUrl":null,"url":null,"abstract":"\n Detailed study on structurally failed well conductors on offshore wellhead platforms lead us to believe that existing assumptions of conductors transfer only lateral loadings to wellhead platforms while entire well vertical loading will be carried by conductor itself; could be wrong. The well conductors could become ‘forced’ to carry a very large vertical loads incase the conductors are structurally failed; especially once exceeded its original design life. As such, some new considerations during the wellhead platform design, which need to be followed, are recommended here. These are to cater any catastrophic eventuality of conductor failures which will restrain further collapse of the conductors or to avoid any progressive collapse of the platform. The recommendations are from a study based on actual findings observed recently in the offshore field.\n The connection between conductors and platforms are conventionally designed as guided based on the load transfer assumptions. That is the huge vertical loadings from internal conductor casings and associated items were not a concern for platform design structural engineers, traditionally, and as such the conductors were designed to be structurally connected to the wellhead platforms using vertical guides. Due to extended design service life of platforms, in many cases the design life went up to two times of their original design life, severe degradation of structural integrity of the conductors were observed in the field. Structural analysis and assessment were carried out on many old intact and failed conductors, in the offshore field, in order to assess its structural and loading behavior with respect to supporting wellhead platforms.\n The study provided that the failed conductors were leaning / collapsing to the wellhead platform resulting in transferring a huge vertical loads which originally were designed to be carried by conductors alone. This huge transfer of vertical loads from conductor to the platform was unexpected and was not considered in platforms original design. Therefore, the platform should have sufficient structural strength to cater such extreme eventuality to avoid the risk of complete collapse. A risk assessment of a tilted / failed conductors indicated that the consequence of total failure of a conductor could be catastrophic in case the platform failed to resist the collapsing conductors. This paper presents the details of the study carried out on aged wellhead platforms, having failed long serving conductors, in Giant offshore field, Abu Dhabi, along with details of new recommendations to be followed while designing new wellhead platforms.\n The paper also recommends the structural design consideration to be followed while designing wellhead platforms in-case a conductor repair is necessitated in future.","PeriodicalId":10967,"journal":{"name":"Day 1 Mon, November 15, 2021","volume":"16 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-12-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"New Recommendations for Offshore Wellhead Platform Structural Design Due to Well Conductor Casings Failures: Outcome of a Study Based on Actual Findings\",\"authors\":\"Abdul Gaffur Varikkodan, A. Sarkar, Mohammed Eissa Mohammed\",\"doi\":\"10.2118/207632-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Detailed study on structurally failed well conductors on offshore wellhead platforms lead us to believe that existing assumptions of conductors transfer only lateral loadings to wellhead platforms while entire well vertical loading will be carried by conductor itself; could be wrong. The well conductors could become ‘forced’ to carry a very large vertical loads incase the conductors are structurally failed; especially once exceeded its original design life. As such, some new considerations during the wellhead platform design, which need to be followed, are recommended here. These are to cater any catastrophic eventuality of conductor failures which will restrain further collapse of the conductors or to avoid any progressive collapse of the platform. The recommendations are from a study based on actual findings observed recently in the offshore field.\\n The connection between conductors and platforms are conventionally designed as guided based on the load transfer assumptions. That is the huge vertical loadings from internal conductor casings and associated items were not a concern for platform design structural engineers, traditionally, and as such the conductors were designed to be structurally connected to the wellhead platforms using vertical guides. Due to extended design service life of platforms, in many cases the design life went up to two times of their original design life, severe degradation of structural integrity of the conductors were observed in the field. Structural analysis and assessment were carried out on many old intact and failed conductors, in the offshore field, in order to assess its structural and loading behavior with respect to supporting wellhead platforms.\\n The study provided that the failed conductors were leaning / collapsing to the wellhead platform resulting in transferring a huge vertical loads which originally were designed to be carried by conductors alone. This huge transfer of vertical loads from conductor to the platform was unexpected and was not considered in platforms original design. Therefore, the platform should have sufficient structural strength to cater such extreme eventuality to avoid the risk of complete collapse. A risk assessment of a tilted / failed conductors indicated that the consequence of total failure of a conductor could be catastrophic in case the platform failed to resist the collapsing conductors. This paper presents the details of the study carried out on aged wellhead platforms, having failed long serving conductors, in Giant offshore field, Abu Dhabi, along with details of new recommendations to be followed while designing new wellhead platforms.\\n The paper also recommends the structural design consideration to be followed while designing wellhead platforms in-case a conductor repair is necessitated in future.\",\"PeriodicalId\":10967,\"journal\":{\"name\":\"Day 1 Mon, November 15, 2021\",\"volume\":\"16 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-12-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Mon, November 15, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/207632-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, November 15, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/207632-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

对海上井口平台结构失效的井导管的详细研究表明,现有的假设认为,导管只将横向载荷传递给井口平台,而整个井的垂直载荷将由导管本身承担;可能是错的。如果套管发生结构故障,套管可能会“被迫”承受很大的垂直载荷;特别是一旦超过其原有设计寿命。因此,在井口平台设计过程中,需要遵循一些新的考虑因素。这些是为了应付任何灾难性的导体故障,这将限制导体进一步倒塌或避免任何平台的渐进倒塌。这些建议来自一项基于最近在海上油田观察到的实际发现的研究。导体和平台之间的连接通常是根据负载传递假设设计的。传统上,平台设计结构工程师并不关心内部导体套管和相关物品的巨大垂直载荷,因此,导体被设计为使用垂直导向装置与井口平台相连。由于平台设计使用寿命的延长,在很多情况下,设计寿命达到了原来设计寿命的两倍,现场观察到导体结构完整性严重退化。为了评估其在支撑井口平台上的结构和载荷行为,对海上油田许多老的完整和失效的导管进行了结构分析和评估。研究表明,失效的导体正在向井口平台倾斜/坍塌,导致巨大的垂直载荷转移,而这些载荷原本是由导体单独承担的。这种巨大的垂直载荷从导体到平台的转移是意想不到的,在平台的原始设计中没有考虑到。因此,平台应具有足够的结构强度来应对这种极端情况,以避免完全倒塌的风险。对倾斜/失效导体的风险评估表明,如果平台无法抵御导体的坍塌,导体完全失效的后果可能是灾难性的。本文介绍了在阿布扎比Giant海上油田的老化井口平台上进行的研究的细节,以及在设计新井口平台时应遵循的新建议的细节。本文还提出了今后在设计井口平台时需要考虑的结构设计问题。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
New Recommendations for Offshore Wellhead Platform Structural Design Due to Well Conductor Casings Failures: Outcome of a Study Based on Actual Findings
Detailed study on structurally failed well conductors on offshore wellhead platforms lead us to believe that existing assumptions of conductors transfer only lateral loadings to wellhead platforms while entire well vertical loading will be carried by conductor itself; could be wrong. The well conductors could become ‘forced’ to carry a very large vertical loads incase the conductors are structurally failed; especially once exceeded its original design life. As such, some new considerations during the wellhead platform design, which need to be followed, are recommended here. These are to cater any catastrophic eventuality of conductor failures which will restrain further collapse of the conductors or to avoid any progressive collapse of the platform. The recommendations are from a study based on actual findings observed recently in the offshore field. The connection between conductors and platforms are conventionally designed as guided based on the load transfer assumptions. That is the huge vertical loadings from internal conductor casings and associated items were not a concern for platform design structural engineers, traditionally, and as such the conductors were designed to be structurally connected to the wellhead platforms using vertical guides. Due to extended design service life of platforms, in many cases the design life went up to two times of their original design life, severe degradation of structural integrity of the conductors were observed in the field. Structural analysis and assessment were carried out on many old intact and failed conductors, in the offshore field, in order to assess its structural and loading behavior with respect to supporting wellhead platforms. The study provided that the failed conductors were leaning / collapsing to the wellhead platform resulting in transferring a huge vertical loads which originally were designed to be carried by conductors alone. This huge transfer of vertical loads from conductor to the platform was unexpected and was not considered in platforms original design. Therefore, the platform should have sufficient structural strength to cater such extreme eventuality to avoid the risk of complete collapse. A risk assessment of a tilted / failed conductors indicated that the consequence of total failure of a conductor could be catastrophic in case the platform failed to resist the collapsing conductors. This paper presents the details of the study carried out on aged wellhead platforms, having failed long serving conductors, in Giant offshore field, Abu Dhabi, along with details of new recommendations to be followed while designing new wellhead platforms. The paper also recommends the structural design consideration to be followed while designing wellhead platforms in-case a conductor repair is necessitated in future.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信