设计和建造基础设施项目价值管理的关键成功因素框架

Q2 Engineering
Susy F. Rostiyanti, Acinia Nindartin, Ju-Hyung Kim
{"title":"设计和建造基础设施项目价值管理的关键成功因素框架","authors":"Susy F. Rostiyanti, Acinia Nindartin, Ju-Hyung Kim","doi":"10.22452/jdbe.vol23no1.2","DOIUrl":null,"url":null,"abstract":"The Design Build (DB) approach is gaining popularity in many countries as it allows a single entity to handle both design and construction, making it a preferred choice for infrastructure projects. With the design process carried out by a team to achieve design constructability, implementing Value Management (VM) in Design Build projects is advantageous and can lead to cost-effective designs. While most studies have concentrated on identifying the important criteria that lead to the effective deployment of VM in infrastructure projects in general, the success factors of VM in DB delivery systems remain unknown. This study aims to identify the critical success factors (CSFs) in the three main stages of the VM workshop and their supporting factors in infrastructure projects delivered under DB system. To achieve the research aim, a questionnaire was distributed to DB contractors involved in infrastructure projects in Indonesia. The Relative Important Index approach was applied to 28 factors, and the analysis revealed the CSFs for each stage of the VM workshop, along with a critical supporting factor. The analysis revealed that there are three CSFs for the pre-study and study stages and one for the post-study stage. The identified CSFs provide a framework for VM success in Design Build projects. The three CSFs in the pre-study stage relate to VM objectives, project information completeness, and personnel involved in the VM workshop. At the study stage, VM success depends on the VM process, the development of alternative designs, and the VM team's innovation. In the post-study stage, VM success is linked to the VM implementation process and developing an execution plan. The cooperation of all stakeholders in implementing the VM workshop results is a critical supporting factor for VM in a DB project.","PeriodicalId":37954,"journal":{"name":"Journal of Design and Built Environment","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-07-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Critical Success Factors Framework of Value Management for Design and Build Infrastructure Projects\",\"authors\":\"Susy F. Rostiyanti, Acinia Nindartin, Ju-Hyung Kim\",\"doi\":\"10.22452/jdbe.vol23no1.2\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Design Build (DB) approach is gaining popularity in many countries as it allows a single entity to handle both design and construction, making it a preferred choice for infrastructure projects. With the design process carried out by a team to achieve design constructability, implementing Value Management (VM) in Design Build projects is advantageous and can lead to cost-effective designs. While most studies have concentrated on identifying the important criteria that lead to the effective deployment of VM in infrastructure projects in general, the success factors of VM in DB delivery systems remain unknown. This study aims to identify the critical success factors (CSFs) in the three main stages of the VM workshop and their supporting factors in infrastructure projects delivered under DB system. To achieve the research aim, a questionnaire was distributed to DB contractors involved in infrastructure projects in Indonesia. The Relative Important Index approach was applied to 28 factors, and the analysis revealed the CSFs for each stage of the VM workshop, along with a critical supporting factor. The analysis revealed that there are three CSFs for the pre-study and study stages and one for the post-study stage. The identified CSFs provide a framework for VM success in Design Build projects. The three CSFs in the pre-study stage relate to VM objectives, project information completeness, and personnel involved in the VM workshop. At the study stage, VM success depends on the VM process, the development of alternative designs, and the VM team's innovation. In the post-study stage, VM success is linked to the VM implementation process and developing an execution plan. The cooperation of all stakeholders in implementing the VM workshop results is a critical supporting factor for VM in a DB project.\",\"PeriodicalId\":37954,\"journal\":{\"name\":\"Journal of Design and Built Environment\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-14\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Design and Built Environment\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.22452/jdbe.vol23no1.2\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"Engineering\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Design and Built Environment","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.22452/jdbe.vol23no1.2","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"Engineering","Score":null,"Total":0}
引用次数: 0

摘要

设计建造(DB)方法在许多国家越来越受欢迎,因为它允许一个实体处理设计和施工,使其成为基础设施项目的首选。设计过程由一个团队进行,以实现设计的可构造性,在设计构建项目中实施价值管理(VM)是有利的,可以导致具有成本效益的设计。虽然大多数研究都集中在确定导致VM在基础设施项目中有效部署的重要标准,但VM在DB交付系统中的成功因素仍然未知。本研究旨在确定虚拟机研讨会三个主要阶段的关键成功因素(CSFs)及其在数据库系统下交付的基础设施项目中的支持因素。为了达到研究目的,向参与印度尼西亚基础设施项目的DB承包商分发了一份调查问卷。相对重要指数方法应用于28个因素,分析揭示了虚拟机研讨会每个阶段的CSFs,以及一个关键的支持因素。分析显示,研究前和研究阶段有三个CSFs,研究后阶段有一个CSFs。确定的csf为VM在设计构建项目中的成功提供了一个框架。预研究阶段的三个CSFs涉及虚拟现实目标、项目信息完整性和虚拟现实研讨会的人员。在研究阶段,虚拟机的成功取决于虚拟机过程、替代设计的开发和虚拟机团队的创新。在后期研究阶段,虚拟机的成功与虚拟机的实施过程和制定执行计划有关。所有利益相关者在实施VM研讨会成果方面的合作是数据库项目中VM的关键支持因素。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Critical Success Factors Framework of Value Management for Design and Build Infrastructure Projects
The Design Build (DB) approach is gaining popularity in many countries as it allows a single entity to handle both design and construction, making it a preferred choice for infrastructure projects. With the design process carried out by a team to achieve design constructability, implementing Value Management (VM) in Design Build projects is advantageous and can lead to cost-effective designs. While most studies have concentrated on identifying the important criteria that lead to the effective deployment of VM in infrastructure projects in general, the success factors of VM in DB delivery systems remain unknown. This study aims to identify the critical success factors (CSFs) in the three main stages of the VM workshop and their supporting factors in infrastructure projects delivered under DB system. To achieve the research aim, a questionnaire was distributed to DB contractors involved in infrastructure projects in Indonesia. The Relative Important Index approach was applied to 28 factors, and the analysis revealed the CSFs for each stage of the VM workshop, along with a critical supporting factor. The analysis revealed that there are three CSFs for the pre-study and study stages and one for the post-study stage. The identified CSFs provide a framework for VM success in Design Build projects. The three CSFs in the pre-study stage relate to VM objectives, project information completeness, and personnel involved in the VM workshop. At the study stage, VM success depends on the VM process, the development of alternative designs, and the VM team's innovation. In the post-study stage, VM success is linked to the VM implementation process and developing an execution plan. The cooperation of all stakeholders in implementing the VM workshop results is a critical supporting factor for VM in a DB project.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Journal of Design and Built Environment
Journal of Design and Built Environment Engineering-Architecture
CiteScore
1.70
自引率
0.00%
发文量
7
审稿时长
16 weeks
期刊介绍: The Journal of Design and Built Environment (JDBE) is a SCOPUS-indexed and free open access publication by the Faculty of Built Environment, University of Malaya. Published biannually, JDBE usually contains four academic papers of wide-ranging topics reporting on issues in the built environment, i.e. architecture and design including landscape architecture, urban and regional planning and studies, building and quantity surveys and real estate studies and management.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信