阿曼苏丹国气田速度串研究案例研究

N. Janusz
{"title":"阿曼苏丹国气田速度串研究案例研究","authors":"N. Janusz","doi":"10.2118/200241-ms","DOIUrl":null,"url":null,"abstract":"\n Petroleum Development Oman operates large amount of gas wells in Sultanate of Oman. Due to the liquid loading occurring in these ageing assets, PDO has already installed 110+ Velocity String completions in the various gas fields across the concession area. In the 2015–2019 period, 39 wells in the Saih Rawl field were retrofitted with Velocity Strings. This paper presents the integrated and standardized approach to Velocity String candidate selection and compares the production performance post-installation against the forecast.","PeriodicalId":10912,"journal":{"name":"Day 3 Wed, March 23, 2022","volume":"5 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-03-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Velocity Strings in Sultanate of Oman Gas Fields; A Case Study\",\"authors\":\"N. Janusz\",\"doi\":\"10.2118/200241-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Petroleum Development Oman operates large amount of gas wells in Sultanate of Oman. Due to the liquid loading occurring in these ageing assets, PDO has already installed 110+ Velocity String completions in the various gas fields across the concession area. In the 2015–2019 period, 39 wells in the Saih Rawl field were retrofitted with Velocity Strings. This paper presents the integrated and standardized approach to Velocity String candidate selection and compares the production performance post-installation against the forecast.\",\"PeriodicalId\":10912,\"journal\":{\"name\":\"Day 3 Wed, March 23, 2022\",\"volume\":\"5 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-03-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, March 23, 2022\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/200241-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, March 23, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/200241-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

阿曼石油开发公司在阿曼苏丹国经营着大量的气井。由于这些老化资产中出现了液体负荷,PDO已经在特许区域的各个气田安装了110多个速度管柱完井。在2015-2019年期间,Saih Rawl油田的39口井进行了Velocity管柱改造。本文介绍了速度管柱候选选择的集成和标准化方法,并将安装后的生产性能与预测进行了比较。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Velocity Strings in Sultanate of Oman Gas Fields; A Case Study
Petroleum Development Oman operates large amount of gas wells in Sultanate of Oman. Due to the liquid loading occurring in these ageing assets, PDO has already installed 110+ Velocity String completions in the various gas fields across the concession area. In the 2015–2019 period, 39 wells in the Saih Rawl field were retrofitted with Velocity Strings. This paper presents the integrated and standardized approach to Velocity String candidate selection and compares the production performance post-installation against the forecast.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信