论在居民点外敷设6 - 35kv电缆电力线路代替架空电力线路的便利性

Q3 Energy
M. Korotkevich, S. Podgaisky
{"title":"论在居民点外敷设6 - 35kv电缆电力线路代替架空电力线路的便利性","authors":"M. Korotkevich, S. Podgaisky","doi":"10.21122/1029-7448-2023-65-5-463-476","DOIUrl":null,"url":null,"abstract":". It is noted that at present, 10 and 35 kV overhead power transmission lines are being laid outside the settlements of the Republic of Belarus on reinforced concrete vibrated (10 kV) and centrifuged (35 kV) poles that are characterized by low reliability and damaging the environment (on account of alienation of land for poles, the need to make a wide clearing for laying in the forest, obstructions by poles and wires of lines to the operation of agricultural machinery, the danger of electric shock to personnel and the public). It is possible to avoid these disadvantages if, instead of overhead lines, power transmission cables with cables insulated by cross-linked polyethylene are used which are characterized by a very low failure flow parameter. Contrary to the prevailing opinion about the higher cost of cable power transmission lines compared to overhead ones of the same rated voltage, it turned out that, taking into account reliability, the cost of electricity lost in the lines for a year, damage to the environment and to the power system caused by the need to perform more expensive emergency repairs (as compared to a planned one), laying cable lines with three-core and single-core cables of a voltage of 10 and 35 kV instead of overhead cables outside the populated area is fairly justified. In this connection, the laying of three-core cables is more preferable. It should be also borne in mind that with an increase in the length of cable lines, the capacitive earth fault current increases, to compensate for which additional devices are needed to be installed in power centers, viz. arc-extinguishing reactors or resistors, accounting for the cost of which (up to 22 % of the cost of one kilometer of cable line) does not significantly affect the conclusions we have drawn regarding the effectiveness of using 6–35 kV cable power lines in an unpopulated area instead of overhead ones, however.","PeriodicalId":52141,"journal":{"name":"Energetika. Proceedings of CIS Higher Education Institutions and Power Engineering Associations","volume":"72 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-10-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"On the Expediency of Laying Cable Power Lines with a Voltage of 6–35 kV Outside Settlements Instead of Overhead Power Lines\",\"authors\":\"M. Korotkevich, S. Podgaisky\",\"doi\":\"10.21122/1029-7448-2023-65-5-463-476\",\"DOIUrl\":null,\"url\":null,\"abstract\":\". It is noted that at present, 10 and 35 kV overhead power transmission lines are being laid outside the settlements of the Republic of Belarus on reinforced concrete vibrated (10 kV) and centrifuged (35 kV) poles that are characterized by low reliability and damaging the environment (on account of alienation of land for poles, the need to make a wide clearing for laying in the forest, obstructions by poles and wires of lines to the operation of agricultural machinery, the danger of electric shock to personnel and the public). It is possible to avoid these disadvantages if, instead of overhead lines, power transmission cables with cables insulated by cross-linked polyethylene are used which are characterized by a very low failure flow parameter. Contrary to the prevailing opinion about the higher cost of cable power transmission lines compared to overhead ones of the same rated voltage, it turned out that, taking into account reliability, the cost of electricity lost in the lines for a year, damage to the environment and to the power system caused by the need to perform more expensive emergency repairs (as compared to a planned one), laying cable lines with three-core and single-core cables of a voltage of 10 and 35 kV instead of overhead cables outside the populated area is fairly justified. In this connection, the laying of three-core cables is more preferable. It should be also borne in mind that with an increase in the length of cable lines, the capacitive earth fault current increases, to compensate for which additional devices are needed to be installed in power centers, viz. arc-extinguishing reactors or resistors, accounting for the cost of which (up to 22 % of the cost of one kilometer of cable line) does not significantly affect the conclusions we have drawn regarding the effectiveness of using 6–35 kV cable power lines in an unpopulated area instead of overhead ones, however.\",\"PeriodicalId\":52141,\"journal\":{\"name\":\"Energetika. Proceedings of CIS Higher Education Institutions and Power Engineering Associations\",\"volume\":\"72 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-10-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Energetika. Proceedings of CIS Higher Education Institutions and Power Engineering Associations\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21122/1029-7448-2023-65-5-463-476\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"Energy\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Energetika. Proceedings of CIS Higher Education Institutions and Power Engineering Associations","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21122/1029-7448-2023-65-5-463-476","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"Energy","Score":null,"Total":0}
引用次数: 1

摘要

. 注意到,目前在白俄罗斯共和国住区外,10千伏和35千伏架空输电线路是在钢筋混凝土振动(10千伏)和离心(35千伏)电线杆上铺设的,其特点是可靠性低和破坏环境(由于电线杆需要占用土地,需要在森林中开辟广阔的空地,电线杆和电线阻碍了农业机械的操作)。对人员和公众有触电危险)。如果不使用架空线路,而是使用交联聚乙烯绝缘电缆的电力传输电缆,其特点是故障流量参数非常低,则有可能避免这些缺点。与普遍认为相同额定电压的电缆输电线路比架空线路成本更高的观点相反,事实证明,考虑到可靠性、线路一年的电力损失成本、需要进行更昂贵的紧急维修(与计划维修相比)对环境和电力系统造成的损害,在人口密集区以外敷设电压分别为10千伏和35千伏的三芯和单芯电缆,而不是架空电缆是相当合理的。在这种情况下,敷设三芯电缆更为可取。还应记住,随着电缆线路长度的增加,电容性接地故障电流也会增加,为此需要在电力中心安装额外的装置,即灭弧电抗器或电阻器。然而,考虑到其成本(高达一公里电缆成本的22%)并没有显著影响我们得出的结论,即在无人居住的地区使用6-35千伏电缆电力线而不是架空电缆的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
On the Expediency of Laying Cable Power Lines with a Voltage of 6–35 kV Outside Settlements Instead of Overhead Power Lines
. It is noted that at present, 10 and 35 kV overhead power transmission lines are being laid outside the settlements of the Republic of Belarus on reinforced concrete vibrated (10 kV) and centrifuged (35 kV) poles that are characterized by low reliability and damaging the environment (on account of alienation of land for poles, the need to make a wide clearing for laying in the forest, obstructions by poles and wires of lines to the operation of agricultural machinery, the danger of electric shock to personnel and the public). It is possible to avoid these disadvantages if, instead of overhead lines, power transmission cables with cables insulated by cross-linked polyethylene are used which are characterized by a very low failure flow parameter. Contrary to the prevailing opinion about the higher cost of cable power transmission lines compared to overhead ones of the same rated voltage, it turned out that, taking into account reliability, the cost of electricity lost in the lines for a year, damage to the environment and to the power system caused by the need to perform more expensive emergency repairs (as compared to a planned one), laying cable lines with three-core and single-core cables of a voltage of 10 and 35 kV instead of overhead cables outside the populated area is fairly justified. In this connection, the laying of three-core cables is more preferable. It should be also borne in mind that with an increase in the length of cable lines, the capacitive earth fault current increases, to compensate for which additional devices are needed to be installed in power centers, viz. arc-extinguishing reactors or resistors, accounting for the cost of which (up to 22 % of the cost of one kilometer of cable line) does not significantly affect the conclusions we have drawn regarding the effectiveness of using 6–35 kV cable power lines in an unpopulated area instead of overhead ones, however.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
1.60
自引率
0.00%
发文量
32
审稿时长
8 weeks
期刊介绍: The most important objectives of the journal are the generalization of scientific and practical achievements in the field of power engineering, increase scientific and practical skills as researchers and industry representatives. Scientific concept publications include the publication of a modern national and international research and achievements in areas such as general energetic, electricity, thermal energy, construction, environmental issues energy, energy economy, etc. The journal publishes the results of basic research and the advanced achievements of practices aimed at improving the efficiency of the functioning of the energy sector, reduction of losses in electricity and heat networks, improving the reliability of electrical protection systems, the stability of the energetic complex, literature reviews on a wide range of energy issues.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信