旋转设备切换仪表板

Khalid Alzahrani, Abdulaziz Alzahrany
{"title":"旋转设备切换仪表板","authors":"Khalid Alzahrani, Abdulaziz Alzahrany","doi":"10.2118/197477-ms","DOIUrl":null,"url":null,"abstract":"\n \n \n This Instruction outlines the procedures for testing spare pumps. The text includes: DefinitionResponsibilitySwitching IntervalsSwitching TimeSwitching ProcedureSwitchover Dashboard\n \n \n \n This procedure outlines switching between \"Main Pump\" (running pump) and \"spare pump\" (the one to be tested). All other type of equipment's (rotating and/or stationary) will be switchover based in the following:PM (Preventive Maintenance) program.Inspection ProgramTest and Inspection T&I program\n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n Switching between spare pumps and main ones shall be done once every 4 to 6 weeks to ensure the equipment availability and reliability. It shall coincide with the monthly vibration survey. For the compressor lube oil system, the functional test is preferred to be scheduled before a planned compressor shutdown.\n Discussions were held with the rotating equipment manufacturers, specialists and users to clarify all corrosion, electrical and mechanical concerns regarding the switching periods between alternate pieces of rotating equipment. The compilation of all of these discussions and concerns resulted in the following two basic guidelines which within themselves comprise the heart of the Rotating Equipment Operating Strategy.\n \n \n \n \n Equipment of this voltage type should be switched from the stand-by mode to the operational mode once per month.\n Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of one continuous hour every month.\n \n \n \n Equipment of this voltage type should be switched from the stand-by mode to the operational mode once every two weeks. This includes the switching between the main and auxiliary lube/seal oil pumps.\n Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of thirty continuous minutes every two weeks.\n \n \n \n \n \n Switching between critical pumps shall be conducted during the normal working days in day time where the support organizations are available.\n \n \n \n This RIM covers four different pump startup scenarios. Each one of these scenarios includes important checks and procedures that need to be followed to ensure a reliable pump start-up. Below you will find a detailed start-up procedure for each scenario. The procedure will be detailed but general, additional steps may be required for some particular process.\n \n \n \n \n \n Switchover = (Total Equipment comply with switchover/Equipment Schedule Switchover) X 100%, Target 90%\n Note:\n Switchover the pump:\n \n \n \n \n","PeriodicalId":11061,"journal":{"name":"Day 1 Mon, November 11, 2019","volume":"26 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Rotating Equipment Switchover Dashboard\",\"authors\":\"Khalid Alzahrani, Abdulaziz Alzahrany\",\"doi\":\"10.2118/197477-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n \\n \\n This Instruction outlines the procedures for testing spare pumps. The text includes: DefinitionResponsibilitySwitching IntervalsSwitching TimeSwitching ProcedureSwitchover Dashboard\\n \\n \\n \\n This procedure outlines switching between \\\"Main Pump\\\" (running pump) and \\\"spare pump\\\" (the one to be tested). All other type of equipment's (rotating and/or stationary) will be switchover based in the following:PM (Preventive Maintenance) program.Inspection ProgramTest and Inspection T&I program\\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n \\n Switching between spare pumps and main ones shall be done once every 4 to 6 weeks to ensure the equipment availability and reliability. It shall coincide with the monthly vibration survey. For the compressor lube oil system, the functional test is preferred to be scheduled before a planned compressor shutdown.\\n Discussions were held with the rotating equipment manufacturers, specialists and users to clarify all corrosion, electrical and mechanical concerns regarding the switching periods between alternate pieces of rotating equipment. The compilation of all of these discussions and concerns resulted in the following two basic guidelines which within themselves comprise the heart of the Rotating Equipment Operating Strategy.\\n \\n \\n \\n \\n Equipment of this voltage type should be switched from the stand-by mode to the operational mode once per month.\\n Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of one continuous hour every month.\\n \\n \\n \\n Equipment of this voltage type should be switched from the stand-by mode to the operational mode once every two weeks. This includes the switching between the main and auxiliary lube/seal oil pumps.\\n Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of thirty continuous minutes every two weeks.\\n \\n \\n \\n \\n \\n Switching between critical pumps shall be conducted during the normal working days in day time where the support organizations are available.\\n \\n \\n \\n This RIM covers four different pump startup scenarios. Each one of these scenarios includes important checks and procedures that need to be followed to ensure a reliable pump start-up. Below you will find a detailed start-up procedure for each scenario. The procedure will be detailed but general, additional steps may be required for some particular process.\\n \\n \\n \\n \\n \\n Switchover = (Total Equipment comply with switchover/Equipment Schedule Switchover) X 100%, Target 90%\\n Note:\\n Switchover the pump:\\n \\n \\n \\n \\n\",\"PeriodicalId\":11061,\"journal\":{\"name\":\"Day 1 Mon, November 11, 2019\",\"volume\":\"26 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-11-11\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Mon, November 11, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/197477-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, November 11, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/197477-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本说明书概述了测试备用泵的程序。文本包括:定义、职责、切换间隔、切换时间、切换程序、切换仪表板此程序概述了“主泵”(运行泵)和“备用泵”(待测泵)之间的切换。所有其他类型的设备(旋转和/或固定)将根据以下内容进行切换:PM(预防性维护)计划。为保证设备的可用性和可靠性,每4 - 6周应进行一次备用泵与主泵的切换。应与每月的振动测量相吻合。对于压缩机润滑油系统,建议在计划的压缩机停机前进行功能试验。与旋转设备制造商、专家和用户进行了讨论,以澄清有关旋转设备交替部件之间切换期间的所有腐蚀、电气和机械问题。所有这些讨论和关切的汇编产生了以下两个基本准则,它们本身构成了旋转设备操作战略的核心。这种电压类型的设备应每月从待机模式切换到工作模式一次。注:除操作不需要的任何备用设备外,每月应至少连续运行一小时。这种电压类型的设备应每两周从待机模式切换到工作模式一次。这包括主、辅润滑/密封油泵之间的切换。注:除操作不需要的任何备用设备外,每两周应至少连续运行30分钟。关键泵之间的切换应在正常工作日进行,在白天支持组织可用的情况下。该RIM涵盖了四种不同的泵启动场景。每种情况都包括重要的检查和程序,需要遵循这些检查和程序,以确保泵的可靠启动。您将在下面找到每个场景的详细启动过程。该程序将是详细的,但一般的,一些特定的过程可能需要额外的步骤。切换=(总设备符合切换/设备计划切换)X 100%,目标90%注:泵切换:
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Rotating Equipment Switchover Dashboard
This Instruction outlines the procedures for testing spare pumps. The text includes: DefinitionResponsibilitySwitching IntervalsSwitching TimeSwitching ProcedureSwitchover Dashboard This procedure outlines switching between "Main Pump" (running pump) and "spare pump" (the one to be tested). All other type of equipment's (rotating and/or stationary) will be switchover based in the following:PM (Preventive Maintenance) program.Inspection ProgramTest and Inspection T&I program Switching between spare pumps and main ones shall be done once every 4 to 6 weeks to ensure the equipment availability and reliability. It shall coincide with the monthly vibration survey. For the compressor lube oil system, the functional test is preferred to be scheduled before a planned compressor shutdown. Discussions were held with the rotating equipment manufacturers, specialists and users to clarify all corrosion, electrical and mechanical concerns regarding the switching periods between alternate pieces of rotating equipment. The compilation of all of these discussions and concerns resulted in the following two basic guidelines which within themselves comprise the heart of the Rotating Equipment Operating Strategy. Equipment of this voltage type should be switched from the stand-by mode to the operational mode once per month. Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of one continuous hour every month. Equipment of this voltage type should be switched from the stand-by mode to the operational mode once every two weeks. This includes the switching between the main and auxiliary lube/seal oil pumps. Note: Excluding any stand-by equipment that is not required by Operations should be run a minimum of thirty continuous minutes every two weeks. Switching between critical pumps shall be conducted during the normal working days in day time where the support organizations are available. This RIM covers four different pump startup scenarios. Each one of these scenarios includes important checks and procedures that need to be followed to ensure a reliable pump start-up. Below you will find a detailed start-up procedure for each scenario. The procedure will be detailed but general, additional steps may be required for some particular process. Switchover = (Total Equipment comply with switchover/Equipment Schedule Switchover) X 100%, Target 90% Note: Switchover the pump:
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信