{"title":"挖掘复杂成熟河流储层潜力降低地质不确定性——以渤海湾D-X油田再开发规划为例","authors":"Yifan He","doi":"10.2523/IPTC-19415-MS","DOIUrl":null,"url":null,"abstract":"\n D-X oilfield implemented an infill adjustment from 2013 to 2015, adding 101 development wells, two central processing platforms and two wellhead platforms.\n After the adjustment, the oil field greatly improved the engineering processing capacity, but it had also entered a period of rapid decline. In order to mitigate the decline and improve the recovery rate, 65 adjustment wells were implemented in this oilfield after the first adjustment. Based on the new drilling data and production data, earlier inefficient well management was turned a more efficient well management, where the engineering processing space is fully utilized, the decline of oil field is alleviated, and the development effect is greatly improved.\n This this paper expounds how to excavate the potential again after the redevelopment project in large fluvial facies oilfield in Bohai bay, taking this oilfield as an example.","PeriodicalId":11267,"journal":{"name":"Day 3 Thu, March 28, 2019","volume":"42 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-03-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Tap the Potentials and Reduce the Geological Uncertainties of Mature Complex Fluvial Reservoir: Case Study Redevelopment Plan of D-X Oilfield in Bohai Bay\",\"authors\":\"Yifan He\",\"doi\":\"10.2523/IPTC-19415-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n D-X oilfield implemented an infill adjustment from 2013 to 2015, adding 101 development wells, two central processing platforms and two wellhead platforms.\\n After the adjustment, the oil field greatly improved the engineering processing capacity, but it had also entered a period of rapid decline. In order to mitigate the decline and improve the recovery rate, 65 adjustment wells were implemented in this oilfield after the first adjustment. Based on the new drilling data and production data, earlier inefficient well management was turned a more efficient well management, where the engineering processing space is fully utilized, the decline of oil field is alleviated, and the development effect is greatly improved.\\n This this paper expounds how to excavate the potential again after the redevelopment project in large fluvial facies oilfield in Bohai bay, taking this oilfield as an example.\",\"PeriodicalId\":11267,\"journal\":{\"name\":\"Day 3 Thu, March 28, 2019\",\"volume\":\"42 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-03-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Thu, March 28, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2523/IPTC-19415-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Thu, March 28, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2523/IPTC-19415-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Tap the Potentials and Reduce the Geological Uncertainties of Mature Complex Fluvial Reservoir: Case Study Redevelopment Plan of D-X Oilfield in Bohai Bay
D-X oilfield implemented an infill adjustment from 2013 to 2015, adding 101 development wells, two central processing platforms and two wellhead platforms.
After the adjustment, the oil field greatly improved the engineering processing capacity, but it had also entered a period of rapid decline. In order to mitigate the decline and improve the recovery rate, 65 adjustment wells were implemented in this oilfield after the first adjustment. Based on the new drilling data and production data, earlier inefficient well management was turned a more efficient well management, where the engineering processing space is fully utilized, the decline of oil field is alleviated, and the development effect is greatly improved.
This this paper expounds how to excavate the potential again after the redevelopment project in large fluvial facies oilfield in Bohai bay, taking this oilfield as an example.