{"title":"在$K$循环调度下运行的集群工具中最坏情况下晶圆延迟的特征","authors":"Dong-Hyun Roh, Tae-Eog Lee","doi":"10.1109/COASE.2018.8560521","DOIUrl":null,"url":null,"abstract":"Cluster tools are widely used manufacturing equipment in semiconductor manufacturing systems and consist of several process chambers, loadlock modules, and a wafer transport robot. The operation of the cluster tool relies on decision making about the robot operations. Generally, a robot iteratively determines its next task according to a given task sequence. This tool schedule is called a cyclic schedule. If the same timing pattern repeats every $K$ work cycles in a cyclic schedule, the schedule is called a $K$ -cyclic schedule. In a cluster tool with a $K$ -cyclic schedule, wafer delay, which is the time that a processed wafer is stored in the process chamber, becomes an important issue. In this study, we identify the worst-case wafer delay, which is the maximum value of wafer delay among all the $K$ -cyclic schedules a cluster tool can have. To do this, we present timed event graph models for dual-armed and single-armed cluster tools and briefly explain the previous research on closed-form formulae of token delays in timed event graphs with K-cyclic schedules suggested by Lee et al. [1]. Finally, we propose a method for deriving a closed-form formula for the worst-case wafer delay in a cluster tool, which can be applied to arbitrary wafer flow patterns and time parameters.","PeriodicalId":6518,"journal":{"name":"2018 IEEE 14th International Conference on Automation Science and Engineering (CASE)","volume":"25 1","pages":"1562-1567"},"PeriodicalIF":0.0000,"publicationDate":"2018-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Characterizing the Worst-Case Wafer Delay in a Cluster Tool Operated in a $K$-Cyclic Schedule\",\"authors\":\"Dong-Hyun Roh, Tae-Eog Lee\",\"doi\":\"10.1109/COASE.2018.8560521\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Cluster tools are widely used manufacturing equipment in semiconductor manufacturing systems and consist of several process chambers, loadlock modules, and a wafer transport robot. The operation of the cluster tool relies on decision making about the robot operations. Generally, a robot iteratively determines its next task according to a given task sequence. This tool schedule is called a cyclic schedule. If the same timing pattern repeats every $K$ work cycles in a cyclic schedule, the schedule is called a $K$ -cyclic schedule. In a cluster tool with a $K$ -cyclic schedule, wafer delay, which is the time that a processed wafer is stored in the process chamber, becomes an important issue. In this study, we identify the worst-case wafer delay, which is the maximum value of wafer delay among all the $K$ -cyclic schedules a cluster tool can have. To do this, we present timed event graph models for dual-armed and single-armed cluster tools and briefly explain the previous research on closed-form formulae of token delays in timed event graphs with K-cyclic schedules suggested by Lee et al. [1]. Finally, we propose a method for deriving a closed-form formula for the worst-case wafer delay in a cluster tool, which can be applied to arbitrary wafer flow patterns and time parameters.\",\"PeriodicalId\":6518,\"journal\":{\"name\":\"2018 IEEE 14th International Conference on Automation Science and Engineering (CASE)\",\"volume\":\"25 1\",\"pages\":\"1562-1567\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2018 IEEE 14th International Conference on Automation Science and Engineering (CASE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/COASE.2018.8560521\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 IEEE 14th International Conference on Automation Science and Engineering (CASE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/COASE.2018.8560521","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

集群工具是半导体制造系统中广泛使用的制造设备,由几个工艺室、负载锁模块和一个晶圆运输机器人组成。集群工具的运行依赖于对机器人操作的决策。一般来说,机器人根据给定的任务序列,迭代地确定下一个任务。这种工具调度称为循环调度。如果相同的定时模式在循环调度中每$K$工作周期重复一次,则该调度称为$K$ -循环调度。在具有$K$周期调度的群集工具中,晶圆延迟,即已处理的晶圆存储在工艺室中的时间,成为一个重要问题。在本研究中,我们确定了最坏情况下的晶圆延迟,这是集群工具可以拥有的所有$K$循环调度中晶圆延迟的最大值。为此,我们提出了双臂和单臂聚类工具的定时事件图模型,并简要解释了Lee等人[1]提出的k -循环调度定时事件图中令牌延迟的封闭形式公式。最后,我们提出了一种推导聚类工具中最坏情况下晶圆延迟的封闭公式的方法,该方法可以应用于任意晶圆流动模式和时间参数。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Characterizing the Worst-Case Wafer Delay in a Cluster Tool Operated in a $K$-Cyclic Schedule
Cluster tools are widely used manufacturing equipment in semiconductor manufacturing systems and consist of several process chambers, loadlock modules, and a wafer transport robot. The operation of the cluster tool relies on decision making about the robot operations. Generally, a robot iteratively determines its next task according to a given task sequence. This tool schedule is called a cyclic schedule. If the same timing pattern repeats every $K$ work cycles in a cyclic schedule, the schedule is called a $K$ -cyclic schedule. In a cluster tool with a $K$ -cyclic schedule, wafer delay, which is the time that a processed wafer is stored in the process chamber, becomes an important issue. In this study, we identify the worst-case wafer delay, which is the maximum value of wafer delay among all the $K$ -cyclic schedules a cluster tool can have. To do this, we present timed event graph models for dual-armed and single-armed cluster tools and briefly explain the previous research on closed-form formulae of token delays in timed event graphs with K-cyclic schedules suggested by Lee et al. [1]. Finally, we propose a method for deriving a closed-form formula for the worst-case wafer delay in a cluster tool, which can be applied to arbitrary wafer flow patterns and time parameters.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信