{"title":"快速施工方法变量(时间、成本、质量)的控制","authors":"M. El-Far, M. Kotb, R. Sabry","doi":"10.1680/jinam.23.00001","DOIUrl":null,"url":null,"abstract":"Fast-track construction projects that begin with inadequate design information have become more common in response to rising construction industry demand. Fast-tracking shortens project duration while increasing rework. To achieve project deadlines while minimizing rework, specialists must select the best fast-tracking strategy. As a result, a questionnaire was developed to assess the success characteristics of fast-track construction and to provide constraints for these features and variables in national construction projects. National construction projects address specified government needs or investments in order to maximize the national return. The surveys limit these factors by specifying maximum and minimum percentages. These percentages were chosen in order to expedite project building. Period varies in national projects from the typical construction approach to the shortest time we can achieve with a plan. Cost and quality are within 20% and 10% of national project traditional construction methods, respectively. The best setting for various construction projects is determined by this proportion. It is preferable to use these percentages as a reference to complete construction projects in the shortest amount of time, with the highest quality, and at the lowest cost. This questionnaire was completed by sixteen building experts. Google Forms questionnaire was completed by 211 persons. This clarifies the results and construction variables time, cost, and quality.","PeriodicalId":43387,"journal":{"name":"Infrastructure Asset Management","volume":"42 1","pages":""},"PeriodicalIF":1.9000,"publicationDate":"2023-04-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Controlling of fast-track construction method variables (time, cost, and quality)\",\"authors\":\"M. El-Far, M. Kotb, R. Sabry\",\"doi\":\"10.1680/jinam.23.00001\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Fast-track construction projects that begin with inadequate design information have become more common in response to rising construction industry demand. Fast-tracking shortens project duration while increasing rework. To achieve project deadlines while minimizing rework, specialists must select the best fast-tracking strategy. As a result, a questionnaire was developed to assess the success characteristics of fast-track construction and to provide constraints for these features and variables in national construction projects. National construction projects address specified government needs or investments in order to maximize the national return. The surveys limit these factors by specifying maximum and minimum percentages. These percentages were chosen in order to expedite project building. Period varies in national projects from the typical construction approach to the shortest time we can achieve with a plan. Cost and quality are within 20% and 10% of national project traditional construction methods, respectively. The best setting for various construction projects is determined by this proportion. It is preferable to use these percentages as a reference to complete construction projects in the shortest amount of time, with the highest quality, and at the lowest cost. This questionnaire was completed by sixteen building experts. Google Forms questionnaire was completed by 211 persons. This clarifies the results and construction variables time, cost, and quality.\",\"PeriodicalId\":43387,\"journal\":{\"name\":\"Infrastructure Asset Management\",\"volume\":\"42 1\",\"pages\":\"\"},\"PeriodicalIF\":1.9000,\"publicationDate\":\"2023-04-28\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Infrastructure Asset Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1680/jinam.23.00001\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Infrastructure Asset Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jinam.23.00001","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 1

摘要

为了应对不断增长的建筑行业需求,从设计信息不足开始的快速建设项目变得越来越普遍。快速跟踪缩短了项目持续时间,同时增加了返工。为了在最小化返工的同时达到项目的最后期限,专家们必须选择最佳的快速跟踪策略。因此,开发了一份调查问卷,以评估快速通道建设的成功特征,并为国家建设项目中的这些特征和变量提供约束。国家建设项目是为了满足特定的政府需求或投资,以实现国家回报的最大化。调查通过指定最大和最小百分比来限制这些因素。选择这些百分比是为了加快项目建设。国家工程的工期各不相同,既有典型的施工方式,也有规划的最短工期。成本和质量分别在国家工程传统施工方法的20%和10%以内。各种建设项目的最佳设置就是由这个比例决定的。最好使用这些百分比作为参考,以便在最短的时间内以最高的质量和最低的成本完成建设项目。这份问卷由16位建筑专家完成。211人完成了Google Forms问卷调查。这澄清了结果和施工变量时间、成本和质量。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Controlling of fast-track construction method variables (time, cost, and quality)
Fast-track construction projects that begin with inadequate design information have become more common in response to rising construction industry demand. Fast-tracking shortens project duration while increasing rework. To achieve project deadlines while minimizing rework, specialists must select the best fast-tracking strategy. As a result, a questionnaire was developed to assess the success characteristics of fast-track construction and to provide constraints for these features and variables in national construction projects. National construction projects address specified government needs or investments in order to maximize the national return. The surveys limit these factors by specifying maximum and minimum percentages. These percentages were chosen in order to expedite project building. Period varies in national projects from the typical construction approach to the shortest time we can achieve with a plan. Cost and quality are within 20% and 10% of national project traditional construction methods, respectively. The best setting for various construction projects is determined by this proportion. It is preferable to use these percentages as a reference to complete construction projects in the shortest amount of time, with the highest quality, and at the lowest cost. This questionnaire was completed by sixteen building experts. Google Forms questionnaire was completed by 211 persons. This clarifies the results and construction variables time, cost, and quality.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
2.70
自引率
14.30%
发文量
18
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信