{"title":"估算白车身生产线的净理想周期时间","authors":"W. Grobler, D. Kotzé, J. Joubert","doi":"10.5784/37-1-683","DOIUrl":null,"url":null,"abstract":"In the automotive industry, a Body in White (BIW) refers to the first step, the basic structure, in the production of a vehicle. Once a BIW production line has been built, the (maximum) capacity is fixed and throughput is therefore limited by the equipment specified during the design phase. The main metric used to inform the production line design is the Net Ideal Cycle Time (NICT). Unfortunately, the state of practice to estimate the NICT is a basic heuristic that does not account for production variation. In this paper, we challenge the current estimation approach by proposing an alternative that assumes actual production to follow a Weibull distribution. The proposed model is derived and estimated from empirical data. The results suggest that BIW production lines have traditionally been designed with too low a capacity, resulting in planned throughput rarely being achieved. On the other hand, increasing the design capacity implies a higher initial investment. In this paper it is demonstrated that the higher investment required is offset by reduced losses, resulting in more reliable planning and returns.","PeriodicalId":30587,"journal":{"name":"ORiON","volume":"99 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Estimating net ideal cycle time for body-in-white production lines\",\"authors\":\"W. Grobler, D. Kotzé, J. Joubert\",\"doi\":\"10.5784/37-1-683\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the automotive industry, a Body in White (BIW) refers to the first step, the basic structure, in the production of a vehicle. Once a BIW production line has been built, the (maximum) capacity is fixed and throughput is therefore limited by the equipment specified during the design phase. The main metric used to inform the production line design is the Net Ideal Cycle Time (NICT). Unfortunately, the state of practice to estimate the NICT is a basic heuristic that does not account for production variation. In this paper, we challenge the current estimation approach by proposing an alternative that assumes actual production to follow a Weibull distribution. The proposed model is derived and estimated from empirical data. The results suggest that BIW production lines have traditionally been designed with too low a capacity, resulting in planned throughput rarely being achieved. On the other hand, increasing the design capacity implies a higher initial investment. In this paper it is demonstrated that the higher investment required is offset by reduced losses, resulting in more reliable planning and returns.\",\"PeriodicalId\":30587,\"journal\":{\"name\":\"ORiON\",\"volume\":\"99 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"ORiON\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5784/37-1-683\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"ORiON","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5784/37-1-683","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

在汽车工业中,白车身(Body In White,简称BIW)指的是汽车生产的第一步,即基本结构。一旦白车身生产线建成,(最大)产能是固定的,因此产量受到设计阶段指定设备的限制。用于通知生产线设计的主要指标是净理想周期时间(NICT)。不幸的是,估计NICT的实践状态是一种基本的启发式方法,不能解释生产变化。在本文中,我们通过提出一种替代方法来挑战当前的估计方法,该方法假设实际生产遵循威布尔分布。所提出的模型是根据经验数据推导和估计的。结果表明,传统的白车身生产线设计的产能太低,导致计划的产量很少实现。另一方面,增加设计能力意味着更高的初始投资。本文证明了较高的投资需要被减少的损失所抵消,从而产生更可靠的规划和回报。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Estimating net ideal cycle time for body-in-white production lines
In the automotive industry, a Body in White (BIW) refers to the first step, the basic structure, in the production of a vehicle. Once a BIW production line has been built, the (maximum) capacity is fixed and throughput is therefore limited by the equipment specified during the design phase. The main metric used to inform the production line design is the Net Ideal Cycle Time (NICT). Unfortunately, the state of practice to estimate the NICT is a basic heuristic that does not account for production variation. In this paper, we challenge the current estimation approach by proposing an alternative that assumes actual production to follow a Weibull distribution. The proposed model is derived and estimated from empirical data. The results suggest that BIW production lines have traditionally been designed with too low a capacity, resulting in planned throughput rarely being achieved. On the other hand, increasing the design capacity implies a higher initial investment. In this paper it is demonstrated that the higher investment required is offset by reduced losses, resulting in more reliable planning and returns.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
11
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信