PERT/CPM技术在果汁生产项目规划中的应用:一个案例研究

N. O. Iheonu, Uzoma K. Achom
{"title":"PERT/CPM技术在果汁生产项目规划中的应用:一个案例研究","authors":"N. O. Iheonu, Uzoma K. Achom","doi":"10.9734/ajpas/2023/v24i2522","DOIUrl":null,"url":null,"abstract":"Timely delivery of natural and fresh juice to its’ growing customers is the focus of SCUBED 100%. The CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) techniques were applied in minimizing the expected time duration for juice production at SCUBED 100%. The current expected production time for a batch stood at 656.66 minutes. Modifications were made on the initial model to minimize the expected duration and after two modification processes, an estimated time duration of 458.33 minutes was realized, saving 198.33 minutes (about 3.3 hours) of production time. This study encapsulates the interplay of theoretical insights and practical implementation, confirming the potential of operational research and management techniques in designing real-world outcomes. SCUBED 100%'s journey towards operational excellence demonstrates the transformative potential of time optimization.","PeriodicalId":8532,"journal":{"name":"Asian Journal of Probability and Statistics","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-08-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Project Planning Application to Juice Production Using PERT/CPM Technique: A Case Study\",\"authors\":\"N. O. Iheonu, Uzoma K. Achom\",\"doi\":\"10.9734/ajpas/2023/v24i2522\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Timely delivery of natural and fresh juice to its’ growing customers is the focus of SCUBED 100%. The CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) techniques were applied in minimizing the expected time duration for juice production at SCUBED 100%. The current expected production time for a batch stood at 656.66 minutes. Modifications were made on the initial model to minimize the expected duration and after two modification processes, an estimated time duration of 458.33 minutes was realized, saving 198.33 minutes (about 3.3 hours) of production time. This study encapsulates the interplay of theoretical insights and practical implementation, confirming the potential of operational research and management techniques in designing real-world outcomes. SCUBED 100%'s journey towards operational excellence demonstrates the transformative potential of time optimization.\",\"PeriodicalId\":8532,\"journal\":{\"name\":\"Asian Journal of Probability and Statistics\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-08-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Asian Journal of Probability and Statistics\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.9734/ajpas/2023/v24i2522\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Asian Journal of Probability and Statistics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.9734/ajpas/2023/v24i2522","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

及时向不断增长的客户提供天然和新鲜的果汁是SCUBED 100%的重点。应用CPM(关键路径法)和PERT(程序评估和审查技术)技术,最大限度地减少SCUBED下果汁生产的预期时间。目前一批的预期生产时间为656.66分钟。对初始模型进行修改,使预期工期最小化,经过两次修改,预计工期为458.33分钟,节省生产时间198.33分钟(约3.3小时)。这项研究概括了理论见解和实践实施的相互作用,证实了运筹学和管理技术在设计现实世界结果方面的潜力。SCUBED 100%的卓越运营之旅展示了时间优化的变革潜力。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Project Planning Application to Juice Production Using PERT/CPM Technique: A Case Study
Timely delivery of natural and fresh juice to its’ growing customers is the focus of SCUBED 100%. The CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) techniques were applied in minimizing the expected time duration for juice production at SCUBED 100%. The current expected production time for a batch stood at 656.66 minutes. Modifications were made on the initial model to minimize the expected duration and after two modification processes, an estimated time duration of 458.33 minutes was realized, saving 198.33 minutes (about 3.3 hours) of production time. This study encapsulates the interplay of theoretical insights and practical implementation, confirming the potential of operational research and management techniques in designing real-world outcomes. SCUBED 100%'s journey towards operational excellence demonstrates the transformative potential of time optimization.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信