{"title":"施工前规划的现状调查","authors":"B. Li, Min Zheng, S. Austin, T. Thorpe","doi":"10.1109/MSIE.2011.5707583","DOIUrl":null,"url":null,"abstract":"The aim of this paper is to investigate current practice in preconstruction planning. Eleven semi-structured interviews were conducted over a four-month period. Through these interviews, two major findings were revealed: first, guesses are frequently made in preconstruction planning process, neither the initial planner nor the downstream planner will later check. They're usually ignored and left until the execution of the plan, when the problems reveal themselves. Secondly, the current techniques for the management of preconstruction planning, such as the critical path method and bar charts, cannot account for the iterative nature of the preconstruction planning process that requires estimations to be made and work to be redone until a satisfactory solution is developed. This paper argues the importance of effective management of information flow in a preconstruction planning process and the need to improve the management of preconstruction planning. A proposed approach using a dependency structure matrix tool to support the management of preconstruction planning was then introduced.","PeriodicalId":18774,"journal":{"name":"MSIE 2011","volume":"19 1","pages":"105-108"},"PeriodicalIF":0.0000,"publicationDate":"2011-02-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Investigation of current practice in preconstruction planning\",\"authors\":\"B. Li, Min Zheng, S. Austin, T. Thorpe\",\"doi\":\"10.1109/MSIE.2011.5707583\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The aim of this paper is to investigate current practice in preconstruction planning. Eleven semi-structured interviews were conducted over a four-month period. Through these interviews, two major findings were revealed: first, guesses are frequently made in preconstruction planning process, neither the initial planner nor the downstream planner will later check. They're usually ignored and left until the execution of the plan, when the problems reveal themselves. Secondly, the current techniques for the management of preconstruction planning, such as the critical path method and bar charts, cannot account for the iterative nature of the preconstruction planning process that requires estimations to be made and work to be redone until a satisfactory solution is developed. This paper argues the importance of effective management of information flow in a preconstruction planning process and the need to improve the management of preconstruction planning. A proposed approach using a dependency structure matrix tool to support the management of preconstruction planning was then introduced.\",\"PeriodicalId\":18774,\"journal\":{\"name\":\"MSIE 2011\",\"volume\":\"19 1\",\"pages\":\"105-108\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-02-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"MSIE 2011\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/MSIE.2011.5707583\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"MSIE 2011","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/MSIE.2011.5707583","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文的目的是调查施工前规划的现行做法。在四个月的时间里进行了11次半结构化访谈。通过这些访谈,我们发现了两个主要的发现:第一,在施工前的规划过程中,人们经常猜测,最初的规划者和下游的规划者都不会在后期进行核实。他们通常被忽略,直到执行计划时问题才会显露出来。其次,目前管理施工前规划的技术,如关键路径法和条形图,不能解释施工前规划过程的迭代性质,因为这需要进行估计,并重新进行工作,直到开发出令人满意的解决方案。本文论述了在施工前规划过程中对信息流进行有效管理的重要性,以及改进施工前规划管理的必要性。然后介绍了一种使用依赖结构矩阵工具来支持施工前规划管理的方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Investigation of current practice in preconstruction planning
The aim of this paper is to investigate current practice in preconstruction planning. Eleven semi-structured interviews were conducted over a four-month period. Through these interviews, two major findings were revealed: first, guesses are frequently made in preconstruction planning process, neither the initial planner nor the downstream planner will later check. They're usually ignored and left until the execution of the plan, when the problems reveal themselves. Secondly, the current techniques for the management of preconstruction planning, such as the critical path method and bar charts, cannot account for the iterative nature of the preconstruction planning process that requires estimations to be made and work to be redone until a satisfactory solution is developed. This paper argues the importance of effective management of information flow in a preconstruction planning process and the need to improve the management of preconstruction planning. A proposed approach using a dependency structure matrix tool to support the management of preconstruction planning was then introduced.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信