{"title":"基于绩效的基础设施PPP项目支付结构设计","authors":"Limin Su, Yongchao Cao, Huimin Li","doi":"10.3846/ijspm.2023.19180","DOIUrl":null,"url":null,"abstract":"The performance-based payment structure has been widely used in infrastructure PPP projects. However, existing research has been absent on the structural unbalance problem of performance-based payment in the current infrastructure PPP projects. This study aims to construct an optimal proportion of the performance-based payment in the total payment, and then design a performance-based payment structure for infrastructure PPP projects. Firstly, the definition of the performance-linked rate is introduced to characterize the proportion of the performance-based payment. Secondly, based on the different objectives of the maximum social benefit and the minimum cost for the public and private sectors, a multi-objective optimization model is constructed to obtain a reasonable value range of the performance-linked rate. Thirdly, the impacts on different parameters in the performance-linked rate are revealed using simulation methods. Finally, the numerical and simulation results show that, for the weak social average ability, the social cost is also high, and a large performance-linked rate should be set. Conversely, when the social average ability is strong, the social average cost is relatively reduced, and a relatively low performance-linked rate should be set. Consequently, the results can guide the contract design in PPP projects.","PeriodicalId":2,"journal":{"name":"ACS Applied Bio Materials","volume":null,"pages":null},"PeriodicalIF":4.6000,"publicationDate":"2023-06-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"PERFORMANCE-BASED PAYMENT STRUCTURAL DESIGN FOR INFRASTRUCTURE PPP PROJECTS\",\"authors\":\"Limin Su, Yongchao Cao, Huimin Li\",\"doi\":\"10.3846/ijspm.2023.19180\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The performance-based payment structure has been widely used in infrastructure PPP projects. However, existing research has been absent on the structural unbalance problem of performance-based payment in the current infrastructure PPP projects. This study aims to construct an optimal proportion of the performance-based payment in the total payment, and then design a performance-based payment structure for infrastructure PPP projects. Firstly, the definition of the performance-linked rate is introduced to characterize the proportion of the performance-based payment. Secondly, based on the different objectives of the maximum social benefit and the minimum cost for the public and private sectors, a multi-objective optimization model is constructed to obtain a reasonable value range of the performance-linked rate. Thirdly, the impacts on different parameters in the performance-linked rate are revealed using simulation methods. Finally, the numerical and simulation results show that, for the weak social average ability, the social cost is also high, and a large performance-linked rate should be set. Conversely, when the social average ability is strong, the social average cost is relatively reduced, and a relatively low performance-linked rate should be set. Consequently, the results can guide the contract design in PPP projects.\",\"PeriodicalId\":2,\"journal\":{\"name\":\"ACS Applied Bio Materials\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":4.6000,\"publicationDate\":\"2023-06-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"ACS Applied Bio Materials\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.3846/ijspm.2023.19180\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"MATERIALS SCIENCE, BIOMATERIALS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"ACS Applied Bio Materials","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.3846/ijspm.2023.19180","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"MATERIALS SCIENCE, BIOMATERIALS","Score":null,"Total":0}
PERFORMANCE-BASED PAYMENT STRUCTURAL DESIGN FOR INFRASTRUCTURE PPP PROJECTS
The performance-based payment structure has been widely used in infrastructure PPP projects. However, existing research has been absent on the structural unbalance problem of performance-based payment in the current infrastructure PPP projects. This study aims to construct an optimal proportion of the performance-based payment in the total payment, and then design a performance-based payment structure for infrastructure PPP projects. Firstly, the definition of the performance-linked rate is introduced to characterize the proportion of the performance-based payment. Secondly, based on the different objectives of the maximum social benefit and the minimum cost for the public and private sectors, a multi-objective optimization model is constructed to obtain a reasonable value range of the performance-linked rate. Thirdly, the impacts on different parameters in the performance-linked rate are revealed using simulation methods. Finally, the numerical and simulation results show that, for the weak social average ability, the social cost is also high, and a large performance-linked rate should be set. Conversely, when the social average ability is strong, the social average cost is relatively reduced, and a relatively low performance-linked rate should be set. Consequently, the results can guide the contract design in PPP projects.