{"title":"南非承包商合同索赔决定的成功率和影响","authors":"Jeffrey Khangale, I. Musonda, Sylvia Okoro","doi":"10.53974/unza.jonas.5.1.715","DOIUrl":null,"url":null,"abstract":"Contractual claims are essential issues and normally disputed because they cause losses if the contractual claims fail to be honoured. The completion of projects can be best without any arising contractual claims by the contractors. However, this appears to be too ideal and almost impossible. Contractual claims have connotations of time and monies, which are to be honoured by the client to the contractor as a payment or compensation for the incurred cost. This article established the success rate or extent to which contractual claims were honoured and the implications of the client’s decisions on contractual claims that were not honoured. The questionnaire was distributed to professionals involved in the administration of contractual claims in projects. Descriptive analysis was used to analyse data. Findings revealed that most contractual claims were honoured in full when they were small in numbers, and when contractual claims increase, the success rate also decreased. The findings further indicated that most projects ended in cost and time overruns due to clients’ decisions on contractual claims. It is expected that the findings of this research will help construction stakeholders to avoid the main causes of contractual claims, and thus increasing the chances of contractual claims being honoured and improving the overall performance of construction projects concerning minimized delays and cost overruns.","PeriodicalId":16473,"journal":{"name":"Journal of natural sciences, life and applied sciences","volume":"10 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-03-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"SUCCESS RATE AND IMPLICATIONS OF CONTRACTUAL CLAIMS DECISIONS ON CONTRACTORS IN SOUTH AFRICA\",\"authors\":\"Jeffrey Khangale, I. Musonda, Sylvia Okoro\",\"doi\":\"10.53974/unza.jonas.5.1.715\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Contractual claims are essential issues and normally disputed because they cause losses if the contractual claims fail to be honoured. The completion of projects can be best without any arising contractual claims by the contractors. However, this appears to be too ideal and almost impossible. Contractual claims have connotations of time and monies, which are to be honoured by the client to the contractor as a payment or compensation for the incurred cost. This article established the success rate or extent to which contractual claims were honoured and the implications of the client’s decisions on contractual claims that were not honoured. The questionnaire was distributed to professionals involved in the administration of contractual claims in projects. Descriptive analysis was used to analyse data. Findings revealed that most contractual claims were honoured in full when they were small in numbers, and when contractual claims increase, the success rate also decreased. The findings further indicated that most projects ended in cost and time overruns due to clients’ decisions on contractual claims. It is expected that the findings of this research will help construction stakeholders to avoid the main causes of contractual claims, and thus increasing the chances of contractual claims being honoured and improving the overall performance of construction projects concerning minimized delays and cost overruns.\",\"PeriodicalId\":16473,\"journal\":{\"name\":\"Journal of natural sciences, life and applied sciences\",\"volume\":\"10 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-03-25\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of natural sciences, life and applied sciences\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.53974/unza.jonas.5.1.715\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of natural sciences, life and applied sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.53974/unza.jonas.5.1.715","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

合同索赔是必不可少的问题,通常是有争议的,因为如果合同索赔得不到履行,它们会造成损失。在不引起承包商任何合同索赔的情况下,工程可以最好地完成。然而,这似乎太理想了,几乎不可能。合同索赔具有时间和金钱的内涵,委托人应向承包商兑现,作为对所发生成本的支付或补偿。本条规定了合同索赔得到履行的成功率或程度,以及客户对未得到履行的合同索赔所作决定的影响。问题单已分发给参与管理项目合同索赔要求的专业人员。采用描述性分析对数据进行分析。调查结果显示,大多数合同索赔要求在数量较少时得到全额兑现,而当合同索赔要求增加时,成功率也会下降。调查结果进一步表明,由于客户对合同索赔的决定,大多数项目的费用和时间都超支。预计本研究的结果将有助于建筑利益相关者避免合同索赔的主要原因,从而增加合同索赔得到履行的机会,并提高建筑项目的整体绩效,最大限度地减少延误和成本超支。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
SUCCESS RATE AND IMPLICATIONS OF CONTRACTUAL CLAIMS DECISIONS ON CONTRACTORS IN SOUTH AFRICA
Contractual claims are essential issues and normally disputed because they cause losses if the contractual claims fail to be honoured. The completion of projects can be best without any arising contractual claims by the contractors. However, this appears to be too ideal and almost impossible. Contractual claims have connotations of time and monies, which are to be honoured by the client to the contractor as a payment or compensation for the incurred cost. This article established the success rate or extent to which contractual claims were honoured and the implications of the client’s decisions on contractual claims that were not honoured. The questionnaire was distributed to professionals involved in the administration of contractual claims in projects. Descriptive analysis was used to analyse data. Findings revealed that most contractual claims were honoured in full when they were small in numbers, and when contractual claims increase, the success rate also decreased. The findings further indicated that most projects ended in cost and time overruns due to clients’ decisions on contractual claims. It is expected that the findings of this research will help construction stakeholders to avoid the main causes of contractual claims, and thus increasing the chances of contractual claims being honoured and improving the overall performance of construction projects concerning minimized delays and cost overruns.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信