FENJA电伴热管中管工程的电光双障鉴定与实施

Frederic Le-Naour, Antoine Marret, K. MacLeod, R. Vivet, I. M. Aglen
{"title":"FENJA电伴热管中管工程的电光双障鉴定与实施","authors":"Frederic Le-Naour, Antoine Marret, K. MacLeod, R. Vivet, I. M. Aglen","doi":"10.4043/31214-ms","DOIUrl":null,"url":null,"abstract":"\n This paper provides an overview of the work completed to design, qualify, manufacture and integrate electrical and optical double barrier penetrators with the Electrically Trace Heated Pipe-in-Pipe (ETH-PiP) as part of the Neptune Energy Fenja Development Project.\n Typical subsea penetrator systems in the oil and gas industry, such as pumps, compressors and X-trees are designed to be retrievable, to enable periodic refurbishment as well as providing the option for replacement, if required. However, the ETH-PiP architecture makes retrieval of system components complicated and uneconomical. Both the electrical and optical dual barrier penetrator system designs have to comply with a set of ETH-PiP specific criteria, such as to be maintenance free over a 25 years service life, prevent water ingress to the pipeline, provide pressure containment for operational media (in an unlikely scenario where the inner pipe bursts) and guarantee minimum footprint to allow an optimum integration onto the Pipeline End Termination (PLET) structure. In addition, the electrical system has to comply with a medium voltage rating (i.e. 5.0/8.7kV) to ensure a wide range of possible ETH-PiP architectures. The optical system has to maintain insertion loss below 0.5dB and a back reflection below -45dB to comply with the stringent requirements of distributed temperature monitoring sensor system over long distances.\n The qualification program of the electrical dual barrier penetrator system was performed in accordance with IEC 60502-4 and SEPS-SP-1001. A tailor made sequence had to be developed for the optical system, based on guidance from SEAFOM-TSD-01, considering that the system partly falls outside the associated standard application.\n The electrical dual barrier penetrator system qualification sequence was developed in two phases; firstly, the electrical transition contacts in the feedthrough chamber were qualified in accordance with IEC 60502-4 and secondly, four electrical double barrier penetrator prototypes were manufactured to allow the completion of the qualification sequence defined as per SEPS-SP-1001. The optical dual barrier penetrator system qualification employed the manufacturing of three prototypes to execute the pre-defined qualification sequence.\n Following the individual qualification of the electrical and optical dual barrier penetrator systems, subsequent welding and full-scale assembly trials were performed to ensure that the maximum allowable temperatures within the penetrators would not be exceeded during welding to the PLET, and to proof test the assembly procedure. Electrical verification testing was also undertaken during these trials to verify that the integrity of the penetrators had been maintained during the assembly and that the PLET arrangement did not give rise to any electrical stresses that could result in excessive deterioration of the penetrators.\n Integration of the four electrical and two optical dual barrier penetrator systems to the project PLET was completed in Q1 2020, with the actual subsea installation of the first ETH-PiP section including the PLET in Q3 2020.","PeriodicalId":10936,"journal":{"name":"Day 2 Tue, August 17, 2021","volume":"177 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Electrical & Optical Double Barrier Qualification and Implementation on FENJA Electrically Trace Heated Pipe-in-Pipe Project\",\"authors\":\"Frederic Le-Naour, Antoine Marret, K. MacLeod, R. Vivet, I. M. Aglen\",\"doi\":\"10.4043/31214-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n This paper provides an overview of the work completed to design, qualify, manufacture and integrate electrical and optical double barrier penetrators with the Electrically Trace Heated Pipe-in-Pipe (ETH-PiP) as part of the Neptune Energy Fenja Development Project.\\n Typical subsea penetrator systems in the oil and gas industry, such as pumps, compressors and X-trees are designed to be retrievable, to enable periodic refurbishment as well as providing the option for replacement, if required. However, the ETH-PiP architecture makes retrieval of system components complicated and uneconomical. Both the electrical and optical dual barrier penetrator system designs have to comply with a set of ETH-PiP specific criteria, such as to be maintenance free over a 25 years service life, prevent water ingress to the pipeline, provide pressure containment for operational media (in an unlikely scenario where the inner pipe bursts) and guarantee minimum footprint to allow an optimum integration onto the Pipeline End Termination (PLET) structure. In addition, the electrical system has to comply with a medium voltage rating (i.e. 5.0/8.7kV) to ensure a wide range of possible ETH-PiP architectures. The optical system has to maintain insertion loss below 0.5dB and a back reflection below -45dB to comply with the stringent requirements of distributed temperature monitoring sensor system over long distances.\\n The qualification program of the electrical dual barrier penetrator system was performed in accordance with IEC 60502-4 and SEPS-SP-1001. A tailor made sequence had to be developed for the optical system, based on guidance from SEAFOM-TSD-01, considering that the system partly falls outside the associated standard application.\\n The electrical dual barrier penetrator system qualification sequence was developed in two phases; firstly, the electrical transition contacts in the feedthrough chamber were qualified in accordance with IEC 60502-4 and secondly, four electrical double barrier penetrator prototypes were manufactured to allow the completion of the qualification sequence defined as per SEPS-SP-1001. The optical dual barrier penetrator system qualification employed the manufacturing of three prototypes to execute the pre-defined qualification sequence.\\n Following the individual qualification of the electrical and optical dual barrier penetrator systems, subsequent welding and full-scale assembly trials were performed to ensure that the maximum allowable temperatures within the penetrators would not be exceeded during welding to the PLET, and to proof test the assembly procedure. Electrical verification testing was also undertaken during these trials to verify that the integrity of the penetrators had been maintained during the assembly and that the PLET arrangement did not give rise to any electrical stresses that could result in excessive deterioration of the penetrators.\\n Integration of the four electrical and two optical dual barrier penetrator systems to the project PLET was completed in Q1 2020, with the actual subsea installation of the first ETH-PiP section including the PLET in Q3 2020.\",\"PeriodicalId\":10936,\"journal\":{\"name\":\"Day 2 Tue, August 17, 2021\",\"volume\":\"177 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-08-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, August 17, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/31214-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, August 17, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31214-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

本文概述了作为Neptune Energy Fenja开发项目的一部分,利用电踪加热管中管(ETH-PiP)完成的电气和光学双屏障穿透器的设计、鉴定、制造和集成工作。石油和天然气行业中典型的海底穿透器系统,如泵、压缩机和x -tree,设计为可回收的,可以定期翻新,如果需要,还可以选择更换。然而,ETH-PiP架构使得系统组件的检索变得复杂且不经济。电气和光学双屏障穿透器系统的设计都必须符合一套ETH-PiP特定标准,例如在25年的使用寿命内免维护,防止管道进水,为操作介质提供压力控制(在不太可能的情况下,内管破裂),并保证最小的占地面积,以实现管道末端(PLET)结构的最佳集成。此外,电气系统必须符合中压额定值(即5.0/8.7kV),以确保广泛的ETH-PiP架构。光学系统必须保持插入损耗低于0.5dB,背反射低于-45dB,以满足远距离分布式温度监测传感器系统的严格要求。根据IEC 60502-4和sep - sp -1001的要求,进行了电气双屏障穿透系统的鉴定程序。考虑到该系统部分超出了相关标准应用,必须根据SEAFOM-TSD-01的指导,为光学系统开发量身定制的序列。电气双障穿透系统鉴定程序分为两个阶段;首先,根据IEC 60502-4对馈通室中的电气过渡触点进行了鉴定,其次,制造了四个电气双障穿透器原型,以完成按照sep - sp -1001定义的鉴定顺序。光学双屏障穿透系统鉴定采用三个原型的制造来执行预先定义的鉴定顺序。在对电气和光学双屏障穿透系统进行单独鉴定后,进行了后续的焊接和全尺寸装配试验,以确保在焊接到PLET期间不会超过穿透器内的最高允许温度,并对装配过程进行验证测试。在这些试验中,还进行了电气验证测试,以验证在装配过程中保持了穿透器的完整性,并且PLET布置不会产生任何可能导致穿透器过度老化的电气应力。将四个电气和两个光学双屏障穿透系统集成到PLET项目于2020年第一季度完成,第一个ETH-PiP部分包括PLET的实际海底安装于2020年第三季度。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Electrical & Optical Double Barrier Qualification and Implementation on FENJA Electrically Trace Heated Pipe-in-Pipe Project
This paper provides an overview of the work completed to design, qualify, manufacture and integrate electrical and optical double barrier penetrators with the Electrically Trace Heated Pipe-in-Pipe (ETH-PiP) as part of the Neptune Energy Fenja Development Project. Typical subsea penetrator systems in the oil and gas industry, such as pumps, compressors and X-trees are designed to be retrievable, to enable periodic refurbishment as well as providing the option for replacement, if required. However, the ETH-PiP architecture makes retrieval of system components complicated and uneconomical. Both the electrical and optical dual barrier penetrator system designs have to comply with a set of ETH-PiP specific criteria, such as to be maintenance free over a 25 years service life, prevent water ingress to the pipeline, provide pressure containment for operational media (in an unlikely scenario where the inner pipe bursts) and guarantee minimum footprint to allow an optimum integration onto the Pipeline End Termination (PLET) structure. In addition, the electrical system has to comply with a medium voltage rating (i.e. 5.0/8.7kV) to ensure a wide range of possible ETH-PiP architectures. The optical system has to maintain insertion loss below 0.5dB and a back reflection below -45dB to comply with the stringent requirements of distributed temperature monitoring sensor system over long distances. The qualification program of the electrical dual barrier penetrator system was performed in accordance with IEC 60502-4 and SEPS-SP-1001. A tailor made sequence had to be developed for the optical system, based on guidance from SEAFOM-TSD-01, considering that the system partly falls outside the associated standard application. The electrical dual barrier penetrator system qualification sequence was developed in two phases; firstly, the electrical transition contacts in the feedthrough chamber were qualified in accordance with IEC 60502-4 and secondly, four electrical double barrier penetrator prototypes were manufactured to allow the completion of the qualification sequence defined as per SEPS-SP-1001. The optical dual barrier penetrator system qualification employed the manufacturing of three prototypes to execute the pre-defined qualification sequence. Following the individual qualification of the electrical and optical dual barrier penetrator systems, subsequent welding and full-scale assembly trials were performed to ensure that the maximum allowable temperatures within the penetrators would not be exceeded during welding to the PLET, and to proof test the assembly procedure. Electrical verification testing was also undertaken during these trials to verify that the integrity of the penetrators had been maintained during the assembly and that the PLET arrangement did not give rise to any electrical stresses that could result in excessive deterioration of the penetrators. Integration of the four electrical and two optical dual barrier penetrator systems to the project PLET was completed in Q1 2020, with the actual subsea installation of the first ETH-PiP section including the PLET in Q3 2020.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信