{"title":"可用性付款中的第三方风险:Palapa Ring Western Package","authors":"A. Nathaniel, Y. Dewi, Shatila Dhiyaannisaa Sani","doi":"10.15294/jils.v7i1.55184","DOIUrl":null,"url":null,"abstract":"The Palapa Ring Western Package is the first Public Private Partnership infrastructure project in Indonesia implementing Availability Payment (AP). Prevailing regulations allow the Government Contracting Agency (GCA) and Implementing Business Entity (IBE) to determine the system of incentives and penalties of AP in their project contract. This research explores two main issues: (1) whether the IBE has obligation for contingent cost liabilities outside of the contractually determined AP amount in the occurrence of damage caused by a third party which interrupts or disrupts infrastructure service availability and (2) whether the GCA has the right to penalize AP amount to the IBE in the occurrence of damage by a third party which interrupts or disrupts service availability. By applying normative legal research using the statute approach, this research concludes that in this project, the IBE has obligation for contingent cost liabilities outside of contractually determined AP amount in the occurrence of damage by a third party and the GCA has the right to penalize AP amount if the IBE fails to maintain service availability. The contractual allocation of operational and maintenance risk to the IBE creates obligation to bear costs during the project lifetime including those due to third-party risk. Further, the use of formula to calculate AP to IBE is solely based on performance data in maintaining service availability according to contractually agreed standards. Thus, the use of AP in the Palapa Ring Western Package may be a point to reference for future Public Private Partnership infrastructure projects.","PeriodicalId":32877,"journal":{"name":"JILS Journal of Indonesian Legal Studies","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Third-Party Risk in the Availability Payment: The Palapa Ring Western Package\",\"authors\":\"A. Nathaniel, Y. Dewi, Shatila Dhiyaannisaa Sani\",\"doi\":\"10.15294/jils.v7i1.55184\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Palapa Ring Western Package is the first Public Private Partnership infrastructure project in Indonesia implementing Availability Payment (AP). Prevailing regulations allow the Government Contracting Agency (GCA) and Implementing Business Entity (IBE) to determine the system of incentives and penalties of AP in their project contract. This research explores two main issues: (1) whether the IBE has obligation for contingent cost liabilities outside of the contractually determined AP amount in the occurrence of damage caused by a third party which interrupts or disrupts infrastructure service availability and (2) whether the GCA has the right to penalize AP amount to the IBE in the occurrence of damage by a third party which interrupts or disrupts service availability. By applying normative legal research using the statute approach, this research concludes that in this project, the IBE has obligation for contingent cost liabilities outside of contractually determined AP amount in the occurrence of damage by a third party and the GCA has the right to penalize AP amount if the IBE fails to maintain service availability. The contractual allocation of operational and maintenance risk to the IBE creates obligation to bear costs during the project lifetime including those due to third-party risk. Further, the use of formula to calculate AP to IBE is solely based on performance data in maintaining service availability according to contractually agreed standards. Thus, the use of AP in the Palapa Ring Western Package may be a point to reference for future Public Private Partnership infrastructure projects.\",\"PeriodicalId\":32877,\"journal\":{\"name\":\"JILS Journal of Indonesian Legal Studies\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"JILS Journal of Indonesian Legal Studies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.15294/jils.v7i1.55184\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"Social Sciences\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"JILS Journal of Indonesian Legal Studies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.15294/jils.v7i1.55184","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"Social Sciences","Score":null,"Total":0}
引用次数: 1

摘要

帕拉帕环西部一揽子计划是印度尼西亚第一个实施可用性支付(AP)的公私合作基础设施项目。现行法规允许政府承包机构(GCA)和实施商业实体(IBE)在其项目合同中确定AP的奖惩制度。本研究探讨了两个主要问题:(1)在第三方中断或破坏基础设施服务可用性造成损害的情况下,IBE是否有义务承担合同确定的AP金额之外的或有成本负债;(2)在第三方中断或破坏基础设施服务可用性造成损害的情况下,GCA是否有权对IBE的AP金额进行处罚。通过使用法规方法应用规范性法律研究,本研究得出结论,在本项目中,IBE有义务承担合同确定的第三方损害的AP金额之外的或有成本负债,如果IBE未能维持服务的可用性,GCA有权对AP金额进行处罚。合同将运营和维护风险分配给IBE,使其有义务在项目生命周期内承担成本,包括由第三方风险引起的成本。此外,使用公式计算AP到IBE完全是基于根据合同约定的标准维护服务可用性的性能数据。因此,在帕拉帕环西部一揽子计划中使用AP可能是未来公私合作基础设施项目的参考点。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Third-Party Risk in the Availability Payment: The Palapa Ring Western Package
The Palapa Ring Western Package is the first Public Private Partnership infrastructure project in Indonesia implementing Availability Payment (AP). Prevailing regulations allow the Government Contracting Agency (GCA) and Implementing Business Entity (IBE) to determine the system of incentives and penalties of AP in their project contract. This research explores two main issues: (1) whether the IBE has obligation for contingent cost liabilities outside of the contractually determined AP amount in the occurrence of damage caused by a third party which interrupts or disrupts infrastructure service availability and (2) whether the GCA has the right to penalize AP amount to the IBE in the occurrence of damage by a third party which interrupts or disrupts service availability. By applying normative legal research using the statute approach, this research concludes that in this project, the IBE has obligation for contingent cost liabilities outside of contractually determined AP amount in the occurrence of damage by a third party and the GCA has the right to penalize AP amount if the IBE fails to maintain service availability. The contractual allocation of operational and maintenance risk to the IBE creates obligation to bear costs during the project lifetime including those due to third-party risk. Further, the use of formula to calculate AP to IBE is solely based on performance data in maintaining service availability according to contractually agreed standards. Thus, the use of AP in the Palapa Ring Western Package may be a point to reference for future Public Private Partnership infrastructure projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
2.10
自引率
0.00%
发文量
13
审稿时长
20 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信