基于P-FTPN的船体安装仿真与优化

Yongquan Zhang, K. Xu, Guosheng Zhou, Jinwei Yu
{"title":"基于P-FTPN的船体安装仿真与优化","authors":"Yongquan Zhang, K. Xu, Guosheng Zhou, Jinwei Yu","doi":"10.1109/ICIEEM.2009.5344299","DOIUrl":null,"url":null,"abstract":"In order to enhance the hull erection efficiency and realize the supervisory control dynamically to construction course, this paper applies Fuzzy-timed place Petri net to simulate the process of hull erection. Triangular Fuzzy Number is utilized to denote the uncertain duration, and an advanced Minkowski subtraction is presented in the model. We eliminate the Hatch Coaming Sections, combine the Compartment Blocks, change the Orientation Double Bottom Block, simplify the complicated Bow Blocks and rearrange the erection scheme. Flow line erecting has been achieved and the efficiency of hull erection has heightened. The construction states can be identified immediately by establishing the Reachable Marking Graph of the erection model and calculating the existing time of markings. Then, the dynamic supervisory control to the hull erection process can be attained.","PeriodicalId":6326,"journal":{"name":"2009 16th International Conference on Industrial Engineering and Engineering Management","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2009-12-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Simulation and optimization of hull erection based on P-FTPN\",\"authors\":\"Yongquan Zhang, K. Xu, Guosheng Zhou, Jinwei Yu\",\"doi\":\"10.1109/ICIEEM.2009.5344299\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In order to enhance the hull erection efficiency and realize the supervisory control dynamically to construction course, this paper applies Fuzzy-timed place Petri net to simulate the process of hull erection. Triangular Fuzzy Number is utilized to denote the uncertain duration, and an advanced Minkowski subtraction is presented in the model. We eliminate the Hatch Coaming Sections, combine the Compartment Blocks, change the Orientation Double Bottom Block, simplify the complicated Bow Blocks and rearrange the erection scheme. Flow line erecting has been achieved and the efficiency of hull erection has heightened. The construction states can be identified immediately by establishing the Reachable Marking Graph of the erection model and calculating the existing time of markings. Then, the dynamic supervisory control to the hull erection process can be attained.\",\"PeriodicalId\":6326,\"journal\":{\"name\":\"2009 16th International Conference on Industrial Engineering and Engineering Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2009-12-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2009 16th International Conference on Industrial Engineering and Engineering Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICIEEM.2009.5344299\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 16th International Conference on Industrial Engineering and Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICIEEM.2009.5344299","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

为了提高船体安装效率,实现对施工过程的动态监控,本文采用模糊定时地点Petri网对船体安装过程进行仿真。模型采用三角模糊数表示不确定持续时间,并提出了一种改进的闵可夫斯基减法。我们取消了舱口围板,合并了隔舱块,改变了方向双底块,简化了复杂的首块,并重新安排了安装方案。实现了流线的架设,提高了船体的架设效率。通过建立安装模型的可达标记图,计算标记的存在时间,可以立即识别施工状态。从而实现对船体安装过程的动态监控。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Simulation and optimization of hull erection based on P-FTPN
In order to enhance the hull erection efficiency and realize the supervisory control dynamically to construction course, this paper applies Fuzzy-timed place Petri net to simulate the process of hull erection. Triangular Fuzzy Number is utilized to denote the uncertain duration, and an advanced Minkowski subtraction is presented in the model. We eliminate the Hatch Coaming Sections, combine the Compartment Blocks, change the Orientation Double Bottom Block, simplify the complicated Bow Blocks and rearrange the erection scheme. Flow line erecting has been achieved and the efficiency of hull erection has heightened. The construction states can be identified immediately by establishing the Reachable Marking Graph of the erection model and calculating the existing time of markings. Then, the dynamic supervisory control to the hull erection process can be attained.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信