{"title":"阿曼苏丹国正在进行的聚合物注入作业的聚合物中断策略","authors":"Y. Svec, O. Kindi, M. Sawafi, R. Farajzadeh, Hanaa Al Sulaimani, Jasper Van Berkel, S. Al-hinai, Moh’d Al Abri, S. Nofli, A. Al-Yahyai, M. Al-Mahrooqi","doi":"10.2118/208202-ms","DOIUrl":null,"url":null,"abstract":"\n Polymer outage (or polymer injection unavailability) is undesirable but also inevitable. When it happens, the question is how to respond to it to minimize its adverse impact on the production. This paper presents the rationale for generating a polymer outage strategy to operate a polymer flood field in the southern area of the Sultanate of Oman. The work presented here is based on field performance and analytical analysis. The diagnostic plots were created from 10 years of polymer flood field response and were used for this operating decision. The pros and cons of two scenarios were discussed. The selected operational strategy is to minimize the short falls of polymer outage. The strategy was implemented in the field.\n Simultaneous injection and production pause (SIPP) is recommended for the full field polymer outage. It minimizes the impact on polymer incremental oil and hence less deferment. Calibrated with the actual results, analytical method is used to determine when to shut down and whether a short of buffer period of water can be tolerated before SIPP is carried out.\n The polymer literature focus on polymer mechanisms, modeling, project initiation and implementation but no paper discusses the operational strategy on how to respond to field polymer outages. This paper shares our operational learnings and the field results of various polymer operation modes on polymer incremental oil. The learning from this field may be of interest to other operators who are planning or currently implementing polymer flood in their fields.","PeriodicalId":10959,"journal":{"name":"Day 3 Wed, November 17, 2021","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2021-12-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":"{\"title\":\"Polymer Outage Strategy for On-Going Polymer Injection Operation in the Sultanate of Oman\",\"authors\":\"Y. Svec, O. Kindi, M. Sawafi, R. Farajzadeh, Hanaa Al Sulaimani, Jasper Van Berkel, S. Al-hinai, Moh’d Al Abri, S. Nofli, A. Al-Yahyai, M. Al-Mahrooqi\",\"doi\":\"10.2118/208202-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Polymer outage (or polymer injection unavailability) is undesirable but also inevitable. When it happens, the question is how to respond to it to minimize its adverse impact on the production. This paper presents the rationale for generating a polymer outage strategy to operate a polymer flood field in the southern area of the Sultanate of Oman. The work presented here is based on field performance and analytical analysis. The diagnostic plots were created from 10 years of polymer flood field response and were used for this operating decision. The pros and cons of two scenarios were discussed. The selected operational strategy is to minimize the short falls of polymer outage. The strategy was implemented in the field.\\n Simultaneous injection and production pause (SIPP) is recommended for the full field polymer outage. It minimizes the impact on polymer incremental oil and hence less deferment. Calibrated with the actual results, analytical method is used to determine when to shut down and whether a short of buffer period of water can be tolerated before SIPP is carried out.\\n The polymer literature focus on polymer mechanisms, modeling, project initiation and implementation but no paper discusses the operational strategy on how to respond to field polymer outages. This paper shares our operational learnings and the field results of various polymer operation modes on polymer incremental oil. The learning from this field may be of interest to other operators who are planning or currently implementing polymer flood in their fields.\",\"PeriodicalId\":10959,\"journal\":{\"name\":\"Day 3 Wed, November 17, 2021\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-12-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"4\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, November 17, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/208202-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, November 17, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/208202-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Polymer Outage Strategy for On-Going Polymer Injection Operation in the Sultanate of Oman
Polymer outage (or polymer injection unavailability) is undesirable but also inevitable. When it happens, the question is how to respond to it to minimize its adverse impact on the production. This paper presents the rationale for generating a polymer outage strategy to operate a polymer flood field in the southern area of the Sultanate of Oman. The work presented here is based on field performance and analytical analysis. The diagnostic plots were created from 10 years of polymer flood field response and were used for this operating decision. The pros and cons of two scenarios were discussed. The selected operational strategy is to minimize the short falls of polymer outage. The strategy was implemented in the field.
Simultaneous injection and production pause (SIPP) is recommended for the full field polymer outage. It minimizes the impact on polymer incremental oil and hence less deferment. Calibrated with the actual results, analytical method is used to determine when to shut down and whether a short of buffer period of water can be tolerated before SIPP is carried out.
The polymer literature focus on polymer mechanisms, modeling, project initiation and implementation but no paper discusses the operational strategy on how to respond to field polymer outages. This paper shares our operational learnings and the field results of various polymer operation modes on polymer incremental oil. The learning from this field may be of interest to other operators who are planning or currently implementing polymer flood in their fields.