调查a区块实施地面支持系统的有效性:以南部非洲金属矿为例

IF 0.7 Q4 GREEN & SUSTAINABLE SCIENCE & TECHNOLOGY
K. Manyelo, Peter Kolapo
{"title":"调查a区块实施地面支持系统的有效性:以南部非洲金属矿为例","authors":"K. Manyelo, Peter Kolapo","doi":"10.46873/2300-3960.1344","DOIUrl":null,"url":null,"abstract":"This study aims to investigate the effectiveness of the ground support systems that are planned to be implemented on Block A, which will be excavated through the Marikana fault zone. The block of ground being prepared for mining has been physically affected by the presence of the Marikana fault and is therefore geomechanically and geotechnically weaker than the normal stoping conditions on the rest of the shaft. Data collected during the raiselines mapping was used as input into the numerical modelling software (Dips and JBlock), which indicated a major scatter of joint orientations in Block A. Shallow dipping orientations of 276 /14 , 174 /11 and 69 /14 were observed. An average RMR below 50 was calculated from the field mapping data which indicates that the quality of the rockmass in Block A is relatively poor and pose the risk of rock falls due to high probability of unstable rocks. Jblock simulations were performed to estimate the load bearing capacity of the roof bolts. The simulation results showed that the probability of failure reduced to 26% at a loading capacity of 160 kN as opposed to a 60% probability using 100 kN capacity. Likewise, the probability of block failure for 1 m blocks and the maximum support failure decreased to 27% and 5% respectively. The area simulated is a stoping panel with a 15 m face length and a 30 m back length. A total number of 10 000 keyblocks were generated and the probability of failure was highest for 1 m at a 60% in between support. The JBlock analysis shows that the support spacing implemented at Mine A does not sufficiently account for all rockfalls that can occur due to keyblock formation in the hangingwall. In order to effectively support the unstable ground, it is recommended that longer grouted coupling roof bolts of 2 m length spaced at 1 £ 1.2 m should be installed, as opposed to the current mechanical end-anchors (ungrouted) of 1.6 m length spaced at 1.5 m £ 1.5 m.","PeriodicalId":37284,"journal":{"name":"Journal of Sustainable Mining","volume":null,"pages":null},"PeriodicalIF":0.7000,"publicationDate":"2022-01-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Investigating the effectiveness of a ground support system implemented on Block A: A case study of Southern Africa Metalliferous Mine\",\"authors\":\"K. Manyelo, Peter Kolapo\",\"doi\":\"10.46873/2300-3960.1344\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This study aims to investigate the effectiveness of the ground support systems that are planned to be implemented on Block A, which will be excavated through the Marikana fault zone. The block of ground being prepared for mining has been physically affected by the presence of the Marikana fault and is therefore geomechanically and geotechnically weaker than the normal stoping conditions on the rest of the shaft. Data collected during the raiselines mapping was used as input into the numerical modelling software (Dips and JBlock), which indicated a major scatter of joint orientations in Block A. Shallow dipping orientations of 276 /14 , 174 /11 and 69 /14 were observed. An average RMR below 50 was calculated from the field mapping data which indicates that the quality of the rockmass in Block A is relatively poor and pose the risk of rock falls due to high probability of unstable rocks. Jblock simulations were performed to estimate the load bearing capacity of the roof bolts. The simulation results showed that the probability of failure reduced to 26% at a loading capacity of 160 kN as opposed to a 60% probability using 100 kN capacity. Likewise, the probability of block failure for 1 m blocks and the maximum support failure decreased to 27% and 5% respectively. The area simulated is a stoping panel with a 15 m face length and a 30 m back length. A total number of 10 000 keyblocks were generated and the probability of failure was highest for 1 m at a 60% in between support. The JBlock analysis shows that the support spacing implemented at Mine A does not sufficiently account for all rockfalls that can occur due to keyblock formation in the hangingwall. In order to effectively support the unstable ground, it is recommended that longer grouted coupling roof bolts of 2 m length spaced at 1 £ 1.2 m should be installed, as opposed to the current mechanical end-anchors (ungrouted) of 1.6 m length spaced at 1.5 m £ 1.5 m.\",\"PeriodicalId\":37284,\"journal\":{\"name\":\"Journal of Sustainable Mining\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.7000,\"publicationDate\":\"2022-01-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Sustainable Mining\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.46873/2300-3960.1344\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"GREEN & SUSTAINABLE SCIENCE & TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Sustainable Mining","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.46873/2300-3960.1344","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"GREEN & SUSTAINABLE SCIENCE & TECHNOLOGY","Score":null,"Total":0}
引用次数: 1

摘要

本研究旨在调查计划在A区块实施的地面支撑系统的有效性,该区块将通过Marikana断裂带开挖。准备采矿的地面块受到Marikana断层的物理影响,因此在地质力学和地质技术上比竖井其余部分的正常采矿条件弱。将凸起线绘制过程中收集的数据输入到数值模拟软件(dip和JBlock)中,结果表明a区块的节理取向主要分布在276 /14、174 /11和69 /14的浅倾斜取向上。根据野外填图数据计算得出RMR平均值在50以下,说明A区块岩体质量较差,存在不稳定岩体的概率较大,存在岩崩风险。通过Jblock模拟估算了顶板锚杆的承载能力。仿真结果表明,在160kn载荷下,失效概率降至26%,而在100kn载荷下,失效概率为60%。同样,1 m块体破坏的概率和最大支护破坏的概率分别下降到27%和5%。模拟区为工作面长度为15 m,工作面长度为30 m的回采盘。总共产生了10,000个关键块,在支撑间距为60%时,1 m的失效概率最高。JBlock分析表明,A矿实施的支护间距不能充分考虑由于上盘形成关键块而可能发生的所有落石。为了有效地支撑不稳定的地面,建议安装较长的2米注浆连接锚杆,间隔为1 ~ 1.2米,而不是目前的机械端锚(未注浆),长度为1.6米,间隔为1.5米~ 1.5米。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Investigating the effectiveness of a ground support system implemented on Block A: A case study of Southern Africa Metalliferous Mine
This study aims to investigate the effectiveness of the ground support systems that are planned to be implemented on Block A, which will be excavated through the Marikana fault zone. The block of ground being prepared for mining has been physically affected by the presence of the Marikana fault and is therefore geomechanically and geotechnically weaker than the normal stoping conditions on the rest of the shaft. Data collected during the raiselines mapping was used as input into the numerical modelling software (Dips and JBlock), which indicated a major scatter of joint orientations in Block A. Shallow dipping orientations of 276 /14 , 174 /11 and 69 /14 were observed. An average RMR below 50 was calculated from the field mapping data which indicates that the quality of the rockmass in Block A is relatively poor and pose the risk of rock falls due to high probability of unstable rocks. Jblock simulations were performed to estimate the load bearing capacity of the roof bolts. The simulation results showed that the probability of failure reduced to 26% at a loading capacity of 160 kN as opposed to a 60% probability using 100 kN capacity. Likewise, the probability of block failure for 1 m blocks and the maximum support failure decreased to 27% and 5% respectively. The area simulated is a stoping panel with a 15 m face length and a 30 m back length. A total number of 10 000 keyblocks were generated and the probability of failure was highest for 1 m at a 60% in between support. The JBlock analysis shows that the support spacing implemented at Mine A does not sufficiently account for all rockfalls that can occur due to keyblock formation in the hangingwall. In order to effectively support the unstable ground, it is recommended that longer grouted coupling roof bolts of 2 m length spaced at 1 £ 1.2 m should be installed, as opposed to the current mechanical end-anchors (ungrouted) of 1.6 m length spaced at 1.5 m £ 1.5 m.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Journal of Sustainable Mining
Journal of Sustainable Mining Earth and Planetary Sciences-Geology
CiteScore
1.50
自引率
10.00%
发文量
20
审稿时长
16 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信