单一建筑活动中的垃圾数据处理算法:一个涉及NAVFAC P-405实现的案例

S. Ali, K. Krishnamurthy, C. Arun, Ladheedha Nasrin Ka, S. James, N. Mathew, A. Sujatha, Sumayya Pm
{"title":"单一建筑活动中的垃圾数据处理算法:一个涉及NAVFAC P-405实现的案例","authors":"S. Ali, K. Krishnamurthy, C. Arun, Ladheedha Nasrin Ka, S. James, N. Mathew, A. Sujatha, Sumayya Pm","doi":"10.4172/2168-9717.1000177","DOIUrl":null,"url":null,"abstract":"Innovations in construction ‘time waste’ management are scarce. Construction delays are usually caused by time wastes at activity levels, and scholarly studies primarily don't deal in explaining waste at singular activity levels. Experience based heuristics play the most important role in fixing the duration of activities by managers. But, construction activities are prone to highly improbable and complex process flows, making heuristics unreliable. This happens due because the probabilities of construction uncertainties in one project being similar in forthcoming projects are meagerly low. Thus, the experience gained by the project management personnel over the years, may not be handy at predicting actual durations and costs of the forthcoming project with sufficient accuracy. The only practical solution would be a fixation of cost and time standards for singular construction activities based on the complete history of projects completed and those personnel involved in it. In a nutshell, it would mean globalizing or at least nationalizing heuristic data of delays and wastes in order to facilitate meaningful future predictions. This can be achieved by devising a mechanism of centralization of construction process related data into a single entity at the national/international level - Data Collection System (DCS). As part of this system, synchronization of personnel and construction site data should take place at every instance a new construction process is activated anywhere within the boundary of existing DCS. A collection of inventory data, material data, labor data, stakeholder data, activity delay data, time waste data, etc. should form the core data in this data center. Data obtained from heuristics should then be converted to mathematical distributions that could then be used for predictions in future construction scenarios. This would result in giving better and better results as the process of data entry proceeds. The scope of this study is limited to construction activities from Indian construction sites involving core and shell in buildings. “Cost overrun” in: (1) Beam and slab construction, (2) Column construction and, (3) Block work is mathematically modeled as probability distributions. US naval code NAVFAC P-405 is employed for site independent duration calculation. As part of this study, steps on using NAVFAC – 405 in calculating delays are explored in detail. Beta, Normal, and extreme value distributions were seen to fit cost overruns in these activities. This could then be entered into the DCS.","PeriodicalId":15092,"journal":{"name":"Journal of Architectural Engineering Technology","volume":"203 1","pages":"1-8"},"PeriodicalIF":0.0000,"publicationDate":"2017-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Waste Data Processing Algorithm in Singular Construction Activities: A Case Involving Implementation of NAVFAC P-405\",\"authors\":\"S. Ali, K. Krishnamurthy, C. Arun, Ladheedha Nasrin Ka, S. James, N. Mathew, A. Sujatha, Sumayya Pm\",\"doi\":\"10.4172/2168-9717.1000177\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Innovations in construction ‘time waste’ management are scarce. Construction delays are usually caused by time wastes at activity levels, and scholarly studies primarily don't deal in explaining waste at singular activity levels. Experience based heuristics play the most important role in fixing the duration of activities by managers. But, construction activities are prone to highly improbable and complex process flows, making heuristics unreliable. This happens due because the probabilities of construction uncertainties in one project being similar in forthcoming projects are meagerly low. Thus, the experience gained by the project management personnel over the years, may not be handy at predicting actual durations and costs of the forthcoming project with sufficient accuracy. The only practical solution would be a fixation of cost and time standards for singular construction activities based on the complete history of projects completed and those personnel involved in it. In a nutshell, it would mean globalizing or at least nationalizing heuristic data of delays and wastes in order to facilitate meaningful future predictions. This can be achieved by devising a mechanism of centralization of construction process related data into a single entity at the national/international level - Data Collection System (DCS). As part of this system, synchronization of personnel and construction site data should take place at every instance a new construction process is activated anywhere within the boundary of existing DCS. A collection of inventory data, material data, labor data, stakeholder data, activity delay data, time waste data, etc. should form the core data in this data center. Data obtained from heuristics should then be converted to mathematical distributions that could then be used for predictions in future construction scenarios. This would result in giving better and better results as the process of data entry proceeds. The scope of this study is limited to construction activities from Indian construction sites involving core and shell in buildings. “Cost overrun” in: (1) Beam and slab construction, (2) Column construction and, (3) Block work is mathematically modeled as probability distributions. US naval code NAVFAC P-405 is employed for site independent duration calculation. As part of this study, steps on using NAVFAC – 405 in calculating delays are explored in detail. Beta, Normal, and extreme value distributions were seen to fit cost overruns in these activities. This could then be entered into the DCS.\",\"PeriodicalId\":15092,\"journal\":{\"name\":\"Journal of Architectural Engineering Technology\",\"volume\":\"203 1\",\"pages\":\"1-8\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Architectural Engineering Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4172/2168-9717.1000177\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Architectural Engineering Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4172/2168-9717.1000177","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

建筑“时间浪费”管理方面的创新很少。施工延误通常是由活动水平上的时间浪费造成的,而学术研究主要不涉及解释单一活动水平上的浪费。基于经验的启发式在管理者确定活动持续时间方面发挥着最重要的作用。但是,构建活动往往具有高度不可能和复杂的过程流,这使得启发式方法不可靠。这是因为一个项目的建设不确定性在即将到来的项目中相似的概率非常低。因此,项目管理人员多年来所获得的经验,可能不足以准确预测即将到来的项目的实际持续时间和成本。唯一实际的解决办法是根据已完成的项目和参与其中的人员的完整历史,确定单一建筑活动的费用和时间标准。简而言之,这意味着将延迟和浪费的启发式数据全球化或至少国有化,以促进有意义的未来预测。这可以通过设计一种机制来实现,即在国家/国际一级将与施工过程有关的数据集中到一个单一实体- -数据收集系统。作为该系统的一部分,在现有DCS边界内的任何地方启动一个新的施工过程时,人员和施工现场数据的每次同步都应进行。库存数据、材料数据、劳动力数据、利益相关者数据、活动延迟数据、时间浪费数据等的集合应该构成这个数据中心的核心数据。然后,从启发式中获得的数据应该转换为数学分布,然后可以用于预测未来的建设方案。随着数据输入过程的进行,这将产生越来越好的结果。本研究的范围仅限于印度建筑工地的建筑活动,涉及建筑物的核心和外壳。“成本超支”在:(1)梁和板的建设,(2)柱的建设,(3)砌块工程是数学建模为概率分布。采用美国海军代码NAVFAC P-405进行与场地无关的工期计算。作为本研究的一部分,详细探讨了使用NAVFAC - 405计算延迟的步骤。在这些活动中,贝塔值、正态值和极值分布被认为适合成本超支。然后将其输入DCS。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Waste Data Processing Algorithm in Singular Construction Activities: A Case Involving Implementation of NAVFAC P-405
Innovations in construction ‘time waste’ management are scarce. Construction delays are usually caused by time wastes at activity levels, and scholarly studies primarily don't deal in explaining waste at singular activity levels. Experience based heuristics play the most important role in fixing the duration of activities by managers. But, construction activities are prone to highly improbable and complex process flows, making heuristics unreliable. This happens due because the probabilities of construction uncertainties in one project being similar in forthcoming projects are meagerly low. Thus, the experience gained by the project management personnel over the years, may not be handy at predicting actual durations and costs of the forthcoming project with sufficient accuracy. The only practical solution would be a fixation of cost and time standards for singular construction activities based on the complete history of projects completed and those personnel involved in it. In a nutshell, it would mean globalizing or at least nationalizing heuristic data of delays and wastes in order to facilitate meaningful future predictions. This can be achieved by devising a mechanism of centralization of construction process related data into a single entity at the national/international level - Data Collection System (DCS). As part of this system, synchronization of personnel and construction site data should take place at every instance a new construction process is activated anywhere within the boundary of existing DCS. A collection of inventory data, material data, labor data, stakeholder data, activity delay data, time waste data, etc. should form the core data in this data center. Data obtained from heuristics should then be converted to mathematical distributions that could then be used for predictions in future construction scenarios. This would result in giving better and better results as the process of data entry proceeds. The scope of this study is limited to construction activities from Indian construction sites involving core and shell in buildings. “Cost overrun” in: (1) Beam and slab construction, (2) Column construction and, (3) Block work is mathematically modeled as probability distributions. US naval code NAVFAC P-405 is employed for site independent duration calculation. As part of this study, steps on using NAVFAC – 405 in calculating delays are explored in detail. Beta, Normal, and extreme value distributions were seen to fit cost overruns in these activities. This could then be entered into the DCS.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信