船舶系统测试过程概念与应用

IF 0.2 4区 工程技术 Q4 ENGINEERING, CIVIL
DAVID B. McGUIGAN USN (Ret.), WILLIAM J. BOYLAN
{"title":"船舶系统测试过程概念与应用","authors":"DAVID B. McGUIGAN USN (Ret.),&nbsp;WILLIAM J. BOYLAN","doi":"10.1111/j.1559-3584.2011.00318.x","DOIUrl":null,"url":null,"abstract":"<div>\n \n <p>Some technical managers are moving closer to a more disciplined approach when introducing ship systems into the fleet. In the past, many installed systems with inadequate testing. These systems were simply not operationally ready. The consequences of their actions show in impaired performance, system down-time and fleet casualty reports (CASREPS).</p>\n <p>Thorough, cohesive and well-managed testing will insure operationally ready ship systems. However, testing must not be done as an independent project to prove whether or not a system meets requirements. The technical manager must consider testing as an integral process of engineering and design. He can do this, if he uses the disciplined total systems approach to ship systems' development and introduction. Testing is an important process in this approach; is not an end unto itself; and is integral to the life cycle of a system. The test process must be adequately designed, constructed and operated. Program management is the most adaptable management technique to testing. In a test program, facilities, fuel and manpower are significant cost factors. The technical manager can minimize test costs and still use a facility that adequately meets his needs. He should use test sites, test facilities, land based test sites, or land based engineering facilities. He must be creative and innovative. He must introduce other techniques to reduce time and cost. These are discussed.</p>\n <p>In 1978–1979, one of the authors developed this concept and with the other implemented it at the Naval Ship Systems Engineering Station (NAVSSES), Philadelphia, Pennsylvania. NAVSSES is discussed as the Navy's Ship System Development and Production Test Center. Several system based facilities are introduced.</p>\n <p>Simply hypothesizing that developmental and initial phase production testing pays off is one thing, but the proof is in actual test results. The paper looks at various tests recently conducted at NAVSSES and shows how several technical managers achieved improved system and component performance through well planned testing, viz., the LSD-41 propulsion system, the FFG-7 diesel generator, air compressor, the RACER, and the reverse reduction gear test processes. The phased development of the DDG-58 LBEF is discussed.</p>\n <p>The paper concludes that substantial pay-off resulted in those instances where the technical manager treated testing as a process integral to engineering and design. Other conclusions are also drawn.</p>\n </div>","PeriodicalId":49775,"journal":{"name":"Naval Engineers Journal","volume":"123 2","pages":"55-72"},"PeriodicalIF":0.2000,"publicationDate":"2011-05-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1111/j.1559-3584.2011.00318.x","citationCount":"2","resultStr":"{\"title\":\"SHIP SYSTEMS TEST PROCESS - CONCEPT AND APPLICATION\",\"authors\":\"DAVID B. McGUIGAN USN (Ret.),&nbsp;WILLIAM J. BOYLAN\",\"doi\":\"10.1111/j.1559-3584.2011.00318.x\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div>\\n \\n <p>Some technical managers are moving closer to a more disciplined approach when introducing ship systems into the fleet. In the past, many installed systems with inadequate testing. These systems were simply not operationally ready. The consequences of their actions show in impaired performance, system down-time and fleet casualty reports (CASREPS).</p>\\n <p>Thorough, cohesive and well-managed testing will insure operationally ready ship systems. However, testing must not be done as an independent project to prove whether or not a system meets requirements. The technical manager must consider testing as an integral process of engineering and design. He can do this, if he uses the disciplined total systems approach to ship systems' development and introduction. Testing is an important process in this approach; is not an end unto itself; and is integral to the life cycle of a system. The test process must be adequately designed, constructed and operated. Program management is the most adaptable management technique to testing. In a test program, facilities, fuel and manpower are significant cost factors. The technical manager can minimize test costs and still use a facility that adequately meets his needs. He should use test sites, test facilities, land based test sites, or land based engineering facilities. He must be creative and innovative. He must introduce other techniques to reduce time and cost. These are discussed.</p>\\n <p>In 1978–1979, one of the authors developed this concept and with the other implemented it at the Naval Ship Systems Engineering Station (NAVSSES), Philadelphia, Pennsylvania. NAVSSES is discussed as the Navy's Ship System Development and Production Test Center. Several system based facilities are introduced.</p>\\n <p>Simply hypothesizing that developmental and initial phase production testing pays off is one thing, but the proof is in actual test results. The paper looks at various tests recently conducted at NAVSSES and shows how several technical managers achieved improved system and component performance through well planned testing, viz., the LSD-41 propulsion system, the FFG-7 diesel generator, air compressor, the RACER, and the reverse reduction gear test processes. The phased development of the DDG-58 LBEF is discussed.</p>\\n <p>The paper concludes that substantial pay-off resulted in those instances where the technical manager treated testing as a process integral to engineering and design. Other conclusions are also drawn.</p>\\n </div>\",\"PeriodicalId\":49775,\"journal\":{\"name\":\"Naval Engineers Journal\",\"volume\":\"123 2\",\"pages\":\"55-72\"},\"PeriodicalIF\":0.2000,\"publicationDate\":\"2011-05-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.1111/j.1559-3584.2011.00318.x\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Naval Engineers Journal\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://onlinelibrary.wiley.com/doi/10.1111/j.1559-3584.2011.00318.x\",\"RegionNum\":4,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Naval Engineers Journal","FirstCategoryId":"5","ListUrlMain":"https://onlinelibrary.wiley.com/doi/10.1111/j.1559-3584.2011.00318.x","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 2

摘要

一些技术经理在将船舶系统引入舰队时,正朝着更严格的方法迈进。过去,许多安装的系统测试不足。这些系统根本没有做好操作准备。他们行为的后果表现在性能受损、系统停机时间和车队伤亡报告(CASREPS)中。全面、连贯和管理良好的测试将确保船舶系统具备作战准备。但是,测试不能作为一个独立的项目来证明系统是否满足要求。技术经理必须将测试视为工程和设计的一个整体过程。如果他使用有纪律的总体系统方法来开发和引入船舶系统,他就能做到这一点。测试是这种方法中的一个重要过程;本身并不是目的;并且是系统生命周期的组成部分。测试过程必须经过充分的设计、构建和操作。程序管理是最适合测试的管理技术。在测试项目中,设施、燃料和人力是重要的成本因素。技术经理可以最大限度地降低测试成本,并且仍然使用能够充分满足其需求的设施。他应该使用测试场地、测试设施、陆基测试场地或陆基工程设施。他必须富有创造力和创新精神。他必须引入其他技术来减少时间和成本。对此进行了讨论。1978年至1979年,其中一位作者提出了这一概念,并与另一位作者在宾夕法尼亚州费城的海军舰艇系统工程站(NAVSSES)实施了这一理念。NAVSSES被讨论为海军的船舶系统开发和生产测试中心。介绍了几种基于系统的设施。简单地假设开发和初始阶段的生产测试是有回报的是一回事,但证据在于实际的测试结果。本文介绍了NAVSSES最近进行的各种测试,并展示了几位技术经理如何通过精心策划的测试,即LSD-41推进系统、FFG-7柴油发电机、空气压缩机、RACER和反向减速器测试过程,提高了系统和部件的性能。讨论了DDG-58 LBEF的分阶段开发。论文的结论是,在技术经理将测试视为工程和设计不可或缺的过程的情况下,会产生巨大的回报。还得出了其他结论。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
SHIP SYSTEMS TEST PROCESS - CONCEPT AND APPLICATION

Some technical managers are moving closer to a more disciplined approach when introducing ship systems into the fleet. In the past, many installed systems with inadequate testing. These systems were simply not operationally ready. The consequences of their actions show in impaired performance, system down-time and fleet casualty reports (CASREPS).

Thorough, cohesive and well-managed testing will insure operationally ready ship systems. However, testing must not be done as an independent project to prove whether or not a system meets requirements. The technical manager must consider testing as an integral process of engineering and design. He can do this, if he uses the disciplined total systems approach to ship systems' development and introduction. Testing is an important process in this approach; is not an end unto itself; and is integral to the life cycle of a system. The test process must be adequately designed, constructed and operated. Program management is the most adaptable management technique to testing. In a test program, facilities, fuel and manpower are significant cost factors. The technical manager can minimize test costs and still use a facility that adequately meets his needs. He should use test sites, test facilities, land based test sites, or land based engineering facilities. He must be creative and innovative. He must introduce other techniques to reduce time and cost. These are discussed.

In 1978–1979, one of the authors developed this concept and with the other implemented it at the Naval Ship Systems Engineering Station (NAVSSES), Philadelphia, Pennsylvania. NAVSSES is discussed as the Navy's Ship System Development and Production Test Center. Several system based facilities are introduced.

Simply hypothesizing that developmental and initial phase production testing pays off is one thing, but the proof is in actual test results. The paper looks at various tests recently conducted at NAVSSES and shows how several technical managers achieved improved system and component performance through well planned testing, viz., the LSD-41 propulsion system, the FFG-7 diesel generator, air compressor, the RACER, and the reverse reduction gear test processes. The phased development of the DDG-58 LBEF is discussed.

The paper concludes that substantial pay-off resulted in those instances where the technical manager treated testing as a process integral to engineering and design. Other conclusions are also drawn.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Naval Engineers Journal
Naval Engineers Journal 工程技术-工程:海洋
自引率
0.00%
发文量
0
审稿时长
>12 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信