{"title":"南水北调中线穿越黄河工程TBM刀具维修技术","authors":"Wang Lan","doi":"10.3724/sp.j.1201.2011.01021","DOIUrl":null,"url":null,"abstract":"The geological conditions of the Yellow River Crossing Project in the Middle Route of South-to-North Water Diversion Project are complicated,for the crossing tunnel strata consists of total sandy layer,total earth layer,upper sand and lower earth layers mixed.In the design of cutter head for shielding machine,soft soil cutting tool and heavy-load cutter head force-transmitting frame were applied to protect the cutting tools.However,during the TBM construction,the facts of abnormal excavating parameters and mucking containing metalwork demonstrated that the TBM cutting tools were severely wearing.By chamber-entering check under pressure,we found out problems and replaced some damaged cutting tools.After the foundation reinforcement,we made a thorough rehabilitation on the cutters needed to be repaired by the scheme of chamber-entering under normal pressure.This maintenance experience can provide an important guide for smooth progress of the Yellow River Crossing project,and a reference for similar projects.","PeriodicalId":69826,"journal":{"name":"南水北调与水利科技","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2011-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"TBM Cutting Tools Maintenance Technology for the Yellow River Crossing Project in the Middle Route of South-to-North Water Diversion Project\",\"authors\":\"Wang Lan\",\"doi\":\"10.3724/sp.j.1201.2011.01021\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The geological conditions of the Yellow River Crossing Project in the Middle Route of South-to-North Water Diversion Project are complicated,for the crossing tunnel strata consists of total sandy layer,total earth layer,upper sand and lower earth layers mixed.In the design of cutter head for shielding machine,soft soil cutting tool and heavy-load cutter head force-transmitting frame were applied to protect the cutting tools.However,during the TBM construction,the facts of abnormal excavating parameters and mucking containing metalwork demonstrated that the TBM cutting tools were severely wearing.By chamber-entering check under pressure,we found out problems and replaced some damaged cutting tools.After the foundation reinforcement,we made a thorough rehabilitation on the cutters needed to be repaired by the scheme of chamber-entering under normal pressure.This maintenance experience can provide an important guide for smooth progress of the Yellow River Crossing project,and a reference for similar projects.\",\"PeriodicalId\":69826,\"journal\":{\"name\":\"南水北调与水利科技\",\"volume\":\"1 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"南水北调与水利科技\",\"FirstCategoryId\":\"1087\",\"ListUrlMain\":\"https://doi.org/10.3724/sp.j.1201.2011.01021\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"南水北调与水利科技","FirstCategoryId":"1087","ListUrlMain":"https://doi.org/10.3724/sp.j.1201.2011.01021","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
TBM Cutting Tools Maintenance Technology for the Yellow River Crossing Project in the Middle Route of South-to-North Water Diversion Project
The geological conditions of the Yellow River Crossing Project in the Middle Route of South-to-North Water Diversion Project are complicated,for the crossing tunnel strata consists of total sandy layer,total earth layer,upper sand and lower earth layers mixed.In the design of cutter head for shielding machine,soft soil cutting tool and heavy-load cutter head force-transmitting frame were applied to protect the cutting tools.However,during the TBM construction,the facts of abnormal excavating parameters and mucking containing metalwork demonstrated that the TBM cutting tools were severely wearing.By chamber-entering check under pressure,we found out problems and replaced some damaged cutting tools.After the foundation reinforcement,we made a thorough rehabilitation on the cutters needed to be repaired by the scheme of chamber-entering under normal pressure.This maintenance experience can provide an important guide for smooth progress of the Yellow River Crossing project,and a reference for similar projects.
期刊介绍:
"South-to-North Water Transfers and Water Science and Technology" was founded in 2003, mainly publishing papers on water science, water engineering, water resources, water environment, water management, etc. The journal currently has the following columns: hydrology and water resources, ecology and environment, high-quality development of follow-up projects of South-to-North Water Transfers and construction of national water network, ecological protection and high-quality development of the Yellow River Basin, flood disasters and response, "dual carbon" and water conservancy technology, efficient utilization of agricultural water and soil resources, hydrogeology and engineering geology, etc.
The journal is now a Chinese core journal; a source journal for Chinese scientific and technological papers (Chinese core journals); a source journal for the Chinese Science Citation Database (CSCD); and a Chinese core academic journal (A) of RCCSE.