{"title":"斯卡蒙登大坝建设的回顾与思考(1966-1970)","authors":"D. Parkinson, J. Charles","doi":"10.1680/jdare.23.00102","DOIUrl":null,"url":null,"abstract":"Scammonden dam has been described as a unique structure with its large embankment not only forming part of the M62 motorway but also impounding a reservoir. This paper presents the recollections and reflections on this huge project from the viewpoint of its two authors who were present on the site for most of the construction period; one of the authors, who is a Highway Engineer, was the Materials Engineer for the main contractor, Sir Alfred McAlpine & Son, and the other author, who is a Geotechnical Engineer, was much involved with some of the instrumentation. The important role of the contractor in sourcing materials for the embankment is described. Each author made a significant contribution in a sequence of events which arose towards the end of embankment construction. This began with identifying an issue relating to the extremely high pore-water pressures in the clay core and then in a preliminary assessment of the effect of this on upstream slope stability during the early stages of reservoir impounding.","PeriodicalId":39070,"journal":{"name":"Dams and Reservoirs","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-04-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Recollections and reflections on the construction of Scammonden Dam (1966-1970)\",\"authors\":\"D. Parkinson, J. Charles\",\"doi\":\"10.1680/jdare.23.00102\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Scammonden dam has been described as a unique structure with its large embankment not only forming part of the M62 motorway but also impounding a reservoir. This paper presents the recollections and reflections on this huge project from the viewpoint of its two authors who were present on the site for most of the construction period; one of the authors, who is a Highway Engineer, was the Materials Engineer for the main contractor, Sir Alfred McAlpine & Son, and the other author, who is a Geotechnical Engineer, was much involved with some of the instrumentation. The important role of the contractor in sourcing materials for the embankment is described. Each author made a significant contribution in a sequence of events which arose towards the end of embankment construction. This began with identifying an issue relating to the extremely high pore-water pressures in the clay core and then in a preliminary assessment of the effect of this on upstream slope stability during the early stages of reservoir impounding.\",\"PeriodicalId\":39070,\"journal\":{\"name\":\"Dams and Reservoirs\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-04-28\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Dams and Reservoirs\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1680/jdare.23.00102\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"Earth and Planetary Sciences\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Dams and Reservoirs","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1680/jdare.23.00102","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"Earth and Planetary Sciences","Score":null,"Total":0}
Recollections and reflections on the construction of Scammonden Dam (1966-1970)
Scammonden dam has been described as a unique structure with its large embankment not only forming part of the M62 motorway but also impounding a reservoir. This paper presents the recollections and reflections on this huge project from the viewpoint of its two authors who were present on the site for most of the construction period; one of the authors, who is a Highway Engineer, was the Materials Engineer for the main contractor, Sir Alfred McAlpine & Son, and the other author, who is a Geotechnical Engineer, was much involved with some of the instrumentation. The important role of the contractor in sourcing materials for the embankment is described. Each author made a significant contribution in a sequence of events which arose towards the end of embankment construction. This began with identifying an issue relating to the extremely high pore-water pressures in the clay core and then in a preliminary assessment of the effect of this on upstream slope stability during the early stages of reservoir impounding.