{"title":"探讨项目复杂性与建设项目范围变化的关系:以南非NEC项目为例","authors":"T. Lukhele, B. Botha, Sijekula Mbanga","doi":"10.5130/AJCEB.V21I2.7518","DOIUrl":null,"url":null,"abstract":"Construction projects are of very complex nature, and subject to circumstances of high uncertainties and risks due to the interdependences of activities and processes in the project performance. As a result of the dynamic complexities inherited in construction projects, changes in the scope of work are inevitable. Of particular concern is that, when scope changes are introduced in a project, contractors follow a systematic procedure in managing the changes, but with poor planning and implementation thereof because the project complexities that underpin the scope changes are not fully understood. Therefore, despite that complexity is an inherent and defining feature of construction projects, studies in the literature have failed to grasp and present the dynamics of project complexity which underlie the scope changes in the delivery of construction project. The TOE (Technical Organizational Environmental) framework was adopted and applied on DECLARATION OF CONFLICTING INTEREST This research forms part of the Doctoral Study for author number one which is registered at the Nelson Mandela University. FUNDING Republic of South Africa’s Department of Higher Education and Training, New Generation of Academics Programme (nGAP) Scholarship. NRF Research Development Grants for nGAP (NGAP_RDG170419227754). a multiple-case study research design in order to explore and denote project complexity relations to scope changes in construction projects. Through a content analysis procedure, six key elements of project complexities that relate to scope changes in the construction projects has emerged. Understanding these complexity elements could enable the project management team to apply a frontend planning approach in the initiation phase of the projects in order to better manage scope changes in the execution phase of the project, and eventually to improve the project performance.","PeriodicalId":51729,"journal":{"name":"Construction Economics and Building","volume":null,"pages":null},"PeriodicalIF":1.8000,"publicationDate":"2021-05-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Exploring Project Complexity Relations to Scope Changes in Construction Projects: A Case Study of NEC Projects in South Africa\",\"authors\":\"T. Lukhele, B. Botha, Sijekula Mbanga\",\"doi\":\"10.5130/AJCEB.V21I2.7518\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Construction projects are of very complex nature, and subject to circumstances of high uncertainties and risks due to the interdependences of activities and processes in the project performance. As a result of the dynamic complexities inherited in construction projects, changes in the scope of work are inevitable. Of particular concern is that, when scope changes are introduced in a project, contractors follow a systematic procedure in managing the changes, but with poor planning and implementation thereof because the project complexities that underpin the scope changes are not fully understood. Therefore, despite that complexity is an inherent and defining feature of construction projects, studies in the literature have failed to grasp and present the dynamics of project complexity which underlie the scope changes in the delivery of construction project. The TOE (Technical Organizational Environmental) framework was adopted and applied on DECLARATION OF CONFLICTING INTEREST This research forms part of the Doctoral Study for author number one which is registered at the Nelson Mandela University. FUNDING Republic of South Africa’s Department of Higher Education and Training, New Generation of Academics Programme (nGAP) Scholarship. NRF Research Development Grants for nGAP (NGAP_RDG170419227754). a multiple-case study research design in order to explore and denote project complexity relations to scope changes in construction projects. Through a content analysis procedure, six key elements of project complexities that relate to scope changes in the construction projects has emerged. Understanding these complexity elements could enable the project management team to apply a frontend planning approach in the initiation phase of the projects in order to better manage scope changes in the execution phase of the project, and eventually to improve the project performance.\",\"PeriodicalId\":51729,\"journal\":{\"name\":\"Construction Economics and Building\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":1.8000,\"publicationDate\":\"2021-05-27\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Construction Economics and Building\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.5130/AJCEB.V21I2.7518\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction Economics and Building","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5130/AJCEB.V21I2.7518","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
Exploring Project Complexity Relations to Scope Changes in Construction Projects: A Case Study of NEC Projects in South Africa
Construction projects are of very complex nature, and subject to circumstances of high uncertainties and risks due to the interdependences of activities and processes in the project performance. As a result of the dynamic complexities inherited in construction projects, changes in the scope of work are inevitable. Of particular concern is that, when scope changes are introduced in a project, contractors follow a systematic procedure in managing the changes, but with poor planning and implementation thereof because the project complexities that underpin the scope changes are not fully understood. Therefore, despite that complexity is an inherent and defining feature of construction projects, studies in the literature have failed to grasp and present the dynamics of project complexity which underlie the scope changes in the delivery of construction project. The TOE (Technical Organizational Environmental) framework was adopted and applied on DECLARATION OF CONFLICTING INTEREST This research forms part of the Doctoral Study for author number one which is registered at the Nelson Mandela University. FUNDING Republic of South Africa’s Department of Higher Education and Training, New Generation of Academics Programme (nGAP) Scholarship. NRF Research Development Grants for nGAP (NGAP_RDG170419227754). a multiple-case study research design in order to explore and denote project complexity relations to scope changes in construction projects. Through a content analysis procedure, six key elements of project complexities that relate to scope changes in the construction projects has emerged. Understanding these complexity elements could enable the project management team to apply a frontend planning approach in the initiation phase of the projects in order to better manage scope changes in the execution phase of the project, and eventually to improve the project performance.
期刊介绍:
Construction Economics and Building (formerly known as the Australasian Journal of Construction Economics and Building [AJCEB]) is a peer reviewed, open access publication for original research into all aspects of the economics and management of building and construction, quantity surveying and property management as well as construction and property education. It is free for authors, readers and libraries.