可再生能源整合研究的实时测试平台的开发和验证:南非电网代码案例研究

IF 2.7 Q1 ENGINEERING, MULTIDISCIPLINARY
Gideon D. Joubert, A. Raji
{"title":"可再生能源整合研究的实时测试平台的开发和验证:南非电网代码案例研究","authors":"Gideon D. Joubert, A. Raji","doi":"10.1108/jedt-07-2022-0380","DOIUrl":null,"url":null,"abstract":"\nPurpose\nDespite South Africa’s ailing electrical grid, substantial renewable energy (RE) integration is planned for the country. As grid-integrated RE affects all grids differently, this study aims to develop an adaptable grid code-guided renewable power plant (RPP) control real-time simulation testbed, tailored to South African grid code requirements to study grid-integrated RE’s behaviour concerning South Africa’s unique conditions.\n\n\nDesign/methodology/approach\nThe testbed is designed using MATLAB’s Simulink and live script environments, to create an adaptable model where grid, RPP and RPP guiding grid codes are tailorable. This model is integrated with OPAL-RT’s RT-LAB and brought to real-time simulation using OPAL-RT’s OP4510 simulator. Voltage, frequency and short-circuit event case studies are performed through which the testbed’s abilities and performance are assessed.\n\n\nFindings\nCase study results show the following. The testbed accurately represents grid code voltage and frequency requirements. RPP point of connection (POC) conditions are consistently recognized and tracked, according to which the testbed then operates simulated RPPs, validating its design. Short-circuit event simulations show the simulated wind farm supports POC conditions relative to short-circuit intensity by curtailing active power in favour of reactive power, in line with local grid code requirements.\n\n\nOriginality/value\nTo the best of the authors’ knowledge, this is the first design of an adaptable grid code-guided RPP control testbed, tailored to South African grid code requirements in line with which RPP behavioural and grid integration studies can be performed.\n","PeriodicalId":46533,"journal":{"name":"Journal of Engineering Design and Technology","volume":" ","pages":""},"PeriodicalIF":2.7000,"publicationDate":"2023-04-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Development and validation of a real-time testbed for renewable energy integration studies: South African grid code case study\",\"authors\":\"Gideon D. Joubert, A. Raji\",\"doi\":\"10.1108/jedt-07-2022-0380\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\nPurpose\\nDespite South Africa’s ailing electrical grid, substantial renewable energy (RE) integration is planned for the country. As grid-integrated RE affects all grids differently, this study aims to develop an adaptable grid code-guided renewable power plant (RPP) control real-time simulation testbed, tailored to South African grid code requirements to study grid-integrated RE’s behaviour concerning South Africa’s unique conditions.\\n\\n\\nDesign/methodology/approach\\nThe testbed is designed using MATLAB’s Simulink and live script environments, to create an adaptable model where grid, RPP and RPP guiding grid codes are tailorable. This model is integrated with OPAL-RT’s RT-LAB and brought to real-time simulation using OPAL-RT’s OP4510 simulator. Voltage, frequency and short-circuit event case studies are performed through which the testbed’s abilities and performance are assessed.\\n\\n\\nFindings\\nCase study results show the following. The testbed accurately represents grid code voltage and frequency requirements. RPP point of connection (POC) conditions are consistently recognized and tracked, according to which the testbed then operates simulated RPPs, validating its design. Short-circuit event simulations show the simulated wind farm supports POC conditions relative to short-circuit intensity by curtailing active power in favour of reactive power, in line with local grid code requirements.\\n\\n\\nOriginality/value\\nTo the best of the authors’ knowledge, this is the first design of an adaptable grid code-guided RPP control testbed, tailored to South African grid code requirements in line with which RPP behavioural and grid integration studies can be performed.\\n\",\"PeriodicalId\":46533,\"journal\":{\"name\":\"Journal of Engineering Design and Technology\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":2.7000,\"publicationDate\":\"2023-04-14\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Engineering Design and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/jedt-07-2022-0380\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, MULTIDISCIPLINARY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Engineering Design and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/jedt-07-2022-0380","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, MULTIDISCIPLINARY","Score":null,"Total":0}
引用次数: 0

摘要

尽管南非的电网状况不佳,但该国计划进行大规模的可再生能源(RE)整合。由于并网可再生能源对所有电网的影响不同,本研究旨在开发一个适应电网代码指导的可再生能源电厂(RPP)控制实时仿真试验台,根据南非电网代码要求量身定制,研究南非独特条件下并网可再生能源的行为。设计/方法/方法使用MATLAB的Simulink和实时脚本环境设计测试平台,以创建可定制网格,RPP和RPP指导网格代码的适应性模型。该模型与OPAL-RT的RT-LAB集成,并使用OPAL-RT的OP4510模拟器进行实时仿真。通过电压、频率和短路事件案例研究,对试验台的能力和性能进行评估。案例研究结果如下。该试验台准确反映了电网规范对电压和频率的要求。RPP连接点(POC)条件被持续识别和跟踪,根据这些条件,试验台随后运行模拟RPP,验证其设计。短路事件模拟表明,模拟风电场通过减少有功功率而增加无功功率来支持相对于短路强度的POC条件,符合当地电网规范要求。原创性/价值据作者所知,这是第一个可适应网格代码引导的RPP控制试验台的设计,它是根据南非网格代码的要求量身定制的,RPP行为和网格集成研究可以根据这些要求进行。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Development and validation of a real-time testbed for renewable energy integration studies: South African grid code case study
Purpose Despite South Africa’s ailing electrical grid, substantial renewable energy (RE) integration is planned for the country. As grid-integrated RE affects all grids differently, this study aims to develop an adaptable grid code-guided renewable power plant (RPP) control real-time simulation testbed, tailored to South African grid code requirements to study grid-integrated RE’s behaviour concerning South Africa’s unique conditions. Design/methodology/approach The testbed is designed using MATLAB’s Simulink and live script environments, to create an adaptable model where grid, RPP and RPP guiding grid codes are tailorable. This model is integrated with OPAL-RT’s RT-LAB and brought to real-time simulation using OPAL-RT’s OP4510 simulator. Voltage, frequency and short-circuit event case studies are performed through which the testbed’s abilities and performance are assessed. Findings Case study results show the following. The testbed accurately represents grid code voltage and frequency requirements. RPP point of connection (POC) conditions are consistently recognized and tracked, according to which the testbed then operates simulated RPPs, validating its design. Short-circuit event simulations show the simulated wind farm supports POC conditions relative to short-circuit intensity by curtailing active power in favour of reactive power, in line with local grid code requirements. Originality/value To the best of the authors’ knowledge, this is the first design of an adaptable grid code-guided RPP control testbed, tailored to South African grid code requirements in line with which RPP behavioural and grid integration studies can be performed.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Journal of Engineering Design and Technology
Journal of Engineering Design and Technology ENGINEERING, MULTIDISCIPLINARY-
CiteScore
6.50
自引率
21.40%
发文量
67
期刊介绍: - Design strategies - Usability and adaptability - Material, component and systems performance - Process control - Alternative and new technologies - Organizational, management and research issues - Human factors - Environmental, quality and health and safety issues - Cost and life cycle issues - Sustainability criteria, indicators, measurement and practices - Risk management - Entrepreneurship Law, regulation and governance - Design, implementing, managing and practicing innovation - Visualization, simulation, information and communication technologies - Education practices, innovation, strategies and policy issues.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信