{"title":"基于风险告知法的EDG AOT扩展在核电厂中的应用","authors":"Yunxin Feng, Wei Hu","doi":"10.1155/2023/8435835","DOIUrl":null,"url":null,"abstract":"At present, the allowed outage time (AOT) of an M310 unit emergency diesel generator (EDG) was 3 days, which can be extended to 14 days through replacement of additional diesel units; although it provides a certain online maintenance time, it cannot meet the needs of ten-years overhauls. In order to avoid stopping the reactor for maintenance of NPP due to insufficient of EDG AOT, based on risk-informed method analysis feasibility of extending AOT for EDG to 28 days, we quantitatively calculate the impact of extension of AOT on risk level of nuclear power plants (NPPs). Analysis shows that extension of EDG AOT to 28 days has less impact on NPPs, and safety of NPPs can be further ensured through temporary risk control measures, so the extension of AOT to 28 days is acceptable. By using risk-informed technology to extend AOT for EDG, unnecessary shutdown and maintenance is avoided and the economy of NPPs and flexibility of maintenance work arrangement is greatly improved while ensuring safety, which is of great significance to operation and maintenance of NPPs.","PeriodicalId":21629,"journal":{"name":"Science and Technology of Nuclear Installations","volume":" ","pages":""},"PeriodicalIF":1.0000,"publicationDate":"2023-01-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Application of EDG AOT Extension Based on the Risk-Informed Method in NPPs\",\"authors\":\"Yunxin Feng, Wei Hu\",\"doi\":\"10.1155/2023/8435835\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"At present, the allowed outage time (AOT) of an M310 unit emergency diesel generator (EDG) was 3 days, which can be extended to 14 days through replacement of additional diesel units; although it provides a certain online maintenance time, it cannot meet the needs of ten-years overhauls. In order to avoid stopping the reactor for maintenance of NPP due to insufficient of EDG AOT, based on risk-informed method analysis feasibility of extending AOT for EDG to 28 days, we quantitatively calculate the impact of extension of AOT on risk level of nuclear power plants (NPPs). Analysis shows that extension of EDG AOT to 28 days has less impact on NPPs, and safety of NPPs can be further ensured through temporary risk control measures, so the extension of AOT to 28 days is acceptable. By using risk-informed technology to extend AOT for EDG, unnecessary shutdown and maintenance is avoided and the economy of NPPs and flexibility of maintenance work arrangement is greatly improved while ensuring safety, which is of great significance to operation and maintenance of NPPs.\",\"PeriodicalId\":21629,\"journal\":{\"name\":\"Science and Technology of Nuclear Installations\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":1.0000,\"publicationDate\":\"2023-01-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Science and Technology of Nuclear Installations\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.1155/2023/8435835\",\"RegionNum\":4,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"NUCLEAR SCIENCE & TECHNOLOGY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Science and Technology of Nuclear Installations","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1155/2023/8435835","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"NUCLEAR SCIENCE & TECHNOLOGY","Score":null,"Total":0}
Application of EDG AOT Extension Based on the Risk-Informed Method in NPPs
At present, the allowed outage time (AOT) of an M310 unit emergency diesel generator (EDG) was 3 days, which can be extended to 14 days through replacement of additional diesel units; although it provides a certain online maintenance time, it cannot meet the needs of ten-years overhauls. In order to avoid stopping the reactor for maintenance of NPP due to insufficient of EDG AOT, based on risk-informed method analysis feasibility of extending AOT for EDG to 28 days, we quantitatively calculate the impact of extension of AOT on risk level of nuclear power plants (NPPs). Analysis shows that extension of EDG AOT to 28 days has less impact on NPPs, and safety of NPPs can be further ensured through temporary risk control measures, so the extension of AOT to 28 days is acceptable. By using risk-informed technology to extend AOT for EDG, unnecessary shutdown and maintenance is avoided and the economy of NPPs and flexibility of maintenance work arrangement is greatly improved while ensuring safety, which is of great significance to operation and maintenance of NPPs.
期刊介绍:
Science and Technology of Nuclear Installations is an international scientific journal that aims to make available knowledge on issues related to the nuclear industry and to promote development in the area of nuclear sciences and technologies. The endeavor associated with the establishment and the growth of the journal is expected to lend support to the renaissance of nuclear technology in the world and especially in those countries where nuclear programs have not yet been developed.